Contract Costing
Contract Costing
CONTRACT ACCOUNT
                                              Contract No. ...... for the year ended
                                                                               Contract
                         Pafticularc                            Rs.                         Pafticularc               Rs.
To   Materials (Issued)                                                    By Work in Progress:
To   Wages               (Paid + Payable)                                              -
                                                                                      Work Certified
To Direct Expenses                                                                     -
                                                                                      Work Uncertified
To Indirect Expenses                                                       By balances c/d:
To Sub{ontract Costs                                                                - Materials at Site
To Cost of Etra Work                                                               - Plant (WDV) at site
To Plant (at Cost)
To Notional Profit - balancino fioure
                            Total                                                              Total
To Profit and Loss Account - transfer of                                   By Notional Profit bld
profits recognised during the period
To Reserve Profit - balancino fioure
                            Total                                                              Total
To Work in Progress b/d                                                    By Reserue Profit b/d
To balances b/d
        - Materials at Site
        - Plant at Site
The Contract Account is generally prepared in three segments. They are                 -
1.     First Segment: Initial Comparison of Incomes & Expenditures for the period, leading to Notional Profit.
2.     Second Segmenh Recognition and Transfer of a portion of Notional Profit to P & L Account and the balance carried
       forward as Reserve Profit.
3.     Third Segments Carry forward of balances from one financial period to another. Hence Third Segment of the previous
       period becomes the First Segment of the next financial period. [Note that the Third Segment is not totalled, it is only
       the carry forward of account balances from one period to the other.
                                                                        6.19
Students'Handbook on Cost Accounting and Financial Management
A Contract is estimated to be 80% complete in its first year ol construction as certified. The Contractee pays 75o/o ol Value of
Work Certified, as and when certified and makes the final payment on the completion of contract. The lollowing information is
available for the first year -
.    Cost of Work -in-Progress         Uncertified                                           Rs. 8,000
o     Profit transferred to Profit & Loss A/c at the end of Year I on incomplete          contract        Rs.60,000
.     Cost of work to   date                                                                              Rs.88,000
Calculate the Value of Work-in-Progress Certified and ahe amount of Contract Price.
Solution:
                                                                                                       Cash Re ceived
1. Since contract is 800/o complete, Profit transferred to P & L A/c         ,3= Z x Notional Profit x Work Certified
                              r\
         So, Rs.60,000    =   1x Notional        Profit x75o/o (i.e. Percentage of Cash Received to Work Certifled is        75olo given)
2. Notional Profit = Work Ceftified + Work Uncertified less Cost of work done till date
              Rs.1,20,000 = Work Certified + Rs.8,000        -   Rs.88,000
              On solving the above, we get Work Certified           =   Rs.2rOOrOOO.
3,   o/oaQ€   of Completion =
                                   Work   Ceftified       Rs.2,00,000
                                                                             = 8oo/o. so, contract price =
                                                                                                             Rs'?'-0-g'000
                                                                                                                             = Rs.2rsorooo.
                                   Contract Pr   ice    Contract Pr ice                                         80o/o
Solution:                                                             st
                                   l.ContractAccountforthevearended3l*March
                      Particularc                                    Rs.                       Pafticularc                                     Rs.
To Materials                                                  35,82,600       By Work in Progress A/c
To Direct Wages       Paid                  32,62,700                                                    Rs'71'91'ooo
         Add:                                                                          -work certified (              ))
                   Payable_Z&lZQ                              33,40,820                                        90o/o                  79,90,000
To Direct Expenses Paid 1,68,000                                                       -Work Unceftified                                3,17,000
         Add:      Payable 9,310                                 1,77,310     By Materials - returned to Stores                             L4,84iO
To Planning and Estimation                                       3,50,000     By Materials at Site                                        85,400
To Cost of Plant installed at site                               7,00,000     By WDV of Plant at site                                   6,16,000
To Establishment Expenses                                        2,03,000
To HO expenses - appoftioned                                     2,50,000
To Notional Profit - balancino fioure                        4,19,510
                         Total                              90,23,240                             Total                              90,23,240
                                                                          6.20
                     Particularc                                    Rs.                            Pafticularc                             Rs.
To P & L,Vc - Profit transfer - See Note b                     2,51,706         By Notional Profit b/d                               4,19,5t0
To Reserve Profit c/d - balancinq fiqure                      1,67.804
                        Total                                 4,L9,sLO                               Total                          41191510
To Work-in- Progress b/d (WC+WUC)                             83,o7,ooo         By Reserue Profit b/d                                1,67,804
To WDV of Plant at site b/d                                    6,16,000
To Materials at Site b/d                                         85.400
Notes:
(b) So, Profittrfd to P&L *r= tx Notionat Profit xffiffi =3x Rs.4,1e,510 x-S### = Rs.2,51,706
Modern Constructions Ltd obtained a contract No.B-37 for Rs.40 Lakhs. The following balances and information relates to the
contract for the veat iust ended      -
                           Particulars                                   At the beqinnino ol the vear Rs.           At the end of the vear Rs.
