Sap PP 6
Sap PP 6
Question Results
Question: Score 1 of 1
Response:
Packaging Logistics
Parts interchangeability
Question: Score 1 of 1
Response:
Bill of Material
Routing
Production Version
Question: Score 1 of 1
            Which of the following time elements does MRP use during backward scheduling
            for in-house production?
            There are 2 correct answers to this question.
Response:
Opening period
Question: Score 1 of 1
            The procurement type of your material is set to "E" for In-house production.
            Which of the following is valid to determine a source of supply in SAP S/4HANA?
            Please choose the correct answer.
Response:
Production Version
Contract
Selection Method
Question: Score 1 of 1
            The setup time on the production line to produce a material is extensive. You
            would like to avoid multiple setups and limit the production of the material
            based on a planning calendar.
            Which type of lot size procedure should you use to accomplish this?
            Please choose the correct answer.
Response:
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   2/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
Response:
Question: Score 1 of 1
            Which data object can be updated with the scheduling results of a routing?
            Please choose the correct answer.
Response:
MRP profile
Material master
Production version
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   3/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
            Which reports can you access via the order and resource reporting transaction in
            advanced planning?
            There are 3 correct answers to this question.
Response:
Operation list
WIP list
Production overview
Production list
Question: Score 1 of 1
Response:
                   The assigned routing and bill of materials (BOM) must be valid in the entire validity
                   period.
The lot size range must be within the lot-size range of the assigned routing.
The deletion flag must NOT be set for the bill of materials (BOM) or the routing.
Question: Score 1 of 1
            The material master of your finished product contains MRP type “PD”. You set a
            manual firming date in the stock requirements list. Which of the following will
            firm planned orders”
            There are 2 correct answers to this question.
            Response:
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   4/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
Response:
Question: Score 1 of 1
            In a first step you have created master recipes. In which sequence are the
            additional objects created?
            Please choose the correct answer.
Response:
                   Process order
                   Control recipe
                   Process message
                   PI sheet
                   Process order
                   Control recipe
                   PI sheet
                   Process message
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   5/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
                   Control recipe
                   Process order
                   PI sheet
                   Process message
                   Control recipe
                   Process order
                   Process message
                   PI sheet
Question: Score 1 of 1
Response:
Heuristics
Demand consumption
Backorder processing
Optimization
Question: Score 1 of 1
Response:
Resource selection
Capacity leveling
Capacity planning
Resource scheduling
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   6/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
            Your project uses process orders for the production of liquid chemicals. What
            can you define to ensure that the production flow happens only in physically
            connected tanks?
            Please choose the correct answer.
Response:
Setup matrix
Operation network
Resource network
Question: Score 1 of 1
            Which data model changes have been implemented in Sales and Distribution?
            There are 3 correct answers to this question.
Response:
Question: Score 1 of 1
            What are uses of the low- level code assigned to each material?
            There are 2 correct answers to this question.
Response:
Question: Score 0 of 1
Response:
Production versions
Outline agreement
Quota arrangements
Question: Score 1 of 1
            What are the options for transferring data to SAP S/4HANA with the SAP
            S/4HANA Migration Cockpit?
            There are 2 correct answers to this question.
Response:
Staging tables
Temporary tables
CSV files
XML files
Question: Score 1 of 1
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   8/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Response:
Question: Score 0 of 1
            When the goods receipt for a finished product is posted during confirmation on a
            manufacturing environment, which of the following actions are also performed
            by default?
            There are 2 correct answers to this question.
Response:
Question: Score 1 of 1
Response:
Simulation of planned changes for costing and mater all requirements planning
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   9/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
Response:
It was created for better planning and estimation of your way to S/4HANA
Question: Score 1 of 1
Response:
Business partner
Employee
Occasional
Expert
Developer
Question: Score 1 of 1
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   10/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Response:
Question: Score 1 of 1
            How can Production Planning and Detailed Scheduling (PP/DS) enhance the
            standard planning functionality?
            Please choose the correct answer.
Response:
Question: Score 1 of 1
            For which planning-relevant data objects do you set just one indicator to include
            then in PP/DS?
