DAP Discussion points
Date:- 31st May 2024
Sr. No.                      Points to discussed                                       Responsbility                      Remarks
   1      Machine mounting pneumatic slide stroke 200mm required                PCPL                   Yes we will do
          Instead of manual toggle clamp used pneumatic type toggle
   2      clamp                                                                 PCPL                   OK
   3      Software discussion meeting need to be schedule.                      PCPL/ Mahindra         Please confirm then we will plan accordingly
   4      One new varient added by mahindra                                     Mahindra               Model shared by Mahindra
          For Cylinder head, 2 separate fixtures to be considered like crank
          case machine. Also, top marking height to be matched for both
   5      fixtures                                                              PCPL                   Yes we will do
          For crack case, in single cycle both parts to be marked based on
          presence sensor. If we put only one model, then same to be
          marked based on presence sensor and other side part marking
   6      will be skipped as no presence confirmation                           PCPL                   Ok
          Different log in password to be provided as operator, supervisors
   7      and admin.                                                            PCPL                   OK
           After part marking, we needs to scan for confirmation. For this
          scanning initially we will scan 100%. After that we will decide the
                                                                                                       HMI not in PCPL scope, we will provide in software.
          frequency through HMI. Without scanning confirmation next cycle
   8      should not start.                                                     PCPL/ Mahindra
          As per process, part should be 100% ok for scanning. We are
          doing 2D marking on casting face. Same is confirmed by your
   9      team. ( no machined face).                                            PCPL                   Ok
          3 nos of spare model programming should be made available for
  10      future expansion.                                                     PCPL                   Ok
           For head one new model will be marked. Model will be shared by                              Once we received model then we will check &
  11      today evening.                                                        Mahindra               confirm
  12      Machine colour to be confirmed by MTWD team.                          Mahindra               Confirm by Mahindra
  13      Revised DAP to be shared ASAP                                         PCPL                   We will submit shortly
  14      Need sample component                                                 Mahindra               Provide by mahindra