Work-in-Progress:                 Work Certified                                                   9,40,000                         30,00,000
                                  Work Uncertilied                                                   11,200                            32,000
Materials at site                                                                                       8,000                          20,000
Accrued Waqes                                                                                           5,000                           3.000
The Contractee pays 80o/o of Work Certified in cash. You are required to prepare               -
o     Contract Account showing clearly the amount of profits transferred to Profit and Loss Account,
r     Contractee's Account, and
o     Balance Sheet.
                                                                         6.21
 Students'Handbook on Cost Accounting and Financial Management
               __!!!P!!!qel---__--i-                 Ks'
                                                         l------.----          }{ssqq                      - - - ---1
                                                                                                     ."-- --]-,--_1s'                                I
Ii
 i'L-
                 Accrueci
               " Accruecj
             Woges
             Wages
                                                         i
                                                         ']
                                                          Iii, ----*
                                                                    :,000
                                                                    3,000
                                                                          Ii
                                                                             ^--. Contractee's
                                                                    . ^^^ LLessr
                                                                          i t-essr
                                                                                   - -.---,r:rr-::1^.
                                                                                   Net
                                                                                   lvet Vatue
                                                                                   wut Value
                                                                                                       balance :,::'::'fli
                                                                                               Account *-,^^-^
                                                                                                          wrP
                                                                                                          VyIP
                                                                                                 contract VYIP
                                                                                        vatue of Contract
                                                                                                               l__(24,00pq8_]
                                                                                                               i__G1,!qpqQ
                                                                                                               :- Z,5Z,AZI
                                                                                                                   2,52,6n                           i
t_ -- +
"
                                                                          6.22
                                                                                                                         Contract Costinq
     WI{ 1:
      Item              Material Issued                 Labour                                 OH                    Plant at Cost
      Ratio                      5                         4                                   2                              4
     Amount        (Rs.5,60,000 x 514) =         (Rs.5,60,000 x 414) =              (Rs.5,60,000 x 214) =         Rs.5,60,000 Computed
                        Rs.7.00.000                   Rs.5.60.000                        Rs.2.80.000             usino Deorn Rate & WDV
                                                               2. WIP Account
                            Particularc                         Rs.                            Pafticularc                              Rs.
     To Contract Ay'c   -   Work Certified                1g,oo,ooo
     To Contract A,/c   -   Work Uncertified               1.40.000      By balance c/d                                           19.40.OO0
                              Total                     19,40,000                                   Total                         19,40.000
                                                        3. Contracteet Account
                         Pafticularc                              Rs.                          Particulars                              Rs.
     To balance c/d                                     16,2o,OOO        Bv Bank (oiven)                                          16,20,000
20
Students'Handbook on Cost Accountinq and Financial Management
Prepare the Contract Account for the financial year ended 31st December and show the amount                          of profit or loss to   be
recognised on this contract. Also show the summary entries in the Balance Sheet.
Solution:
Note:    In this question, cost of work uncertified is not given. However, total work done is 213'd or 66.670/o, while extent of
         certification is 50o/o. Hence balance !6.670/o constitutes work done but not certified. This should be computed on
         proportionate cost basis in the following manner.
      So, Proportionate Cost     of   t6.67o/owork done (i.e. Uncertified Work) = Rs.10,49,000,                        Rs.2,62,250.   .
                                                                                                             YOUr,o=
(c)   Percentage of Compleuon         =   *q!9P             =5oo/o(given)
                                          Contract Pr ice
                                                                      6.24
                                                                                                                                   Contract Costing
                                                                                                                                                  i,:::l,::,
                                                                                                                                                  on    1st
October. On 31st December. when their accounts were made up, the                          was as follows    -
                    Contract                                                          1                               2                                   3
Contract Price                                                                2,00,000                          1,35,000                        1,50,000
Expenditure:        Materials                                                  39,400                            29,000                          10,000
                    Wages                                                      63,250                            56,200                            7,000
                    General Expenses                                            2,000                             1,400                               500
                    Plant installed                                            10,000                             8,000                            6,000
Materials on hand                                                               2,000                             2,000                            1,000
Wages accued                                                                     1,725                            1,900                               800
General Expenses accrued                                                            300                             200                               100
Work Certified                                                                1,20,000                           80,000                          19,000
Cash Received in respect thereof                                               90,000                            60,000                          13,500
Work linished but uncertified                                                    3,000                            4.000                            1,050
Contract t had been negotiated two years back with an escalation clause providing that should Material Prices and Wage Rates
increase by more than 2.5olo, the Contragleg would increase the Contract Price by 207o ol the rise in the cost of materials and
40% of the rise in the wage rates beyond 2.5o/oin each case.