            There are 2 correct answers to this question.
Response:
Material
Plant
Production version
Work center
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   11/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
            What are the consequences when you assign a planned order to a production
            line manually, using the planning table in repetitive manufacturing?
            Please choose the correct answer.
Response:
Question: Score 1 of 1
Response:
Move time
Wait time
Queue time
Question: Score 1 of 1
            Which of the following elements does MRP take into account during net
            requirement calculation?
            There are 2 correct answers to this question.
Response:
Purchase orders
Safety stock
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   12/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Lot size
Question: Score 1 of 1
            What are the possible categories for the Business Partner master data object in
            SAP S/4HANA?
            There are 3 correct answers to this question.
Response:
Customer
Person
Vendor
Group
Organization
Question: Score 1 of 1
            How can you limit the number of master data objects to be created when the
            manufacturing process is the same for many different products?
            Please choose the correct answer.
Response:
Question: Score 0 of 1
            You need to model goods receipt processing time in Detailed Scheduling. Which
            modelling options do you have?
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   13/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Response:
                   Model a handling resource in the location master and goods receipt time in the
                   mater all master.
Question: Score 1 of 1
            How can you set up the supply source for the SAP Kanban process?
            There are 3 correct answers to this question.
Response:
Question: Score 1 of 1
            What Kanban status automatically posts goods receipt with reference to the
            procurement element?
            Please choose the correct answer.
Response:
Full
In use
Empty
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   14/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Wait
Question: Score 1 of 1
            The production plan is being disrupted by last minute demands that are entered
            in the system. Which is the most efficient way to handle last minute demands
            and protect the current production plan?
Response:
                   Manually firm all planned orders for materials within the replenishment lead time of
                   the material
                   In the material master record, set MRP type to P4 and a planning time fence on the
                   replenishment lead time of the material
                   In the material master record, set MRP type to P1 and a planning time fence on the
                   replenishment lead time of the material
                   In the stock requirements list, set a manual firming fence for a date based on the
                   replenishment lead time of the material
Question: Score 1 of 1
            To ensure that the warehouse operator only stages large components in the
            exact required quality for each production order, which warehouse material
            staging method would you recommend?
Response:
Kanban
Pick parts
Crate parts
Question: Score 1 of 1
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   15/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
            Which transaction code can you use in SAP S/4HANA to enter and display goods
            movements?
            Please choose the correct answer.
Response:
MBNL
MIGO
MB02
MMBE
Question: Score 1 of 1
Response:
Order list
Resource utilization
Resource overview
Production list
Question: Score 1 of 1
            MRP created a planned order for a material that has one single material from
            stock as a component. What happens to this dependent requirement when you
            convert the planned order into a production order?
Response:
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   16/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
            Which SAP solutions support the supplier area in the portfolio of the Digital
            Value Network?
            There are 3 correct answers to this question.
Response:
SAP SuccessFactors
SAP Concur
SAP S/4HANA
SAP Ariba
Question: Score 0 of 1
Response:
Guided Configuration
Premium engagement
SAP MaxAttention
Question: Score 1 of 1
            What are the three layers in the SAP Best Practices Content for SAP S/4HANA?
            There are 3 correct answers to this question.
Response:
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   17/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Process Flows
Solution Package
Test Scripts
Building Blocks
Scope Items
Question: Score 1 of 1
            What must be used in the system to plan the requirements for different
            subcontractors separately?
Response:
Production versions
Storage locations
MRP areas
Planning plant
Question: Score 1 of 1
            You are transferring data from SAP S/4HANAlo embedded PP/OS. What master
            data objects are mapped to a location?
            There are 3 correct answers to this question.
Response:
Workcenter
Warehouse number
Plant
Customer
Supplier
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   18/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
Response:
Question: Score 1 of 1
            What are the main processes of the embedded PP/OS in SAP S/4HANA?
            There are 2 correct answers to this question.
Response:
Question: Score 1 of 1
            In which material master views can you select the batch management
            checkbox?
            There are 2 correct answers to this question.
