Package 1

The documents list work items needing completion across multiple stations. Common items include fixing nomencleature and cable tagging, repairing or replacing damaged equipment, addressing lighting and switch issues, and performing testing of generators, UPS systems, and light levels.

Uploaded by

abhipatel.6381
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views2 pages

Package 1

The documents list work items needing completion across multiple stations. Common items include fixing nomencleature and cable tagging, repairing or replacing damaged equipment, addressing lighting and switch issues, and performing testing of generators, UPS systems, and light levels.

Uploaded by

abhipatel.6381
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

APMC

1 Nomencleature and cable tagging in some of the LT panels pending


2 Door handles of some of the Panels are damaged
3 FPP HMI display not working
4 Cable glands and gas flooding pipe gaps to be fixed
5 Acrylic Sheets to be covered where terminal covers removed
6 CRC for HVAC system installation pending
7 Rubber mat for Battery banks to be provided
8 Battery banks numbering to be done
9 Nomenclature for all switch-socket to be done
10 Light fixture naming to be done
11 Some of the LA pits value measured is above limit
12 FACP earthing to be done
13 All FDA detector caps to be removed
14 Cutouts for cable tray entry in DG room to be sealed
15 Cutouts in Pump room to be sealed
16 FHC numbering for some FHCs is pending
17 DG & UPS load testing to be done
18 Circuit checking of Light fixtures as per requirement to be checked
19 Lux level of station area wise & individual rooms to be checked in Normal & Emergency mode
20 UV coating for HVAC copper pipes to be provided
21 Selector switch (auto and manual mode) to be provided in Ventialation Panel

JIVRAJ

1 Nomencleature and cable tagging in some of the LT panels pending


2 Door handles of some of the Panels are damaged
3 FPP HMI display not working
4 Cable glands and gas flooding pipe gaps to be fixed
5 Acrylic Sheets to be covered where terminal covers removed
6 CRC for HVAC system installation pending
7 Rubber mat for Battery banks to be provided
8 Battery banks numbering to be done
9 Nomenclature for all switch-socket to be done
10 Light fixture naming to be done
11 Some of the LA pits value measured is above limit
12 FACP earthing to be done
13 All FDA detector caps to be removed
14 Cutouts for cable tray entry in DG room to be sealed
15 Cutouts in Pump room to be sealed
16 FHC numbering for some FHCs is pending
17 DG & UPS load testing to be done
18 Circuit checking of Light fixtures as per requirement to be checked
19 Lux level of station area wise & individual rooms to be checked in Normal & Emergency mode
20 UV coating for HVAC copper pipes to be provided
21 Selector switch (auto and manual mode) to be provided in Ventialation Panel
RAJIVNAGAR
1 Gas flooding system for Main Lighting Panel is in Red zone, yet control panel showing system OK
2 All panel fire supression tube entry point glanding to be done.
3 Cable tagging pending.
4 number and identification tags to be provided
5 Extra material from UPS to be removed
6 Rubber mat in UPS room to be provided
7 Fan to be provided in Security room
8 Water leakage from Main and Stand-by pumps
9 Cable entry in LT Panels, extra space to be closed
10 For 4-way and 2-way, all nut bolts to be fixed.
11 Cable tray cutouts in DG room to be sealed
12 Pressure gauge of appropriate scale to be provided in Pump room
13 In Tecchnical and Non-technical rooms some of the light fixtures not working
14 For some light fixtures, wrong switch connectivity is done. To be rectified
15 At street level, few light fixtures are not working
16 Light fixture naming to be done
17 All switch socket nomencleature to be done
18 DG & UPS load testing to be done
19 Circuit checking of Light fixtures as per requirement to be checked
20 Lux level of station area wise & individual rooms to be checked in Normal & Emergency mode
21 UV coating for HVAC copper pipes to be provided
22 Selector switch (auto and manual mode) to be provided in Ventialation Panel
SHREYAS

1 Drain water leakage in ASS room


2 All panel fire supression tube entry point glanding to be done.
3 All Panels Gas flooding system integration with FAS system to be done
4 Cable tagging pending for some Panels
5 Number and identification tags to be provided
6 Lights inside some Panels not working
7 Extra material from UPS to be removed
8 Rubber mat in UPS room to be provided
9 Fan to be provided in Security room
10 Cable entry in LT Panels, extra space to be closed
11 In paid concourse, some of the light fixtures need to be fixed properly
12 For 4-way and 2-way, all nut bolts to be fixed.
13 Cable tray cutouts in DG room to be sealed
14 CRC in SCR room to be installed
15 Pressure gauge of appropriate scale to be provided in Pump room
16 In Tecchnical and Non-technical rooms some of the light fixtures not working
17 For some light fixtures, wrong switch connectivity is done. To be rectified
18 At street level, few light fixtures are not working
19 Resistivity of few LA pits value was exceeding the limit
20 Repeater Panel showing error
21 Light fixture naming to be done
22 All switch socket nomencleature to be done
23 DG & UPS load testing to be done
24 Circuit checking of Light fixtures as per requirement to be checked
25 Lux level of station area wise & individual rooms to be checked in Normal & Emergency mode
26 UV coating for HVAC copper pipes to be provided
27 Selector switch (auto and manual mode) to be provided in Ventialation Panel