It is agreed that since the signing of the agreement the Material Prices had gone up by 107o and Wage Rates by 15%, the value
of Work Certified does not take into account the etfect of the escalation clause.
The Plant was installed on the dates of the contracts and depreciation is taken at                  10o/o   per annum. Prepare the respective
accounts in the Contract Ledger and give suitable entries in the Company's Balance Sheet.
Solution:
                                                    1. Computation of Escalation Claim
            Note: Escalation Clause         is applicable only for Contract No.1. The escalation claim is computed as under               -
                                                                 (a) Materials
                                            No claim                 Escalation Claim = 2oolo of this differcnce
                                                                       6.25
Students'Handbook on Cost Accounting and Financial Management
                                                    2.                      of                        on Plant used
       Contract Number                                        1                                              2                                       3
(a) Value of Plant (Rs.)                           Rs.10,000                                           Rs.8,000                                 Rs.6,000
(b) Period of use                      ls   Jan to 31* Dec = 12 mths                      ls   July to 31* Dec. = 6 mths            ls   oct to 31st Dec. = 3 mths
(c) Depreciation at      100/o p.a                        Rs.1,000                                     Rs.40O                                    Rs.15O
                                                                      4. Profit
               Contract Number                                                                          I                              2                              3
(a) Notional Profit las oer Contract fucl                                                          20.660                        (3,000)                         1,500
(b)   o/o                     Work Certified
            of completion =                                                                          600/o                         59o/o                         LZo/o
                              Contract Pr ice
                                                                                                                     (3,000) Loss fully               Less than 25olo
(c) Profit Recognised                                             Z   x   20,660   x   75o/o= 10,330
                                                                                                                            written off        complete, so ignored.
                                                                                   6.26
                                                                                                                                            Contract Costing
Solution:
                        Particularc                        Year 1                                          Year 2                                    Year 3
1. Income: (a) Work Certified                                   Nil                                       3,00,000                                 8,00,000
          (b) Work Uncertified                              s0,000                                          10,000                                   20.000
                       Total Income                        50,000                                        3,10,000                                 8,20,000
2. Cost of work till date                                   s0.000                                        2,30,000                                 6,60,000
3. Notional Profit (1 - 2)                                     Nit                                         80,000                                 1,60,000
      o/o
                                  Work Ceftified                Nil                       Rs.3,00,000                                 Rs.8,00,000        g0o/o
4.          of Completion =                                                                                = 30o/o                                   =
                                  Contract    Pr ice                                     Rs.10,00,000                                Rs.10,00,000
5. Transfer to P&L A/c                                          Nil     ! xNotional *r          cash Received        l   xNotional Pftx
                                                                                                                                            Cash Re ceived
   {based on Notional Profit formula)                                   3                       Work Certified       3                      Work Certified
(Note: Since question specifies
Estimated Total Profit     20o/o, i.e. =                                =   !x    ns.8o.ooo     * Rs.3,00,000
                                                                                                  Rs'2'75'ooo                           Rs'7'50'ooo
                                                                                                                         =33x 1.6o.o00x Rs.8,00,000
Rs.2,00,000, ETP can also be used for
                                                                            3
Profit Recoqnition.)                                                                                 = Rs.2LM4                               = Rs.1r00r0OO
(d) ErP x
                          Cost till   date x- Cash Re ceived                             = 2.00 x
                                                                                                     2'30 x2'75
                                                                                                                                   = 2.oo x
                                                                                                                                              6'60   \   2'75
                   Estimated Total         Costs       Work Certified                                8.00     3.00                            8.00 3.00
                                                                                                     = Rs.52,708                             = Rs.1,51,25O
Since the above amounts are higher than the profits computed based on Notional Profiits, on prudence                                 /   conservatism basis,
the amounts shown at Point 5 above shall be transferred to P&L A/c.
Solution:
                                                          WorkCeftified          Rs.27,50,000
1. Percentage of Completion                              -Contract Pr   ice      Rs.32,50,000                                                    = 84.620/o
                                                                                  5.27
Students'Handbook on Cost Accounting and Financial Management
Paramount Engineers are engaged in construction and erection of a bridge under a long-term contract. The cost incurred upto
31st Mareh was as under:
Fabrication  Costs:          Direct Materials                                         Rs.280 Lakhs
                             Direct Labour                                            Rs. 100 Lakhs
                             Overheads                                                Rs. 60 Lakhs
          Total Fabrication Costs                                                     Rs. 440 Lakhs
Add:      Erection Costs                                                              Rs. 110 Lakhs
          Total Costs to date                                                         Rs.550 Lakhs
The Contract Price is Rs.11 Crores and the cash received on account tillSlst March was Rs.6 Crores. Work Certified till                           g13r
March was however Rs.6.80 Crores.
