0% found this document useful (0 votes)
56 views1 page

Quality Checklist For Site Works: 01 Setting Out Task A-Surveying Works

The document is a quality checklist for site works focusing on surveying tasks related to construction projects. It includes a series of questions to verify the availability of survey plans, establishment of coordination points, compliance with local authority setbacks, and the correct location of structural elements. The checklist also provides space for corrective actions and comments if any issues are identified.

Uploaded by

adnan-651358
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
56 views1 page

Quality Checklist For Site Works: 01 Setting Out Task A-Surveying Works

The document is a quality checklist for site works focusing on surveying tasks related to construction projects. It includes a series of questions to verify the availability of survey plans, establishment of coordination points, compliance with local authority setbacks, and the correct location of structural elements. The checklist also provides space for corrective actions and comments if any issues are identified.

Uploaded by

adnan-651358
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

QUALITY CHECKLIST FOR SITE WORKS

01 SETTING OUT TASK


A- SURVEYING WORKS

ARCHITECTURAL STRUCTURL SERVICES & UTILITY


INTERIOR

Building Unit Designation Name: Project ID:


Name of the Contractor Group: Location:
Construction Drawing Ref. No.: Quantity:

CL : 01-A
Sl.No. Description YES NO NA
1 Is contour/ survey plan available?
2 Establishment of Co-ordination points, MAIN GRID LINES, CENTRE LINES in both
directions, block levels, spot level etc. Is it as per Drawings?
3 Check for set back are they as per the norms of local authority approval drawing?
4 Check whether there is any variation in the actual marking and whether it is recorded/
reported?
5 LOCATION of INDIVIDUAL STRUCTURAL ELEMENTS like Column footings, columns,
location of pile, etc.,
Are they as per Drawings?
CORRECTIVE ACTION PROPOSED- Item wise.
If 'No' is marked, please specify reasons and thereafter corrective action proposed.
(Add additional sheets, if necessary)

Comments:

Contractor's Rep.: Client Rep.: Lines & Visions Int. Rep.: