Permit To Work
Permit To Work
Revision history
Approval Authority:
Summary
The Permit to Work system is used to control and manage specific hazards during the
course of the work. The purpose of such a system is to achieve a safe working
environment by providing management control over the various activities that may
have potential for hazard. The Permit To Work system requires the involvement of
competent and responsible persons as well as the application of safety measures in a
controlled sequence.
Page 1 of 24
HSE Department Réf:
1.0 PURPOSE
The Permit to Work (PTW) system is used to control and manage specific
hazards during the course of the work. The purpose of such a system is to
achieve a safe working environment by providing management control over
the various activities that may have potential for hazard.
The PTW System is used to minimize the risk of harm to people, environment
and assets. The permit identifies all hazards and safeguards to be in-place
prior to work commencing to manage the hazards. Training on the Permit to
Work System will be provided to all personnel as part of their HSE induction.
3.0 INSTRUCTIONS
Page 2 of 24
HSE Department Réf:
APPENDIX I - 1 PURPOSE
The Permit to Work system is used to communicate and record specific
hazards during the course of the work as identified in pre-task risk
assessments. PTW is used to document the risk assessment and
management process. The purpose of such a system is to achieve a safe
working environment by providing management control over the various
activities that may have potential for hazard.
Page 3 of 24
HSE Department Réf:
APPENDIX I - 2 DEFINITIONS
Page 4 of 24
HSE Department Réf:
Example: Work with hand tools, portable electric tools, welding (in area
where no potential for hazardous atmosphere), excavating;
trenching, painting, working at height etc.
Line Break/Hydro Test procedures will include ensuring all points where
the possibility of pressure or liquids could be released are to be
barricaded with appropriate warning tape or guarded, so that no un-
authorized personnel could enter these areas. Pressure shall be vented
through a properly designed valve venting arrangement (High point
vents and/or low point drains). Breaking of lines is unacceptable.
Isolation and pressure reduction to zero shall be confirmed prior to
breaking containment. In the event that a high point vent / low point
drains are not available, the HSSE Department shall be contacted.
All areas where the actual release of hydrostatic pressure or liquids are
to be released shall be barricaded with appropriate warning tape, to
ensure that un-authorized personnel are aware of a hazardous working
area and should not enter. Appropriate containment shall be in place
Page 5 of 24
HSE Department Réf:
Any work that develops sparks, flames or heat sufficient to cause ignition
shall be done under control of a hot work permit. This will apply to the use
of spark or flame producing tools and equipment, including the use of
portable electric and pneumatic tools in an area where the potential for a
hazardous atmosphere exist or could exist or where flammable or
combustible material is stored or used.
The entry of personnel into any space or structure (tank, vessel, vault,
excavation when 1.2 meters or deeper, etc.) not normally intended for
human occupancy, in which entry, movement within or exit is restricted.
This permit will be used for all work that requires Electrical De-energising,
Blind Flange, Slip Blind, Disconnected Line, Isolation Spool, Double Valve &
Vent, Open Flange, and Instrument Disconnect to control the hazardous
energy.
Page 6 of 24
HSE Department Réf:
equipment being controlled from being operated until the Lockout / Tag-
out is removed.
Page 7 of 24
HSE Department Réf:
Page 8 of 24
HSE Department Réf:
Confine Hazardous
General Hot Line Break Radiographi
d Space Energy
Work Work Hydro-Test c Permit
Entry Control
Colour of
White Blue Green Yellow Orange Red
Permit
Re-
At shift change of Performing Authority
validation
Safety
Check No Yes Yes Yes Yes
Yes
Required
Entry Area JV Area Area
Senior Superviso Supervis
Superviso Superintende Superintende Superintende
Signatory r or
r nt nt nt
All Permits for the following days activities shall be raised by the
Performing Authority no later than 3pm on the previous work day. The
Area Authority shall approve all permits to work by 5pm and all permits for
the following day shall be posted on the Work Permit Board no later than
6pm.
The PTW Co-ordinator shall maintain a Permit Register. All permits shall be
returned to PTW Co-ordinators office on expiry date. It is the responsibility
of the PTW Co-ordinator to assist the Construction Manager in the control
and communication of PTW.
Page 9 of 24
HSE Department Réf:
Page 10 of 24
HSE Department Réf:
When work is stopped the Area Authority must write on the permit the
reason for stopping the work, the time and any other relevant information.
When conditions have been corrected and are safe, the PA may request
and issue a new work permit.
The PA has the responsibility to stop work and advise the Area Authority of
his action any time he feels the safe conditions in the area do not meet the
conditions on the work permit. The Area Authority and the Performing
Authority shall take action to correct deficiencies before resuming the job.
Page 11 of 24
HSE Department Réf:
Page 12 of 24
HSE Department Réf:
Page 13 of 24
HSE Department Réf:
Area
Description of work
Equipment to be used
SITE PREPARATION
Tick if
Initial Person performing the work must initial in boxes at left
required
Equipment isolation
Depressurize, drain, purge equipment
Lockout/Tag out
Electrical disconnect/ fuse removal
Blinds and tags
Area barricades/road closures/Signage
Scaffolding
Rigging diagram prepared and approved by competent person
X-ray work
Mechanical ventilation
Fall protection
Underground and Overhead cables / services
Other.
Safety & protective equipment required:
Page 14 of 24
HSE Department Réf:
SUSPEND/REVALIDATE
Valid until end of shift
Suspend/ Performing
Area Authority Date and Time Unless otherwise
Revalidate Authority
validated
Page 15 of 24
HSE Department Réf:
Area
Equipment to be used
SITE PREPARATION
Tick if
Initial Issuer must tick applicable boxes at left & Initial
required
Combustible gas tested initially and every_____________hrs.
Continuous Gas Monitoring
Fire extinguisher at job site
Flammables removed from immediate area (minimum 15m free
zone)
Cover nearby equipment with fireproof blankets
Equipment isolated, drained, blinded, gas freed
Fire Watch at job site
Communications provided
Area barricaded / Signate
Exact hot work location identified
Other restrictions or special approvals
Page 16 of 24
HSE Department Réf:
Performing Authority
Issuing Authority/Area Authority
SUSPEND/REVALIDATE
Valid until end of shift
Suspend/ Performing
Area Authority Date and Time Unless otherwise
Revalidate Authority
validated
Page 17 of 24
HSE Department Réf:
Page 18 of 24
HSE Department Réf:
Area
Date Valid From Hours To Hours
Work location
Permit requested by
Description of work
Equipment to be used
SITE PREPARATION
Tick if
Initial Issuer must tick applicable boxes at left & Initial
required
Combustible gas tested initially and every_____________hrs.
Sketch of Test/Equipment:
APPROVAL SIGNATURES
(By signing below parties agree work is safe to begin)
Performing Authority
Page 19 of 24
HSE Department Réf:
Page 20 of 24
HSE Department Réf:
Department: Area:
Date:
Equipment Description:
Purpose of Isolation:
Hazardous Energy
Volts Pressure Temperature Other
Source
Method Of Isolation
Page 21 of 24
HSE Department Réf:
Page 22 of 24
HSE Department Réf:
Page 23 of 24
HSE Department Réf:
APPROVAL
SubContractor: Signature:
The perimeter of the ”radiation area” must be roped off and have “warning signs” placed at intervals along the
perimeter(+) and at each entrance into the area. The “radiation area” must be clear of all none classified
personnel prior to each exposure and must be under visual surveillance during each exposure. Prior to use all
equipment is to be inspected and after each exposure both the camera and guide tube are to be surveyed
ensuring the source in the shielded position. The radioactive source shall not be left unattended.
RADIOGRAPHY WILL NOT COMMENCE UNTIL ALL SAFETY REQUIREMENTS HAVE BEEN CONFIRMED
SUSPEND/REVALIDATE
Valid until end of shift
Suspend/ Performing
Area Authority Date and Time Unless otherwise
Revalidate Authority
validated