A technical estimate of the contract indicate the following degree of completion of work               -
Fabrication: Direct Material-70o/o, Direct Labour and Overheads - 600/o. Erection - 40%.
Estimate the profit that could be taken to Profit & Loss A/c against this partly completed contract as at 31sr March.
                                                                                                                                  1oo'oo
                                            Labour                                                 100.00
                                                                                                                                   600/o
                                                                                                                                           = 166.67
                                                                                                                                   60'00
                                            Overheads                                               60.00
                                                                                                                                   600/o
                                                                                                                                           -   1oo.oo
                                                                                                                                  110'oo
                        Erection                                                                   110.00
                                                                                                                                   40o/o
                                                                                                                                           =   27s.oo
ol x     Notional Profit x
                              Cash Re ceived
                              Work Certified
                                                                                                           2
                                                                                                           3
                                                                                                               x   13o.oo    x 600'00 = 7G.47
                                                                                                                               680,00
Obseruation: Least of the above is Rs.76.47 Lakhs (6m formula listed above). Hence, Profit recognised on prudence
basis is Ps.76.47 Lakhs. The balance Reserve Profit is (Rs.130.00 - Ps.76.47) = Rs.53.53 Lakhs.
As soon as materials are delivered to the site, they are charged to the Contract Account. A record is also kept ol materials as
they are actually used on the contract. Periodically a stock check is made and any discrepancy between Book Stock and
Physical Stock is transferred to a g.eneral "Contract Material Discrepancy" Account. This is absorbed back to each Contract,
cunently at the rate of 0.5% of Materials booked. The stock check at the year+nd revealed a Stock Shortage of Rs.5,000.
In addition to Direct Charges listed above, general 0H are charged to contracts at 5olo of value of Work Certified. General 0H of
Hs.l5,000 had been absorbed into the cost of work completed at the beginning of the year. lt has been estimated that further
costs to complete the contract will be Rs.2,20,0fi1. This estimate included the cost ol materials on site at the end of the year
lust finished and also a provision for rectification.
Required:
1. Determine the profitability of the above contract and recommend how much profit (to the nearest Rs.000s) should be taken
   lor the year just ended.
2. State how your recommendation in (1) would be atfected if the Contract Price was Rs.40 Lakhs (rather than Rs:25 Lakhs)
    and if no estimate has been made of costs to completion. Assume Retention Money = 2trlo.
                                                                       6.29
                                        2.                of Profit on                   basis            Rs.OOOs
                                                  Work Ceftified _22,00
 A. Percentage of Completion
                                                  Contract Pr ice  25,00                                                                                    = 88o/o
 B. Current Year Profit                       = as per Contract A,/c above                                                                                       4.67
 C. Cost till date                            = as per Conkact Iy'c above
                                              = WC + WUC - Notional Profit = 22,00 + 40               -   4,61                                                  17.73
                                                       Contract Price                                                 25,00
 D. Estimated Total Profit (ETp)              Less:    Estimated Total Costs (a) Cost till date                      (17,73)
                                                                (b) Fufther Costs      qiven                          (2.00)                                     5,07
 E. Profit to be transferred to p&L             Least
                                              =       of the followinS (a) to (c)                                                                               4,tl
 (a) Estimated Total Profit x Work Certified
                                  Contract
                                  Cost"r'tce
                                        till date
                                                                            = 5,07
                                                                                     "ffi           = 4,46
                                                                     6.30
a
    W{lti..**
    RST Construction Ltd commenced a contract on lst April 2$g. the
                                                                                                                                .:.'.,, ":.:-.,,";   :...:,frli:i$l#
                                                                                            torai-Cd;iraci",wa-Ji6;iiiig"2iJi5.""iifi;"iitdiJ& to
    estlmate the Total Profit on the contract and to take to the credit of P & L Account that proportion of estimateO profft
                                                                                                                              on castr
    basis, which the work completed bore to the total contract. Actuat expenditurc for ure peri&i rJapiu
                                                                                                             aioiilo ifi-r,ii,iir ioro
    and estimated expenditule for la April 2010 to 3$ september 2010 are qiven below
                                  Particulars                                  lst Apr 2009 to 31* Mar 2010                     1* Apr 2010to         illh   Sep 2010
                                                                                                  (Actuals) (                                  (Estimated) (Hs.)
