0% found this document useful (0 votes)
34 views1 page

DAP Meeting Points

Uploaded by

Kartik Agrawal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
34 views1 page

DAP Meeting Points

Uploaded by

Kartik Agrawal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

DAP Discussion points

Date:- 31st May 2024


Sr. No. Points to discussed Responsbility Remarks
1 Machine mounting pneumatic slide stroke 200mm required PCPL Yes we will do
Instead of manual toggle clamp used pneumatic type toggle
2 clamp PCPL OK
3 Software discussion meeting need to be schedule. PCPL/ Mahindra Please confirm then we will plan accordingly
4 One new varient added by mahindra Mahindra Model shared by Mahindra
For Cylinder head, 2 separate fixtures to be considered like crank
case machine. Also, top marking height to be matched for both
5 fixtures PCPL Yes we will do

For crack case, in single cycle both parts to be marked based on


presence sensor. If we put only one model, then same to be
marked based on presence sensor and other side part marking
6 will be skipped as no presence confirmation PCPL Ok
Different log in password to be provided as operator, supervisors
7 and admin. PCPL OK
After part marking, we needs to scan for confirmation. For this
scanning initially we will scan 100%. After that we will decide the
HMI not in PCPL scope, we will provide in software.
frequency through HMI. Without scanning confirmation next cycle
8 should not start. PCPL/ Mahindra
As per process, part should be 100% ok for scanning. We are
doing 2D marking on casting face. Same is confirmed by your
9 team. ( no machined face). PCPL Ok
3 nos of spare model programming should be made available for
10 future expansion. PCPL Ok
For head one new model will be marked. Model will be shared by Once we received model then we will check &
11 today evening. Mahindra confirm
12 Machine colour to be confirmed by MTWD team. Mahindra Confirm by Mahindra
13 Revised DAP to be shared ASAP PCPL We will submit shortly
14 Need sample component Mahindra Provide by mahindra