    ilateriaF lssued                                                                                    7,76,250                                             12,99,375
    l-abour:                  Paid                                                                      5,17,500                                              6,19,750
                              Prepaid                                                                     37,500
    Plant purchased
                              Outstanding                                                                 12,500                                                 5,d
                                                                                                        4,00,000
    Plant Returns to Store (Historica! Cost)                                    (0n 30u Sept 2(X)9) 1.00.000                   (On 30tr Sept 201013.00.000
                                                                                6.31
Students'Handbook on Cost Accounting and Financlal Management
                         Particulars                               lsr Aor 2009 to 31sr Mar 2010                   1st   Aor 2010 to 3@ Sep 2010
Expenses: Paid                                                                               2,25,000                                     3,75,000
                        Outstanding                                                            25,000                                       10,000
                        Prepaid                                                                15,000
ItUork Certified                                                                            22,50,000                                         trl
Work Uncertified                                                                               25,000
Cash received                                                                               19,75,000
Material at site                                                                               82.500                                       42.500
@depreciational25%onWDVMethod.TheContractislikelytobecompletedon30tttSep2010.
Required: Prepare the Contract Account. Determine the profit on the contract for the year 200$'2010 on prudent basis, which
has to be credited to P & L Account.
Solution:                                   1. Statement   of                 Tr
         Pafticularc                                                  Till date                    Additional                               Total
A, Income:
   Work Certified                                           Given = 22,50,000                                                  Given   = 49,21,875
   Work Uncertified                                          Given  =  25,000
             Total                                                  22,75,OOO                                                          49,21,875
B. Expenditure:
   Materials    (WN a)                                                  6,93,750                      13,39,375                          20,33,L25
   Labour ,(WN b)                                                       4,92,500                       6,49,500                          tL,42,000
   Expenses (WN c)                                                      2,35,000                        3,75,000                          5,10,000
   Deoreciation (WN d)                                                    87.500                          28.125                          1.15.625
                   Total                                            15,08,750                      23,92,OOO                           34,OO,75O
C. Profit (A   -   B)                                                7,66,250                                                          10,21rtAs
                                                                Notional Profit                                            Estimated Total Proft
D. Profit transfer       to P&L A/c      (based on formula specified in the question)
                              work certified  . Work Et:Y"g                 E'2?80'009 , B!92!499 Rs.3,8e,o(x!
Estimatedrotatprofitx
                              Contract    Price i?tl        =Rs.10,21,12s
                                                     Certified            " Rs.49,21,875 Rs.22,50,000 =
                                            1$ Aor 2OO9 to 31s Mar 2010
                                    Opening Stock+Issues - Closing Stock =                      Opening Stock + Issues - Closing Stock =
                                        Nil + 7,76,250 - 82,500 = 6,93,750                          500 + 12,99,375        -
                                      Paid + O/S at end - Prepaid at i:nd =            Prepaid of previous period + paid during the.year'+
                                    5,17,500 + 12,500 - 37,500 = 4,92,500                                  O/S at end - O/s at beginning =
                                         Paid + O/S at end - PrePaid at end =          Prepaid of previous period + paid during the year +
                                      2,25,000 + 25,000 - 15,000 = 2,35,000                               O/S at end - O/s at beginning =
                                                                                                             000+10,000-25,000=3
                                       3,00,000 x25o/ol,l2 rnontl^rs = 75,000             (3,00,000   -   75,000) x 25o/o x 5 months = 28,125
                                        1,00,000 x25o/ox 6 months = 12,500
                                                                     6.32
                                                                                                                                                :;:ff,   I.,i
AKP Builders Ltd commenced a contract on 1.r April zoog. ffre Total contrqgl_rryas tor Rs,5sg,000. Actual rrf.noitrr.          til;             f*
         stApril 2008 to 31st March 2009 and estimated erpenditure for lst
                                                                           April 2009 to 31st December 200g are qiven below-
                    Particulars                                     2008-2009 (Actual)          2009-2010 (9 months) Gstimated)
Material issued                                                                Rs.90,000                               Rs.8!i,750
Labour: Paid                                                                                     Rs.75,000                                   Rs.87,325
            Outstanding at the end                                                                Rs.6,250                                    Rs.8,300
Plant                                                                                            Rs.25,000
Sundry Expenses:Paid                                                                              Rs.7,250                                    Rs.6,875
                 Prepaid at the end                                                                Rs.625
Establishment Charqes                                                                            Rs.14.625
A part of the material was unsuitable and was sold for Rs.18,125 (Cost being Rs.15,000) and a part of PIant was soapped and
disposed of for Rs.2,875. The value ol Plant at Site on 31"t March 2009 was Rs.7,750 and value of Material at Site was Hs.4,250.
Cash received on account to date was Rs.l,75,000, representing 80o/o of the Work Certified. The cost of Work Uncertified was
valued at Hs.27,375.
The Contractor estimated further expenditure that would be incurred in completion of the conlract as under
                                                                                                                                -
o   The Contract would be completed by 31st December 200g.
o      A further sum of Rs'31,250 would have to be spent on the Plant and the Residual Value                       of the Plant on the completion of
       the contract would be Rs.3,750.
.      Establishment Charges would cost the same amount per month as in the previous year.
.      Rs.10,800 would be sutficient to provide for contingencies.
Prepare Contract Account and calculate Estimated Total Profit on this contract. Prolit transferable to Profit and Loss Account
is to be calculated by reducing Estimated Profit in proportion of Work Certified and Contract price.
(d) Depreciation
                                                           = 7,250     - 625 = 6,625                                                 ill?,5:";[
                                        Cost      -   Disposed     -   Residual Value               Opening Value + Purchases - Residual Value
                                     = 25,000         -   2,875   - 7,750 = 14,375                          = 7,750 + 31,250 - 3,750 = 35,250
                                                                               6.33
Students'Handbook on Cost Accounting and Financial Management
                                         2,                         for the
                   Particularc                                         Rs.                    Pafticularc                                     Rs.
To Material Issued                                                  90,000     By Work in Progress
To  Labour         (as per WN above)                                81,250              -Work Certified                               2,L8,750
To Expenses (as per WN above)                                         6,625             -Work Unceftified                               27,375
To Plant at Cost                                                    25,000     By Bank - Sale Value of Plant sold                        2,875
To Establishment Charges                                            L4,625     By Bank - Sale Value of Materials sold                   18,125
To P&L  Iy'c       - Pft on Sale of Matls.                            3,125                      -
                                                                               By balance c/d Materials at Site                          4,250
To Notional Profit                                                  58.500     By balance c/d - Plant at Site                            7,750
                      Total                                      2,79,L25                            Total                          2,79,L25
To Profit & Loss A/c - Transfer                                      29,960    By Notional Profit b/d                                   58,500
To Reserue Profit dd                                                 28.540
                      Total                                         58,50O                           Total                             58,500
To WIP bld (2,18,750 + 27,375)                                     2,46,125
                                                              By Reserue Profit b/d                                                     28,540
To Materials at sitb b/d                                              4,250
To Plant at Site b/d                                                  7.750
Note: Plant scrapped & disposed off for Rs.2,875 is assumed to be at cost. So, Loss / Gain thereon is ignored.
                           oe{€bil Fofr -           M
                                               ftcognfrion - Disp@ d ilateriab afr a Loes
         Dick and Harry, undertook a contract for construction of a cycle shed for a sum of Rs.l,fl),fi[ . The work was started
on 1* April, 20X1 and the following expenses were incurred:
    Plant   -   Rs.S,fi)O, Stores   -   Rs.l8,fiXt, Wages   -   Rs.16,250, Sundry Expenses   -   Rs.l ,325, Establishment Charges: Rs.2,925
Materials costing Rs.3,0(X) were found to be unsuitable for the contract and werc immediately sold for Rs.2,625.
The vatue   ol Plant on 31tt March 20)P, was Rs.1,550 and of Stores Rs.850. Cash received on account was Rs.35,{X}0
reprcsenting 807o of the work certified. The work uncertified was valued at Rs.5,475 and this was certified later for Rs.6,250.
The Fhm decided to estimate the further expenditure on completion of the contract and tO take to the credit of P&L A/c for
20X1-X2, that portion of the total estimated profit, which the work certified, bore to the total contract price.
Preparc Contract, Stores and Plant Account for the year ended 31st March 20X2 and also show your calculations for the amount
credited to Profit & Loss Account lor the year.
                                                                          6.34
                          Pafticularc                                                      Till date       Additional                            Total
             Sub--Total Cost excluding Contingencies                                         38,100                46,6t9                       84,719
 Add:        Contingencies (2.5o/o of Rs.84,719)                                                                    2,118                         2,t18
                             Total                                                          38,100                 48,737                       86,8,37
 C. Profit (A    -   B)                                                                     tL,125                                              13,163
                                                                                    NotionalProfit                              Estimated Total Profit
 D. Profit transfer        to P&L A/c    (based on formula specifled in tne question)
                                         rotatprofitx                                       ,.
                             Estimated
                                                        ##F                   =Rs.13,163
                                                                                                 ffi               = Rs.5,75e
 Notes:
          Particulars                                        Incurred till date                                                             Additional
 (a) Materials                                      Issued - Sold - Closing Stock                                     Opening Stock + Purchases
                                              =   18,000 - 3,000 - 850 = 14.150                                        = 850 + 17,150 = 18.000
 (b) Establishment Charoes                        Rs,2,925 (qiven) for 12 months                        Rs.2,925 x 9112 = Rs.2,194 for 9 months
 (c) Depreciation                                       Cost Less Residual Value                       Opg Balance + Purchases - Residual Value
                                                             -
                                                      = 5,000 1,550 = Rs.3,450                                 = 1,550 + 6,250 - 750 = Rs.7,050
                                        2. Contract Account      for               ended 31                  20x2
                          Particulars                               Rs.                            Particularc                                      Rs.
To Materials Issued                                              19,000       By   Work-in-Progress -      Work Ceftified                        43,750
To Wages                                                         76,250                                  - Work Uncertified                       5,475
To Sundry Expenses                                                1,325       By balances    c/d         - Plant                                  1,550
To Establishment Charges                                          2,925                                  - Materials                                8s0
To Plant                                                          5,000       By Bank - Sale Value of Material Sold                               2,625
To Notional Pr6nt c/O                                         11,125          By P & L (Loss on Materials) (3.000 - 2.625\                          375
                            Total                             51,625                                     Total                                  5L,625
To P&L Ay'c - Profit transfer as per WN 1 above                   5,759       By Notional Profit c/d                                             11,125
To Reserve Profit c/d - balancino fiqure                         5.366
                            Total                             tL,L25                                     Total                                  11,125
To WIP b/d (WC + WUC) (43,750 + 5,475)                           49,225       By Reserve Profit b/d                                               5,356
To Plant at Site b/d                                              1,550
To Materials at site b/d                                            8s0
Note:LossonSaleofMaterialwillbedebitedseparatelytoP&
          Rs.6,250 will be considered in the subsequent period,s accounts.
                                                                                                                                              l::.il*
  st March
                                                                                                                     J   uncoiipleteo   ;;;ii.Li;'iJ'ffi
31rt
                     Particulars / Contract No.                                      723                    726                  729                731
TotalContract Price                                                                B.2A                   14.4(l               10.08              28.80
Estimated TotalCosts on the Contract                                               20.50                  11.52                12.60              21.60
 Expenses for the year ended 31st March
 Direct Materials                                                      5.22              1.80              1.98            0.80
 Direct Wages                                                          2.32              4.32             3.90             2.16
 Overheads (excluding Depreciation)                                    1.06              2.60             2.62             1.05
 Profit Reserve as on lst April(beginning)                             1.50
 Plant issued at Cost during the year                                  s.00              3.50             2.75             3.00
 Materials at Site as at 1s April (beginning)                          0.75
 Materials at Site as at 31st March (end)                              0.45                                0.;                  0.;                0.;
Value of Work Certified on 1st April (beginning)                       4.75
Work Certified during the year                                       12.76             13.26              7.56             4.32
Work Uncertified as on 31st March (end)                               0.84              0.24              0.14             0.18
Progress Payments received durinq the vear                            9.57              9.00              5.75             3.60
Depreciation atzcflh per ann
remaining contracts were started in the la week of April this year. Determine the Profit / Loss in respect
                                                                                                            ol each contraA for
the year ended 31st March. Also prepare the Contract Account.
                                                                       6.35
Students'Handbook on Cost Accounting and Financial Management
Solution:                            1. Contract Account for the vear ended 31o March (in Rs.Lakhs
  Pafticularc               723          726          729     731    Total        Particulars             723      726       729      73L     Total
To WIP b/d                  4.75                                       4.75    By Reserue b/d             1.50                                  1.50
To Materials b/d            0.75                                       0.75    By WIP a/c
To Materials                5.22         1.8;         1.9;    0.8;     9.80    -Work Certified           17.5r    13.26      7.56     4.32     42.65
To Wages                    2.32         4.32         3.90    2.L6    12.70    -Wort    Uncertified       0.84    0.24       0.14     0.18      1.40
To OH                       1.06         2.60         2.62    1.05     7.33    By balance c/d
To Depreciation              1.00        0.70         0.55    0.60     2.85    *Materials                 0.45     0.20      0.08     0.0s      0.78
 on Plant at'20o/o
To Notional Pft {d          5.20         4.28                          9.48    Bv Loss c/d                                   t.27     0.06      1.33
        Total              20.30       L3.70      9.05        4.61   47.66             Total            20.30    L3.70      9.05      4.61    47.66
To Loss b/d                                           t.27_   0.06     1.33    By Notional                5.20     4.28                         9.48
To P&L - Pft tfr             1.3;        1.5;                          2.86.           Profit b/d
To Reserve Pft dd           3.90         2.72                          6.62    By P&L - Loss tfr                             2.52     0.05      2.58
To Provision c/d                                      t.25             r.25
        Total               5.20        4.24          2.s2    0.06   12.06             Total              5.20    4.24      2.52      0.06    12.06
Note:
o     Profit/ (Loss) to be transferred to P&L A/c is determined on prudence basis, as per WN 2 below.
.     In respect of profit-making contracts, the balance profit is called "Reserve Profit', while in respect of loss-making
      contracts, the balance is called "Provision against Future Losses" (or) "Reserve for Contingencies". Both Reserve and
      Provision constitute Credit balances, and are treated in the same way while disclosing WIP in the Balance Sheet.
.     In Contract 729, Current Loss is 1.27 whereas the Worst Loss of 2.52 is to be provided for. The balance 1.25 constitutes
      provision for foreseen losses and is hence carried forward as "Provision" (not Reserve Profit).
o     Total Column is only for information value.
                              2.                       of               on
                  Contract Number                                               723                     726                 729                 73L
(a) Contract Price                                                             23.20                   74.40               10.08               28.80
(b) Work Certified (cumulative)                                                t7.5t                   13.26                7.56                4.32
For Contract No.723 and 726. least of the followinq is transferred to P&L A,/c (on                               conseruatism
                              Formula                                                          Contract 723                         Contract 726
                Work Certified                                                              xt7'51 = 2,oq
(a) ETP x                                                                          2.70                                       2.88xL3'26 =2.6s
                Contract   Pr ice                                                            23.20                                 L4.40
(b) ETP x
                Work   Certified
                               x- Cash Re ceived                          2.70x17'51        x 9'57 =1.53           2.88x13'26x
                                                                                                                                      9'oo
                Contract Pr   ice        Work Ceftified                           23.20       t2.76                         t4.40     13.26
                                                                                                                                              =t.80
                    Cost till date                                                                                                    9'22
(c) ETP x                                                                          2.70x13'15 =t.73                           2.88x           =2,3o
               Estimated Total Costs                                                           20.50                                  11.52
(d) ETP x
                     Cost till     date x-Cash Re ceived                  2.70x13'15 x 9'57 =1.30                  z.BB, 9'22 x 9'oo = 1.56
                Estimated Total     Costs Work Ceftified                       20.50 12.76                              11.52 L3.26
                            Work Ceftified
(e) Notional Profit x                                                              5.2oxt7'51 =g,g2                          4.28 x13,26 _ 3.g4
                            Contract     Pr ice                                                23.20                                  t4.40
ff)        NotionalProfit x
                                    Cash Re ceived                             ?x5.20x9'57 =2.60                      ?xc.28x 9'oo =4.35
      1"                           Work Certified                              3      t2.76                           3       13.26
Note: In the above formulae -
. In Formula (c) and (d), Cost till date = WIP (WC + WUC) less Notional Profit, as per Contract A/c.
                                                                           6.36
                                                                                                                    Contract Costinq
.    For calculating percentage of completion, i.".                        cumulative Work Certified should be mnsidered (i.e.
                                                          #m,
     including     Opening        balance   of work   certified.). However,     for   considering   the   percentage     of    payment,
     .i.e. Cash Re ceived     Cash Received during that year should be compared with Work Ceftified during
        W;rk-Grtitu;,                                                                                                that year      (i.e.
The agreed retention is 10% of the Value of Work Certified by the Contractee's Architect. Contract C is scheduled to be handed
over to the Contractee in the near future. lt is estimated that Rs.3,05,000 shall be needed to be spent in addition to what has
been tabulated above, to complete this particular contract. This amount includes an altowance                for plant   depreciation,
construction services and for contingencies.
Prepare Contract A/cs for each of the three contracts and recommend how much Profit / Loss should be recognized for the year.
                                                                 6.37
Students'Handbook on Cost Accounting and Financial Management
I{ote:   Since no profit has been previously recognized on Contract A, Value of Work Certified till last Y€or = Cost of Rs3,18
         as given in the Question. For Contract C, value of Work Certified = C,ost of Work Certified + Profit recognized last
         Y€or=8,!4+35=8,49.
                     2.                  of                 for                      of ProfIt or      on ConfacB
                         Pafticularc                                                       A                          B                              c
                                                                          2'oo                      8'60                          21'oo
A. Percentage of Completion =
                                  Work Certified
                                                                                 -   11.360lo               -   57.9to/o
                                                                                                                                  24,20
                                                                                                                                          -   86.770/o
                                  Contract Pr ice                      17,60                        14,85
B. Current Year Profit (as per Contract A/c)                                              L7                Loss (55)                             4,LL
                                                                                          Nit                     (ss)       Based on Prudence,
C. Profit to be transfened to P&L                                    (<   25o/o complete)            Cunent Loss                    shown below.
Estimated Total Costs = Costs till date (as above) + Fufther Costs to be incurred = L7,09 + 3,05 20,14
Estimated Total Profit                     = Contract Price (less) Estimated Total C.osts = 24,20 -20,L4                                           4,06
Profit to be transferred to P&L            = Least of the followins (a) to (f)                                                                    3.10
However, this profit is calculated on the basis of the cumulative Cost incurred till the end of the current year' Hence Profit to
be transferred thib year = 3,10 - 35 Profit already taken last yedr = 2,75.
5.38