Response:
Purchasing
Basic Data 1
Work Scheduling
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   19/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
MRP 4
Question: Score 1 of 1
            What information is included in the SAP Readiness Check result for SAP
            S/4HANA?
            There are 3 correct answers to this question.
Response:
Question: Score 1 of 1
Response:
Question: Score 1 of 1
            You are creating a production order manually. What activities are involved in
            this process?
            There are 3 correct answers to this question.
            Response:
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   20/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Planning selection
Question: Score 1 of 1
Response:
Question: Score 1 of 1
Response:
Warehouse task
Warehouse order
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   21/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
Response:
Question: Score 1 of 1
            In your project, you have several materials that are planned by different people.
            How can you assign the planning responsibility?
            Please choose the correct answer.
Response:
MRP group
MRP type
MRP controller
Question: Score 1 of 1
Response:
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   22/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
Response:
Question: Score 1 of 1
            Which of the following elements does the MRP run take into account?
            There are 2 correct answers to this question.
Response:
Shipments
Sales orders
Material documents
Question: Score 1 of 1
            A resource was created in SAP S/4HANA PP/DS through the internal CIF
            integration and named “W1904_1000_001”. What does the suffix 001 in the
            resource name represent?
            Please choose the correct answer.
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   23/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Response:
Capacity category
Question: Score 1 of 1
Response:
HANA Live
Question: Score 1 of 1
Response:
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   24/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
            Your client is asking for your advice on material master numbering in SAP
            S/4HANA. What do you need to consider?
            There are 2 correct answers to this question.
Response:
                   The maximum mater all number length is 40 for external numbers and 18 for
                   internal numbers
                   In Customizing you can decide by material type whether to use the long material
                   number.
Question: Score 1 of 1
            Where can you find the latest in version of the Simplification List for SAP
            S/4HANA?
            Please choose the correct answer.
Response:
Question: Score 1 of 1
Response:
At order release
At order settlement
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   25/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
At order confirmation
At order creation
Question: Score 1 of 1
            Which Kanban master data object controls the relationship between the supply
            and demand source?
            Please choose the correct answer.
Response:
Rate routing
Kanban container
Control cycle
Question: Score 1 of 1
Response:
Question: Score 1 of 1
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   26/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Response:
Question: Score 1 of 1
            In which data objects do you maintain the production in as the work center for
            repetitive manufacturing?
            There are 2 correct answers to this question.
Response:
Production version
Routing
Question: Score 1 of 1
            What are examples of assignment objects you can maintain in the Engineering
            Workbench?
            There are 3 correct answers to this question.
Response:
                   Component assignment
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   27/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
Response:
Question: Score 1 of 1
Response:
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   28/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
Response:
Processing time
Queue time
Move time
Floating time
Question: Score 1 of 1
            An issue storage location was NOT found through the work center, bill of
            material (BOM) item, or material master. What determines whether the storage
            location can be derived from the production version?
Response:
Plant Data
MRP Controller
MRP Group
MRP Profile
Question: Score 1 of 1
Response:
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   29/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
            Which of the following data objects are updated when a user confirms an
            operation?
            Please choose the correct answer.
Response:
Question: Score 1 of 1
            You have maintained the parameters for simple discontinuation in the material
            master of a component. Which business process will be affected if the available
            stock is zero and the discontinuation date is in the past?
Response:
Kanban
Backflushing
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   30/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
            What data processing steps are obsolete if you use SAP S/4HANA Analytics?
            There are 2 correct answers to this question.
Response:
Question: Score 1 of 1
            Which material master setting is required to use the repetitive planning table for
            production with production orders?
            Please choose the correct answer.
Response:
At least one valid production version must exist on the MRP4 view
Question: Score 1 of 1
            Which of the following functions can be performed when the production order
            has the status “Created” (CRTD)?
            Please choose the correct answer.
Response:
A user trigger material availability check via mass processing (transaction COHV)
                   A user can trigger material staging via mass processing (transaction COHV).
https://www.erpprep.com/user/quiz/1744873/userresults                                                                                   31/32
7/19/2020                    SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing - Full | ERPPrep
Question: Score 1 of 1
            Which options do you have to plan both quant ties and capacities during line
            loading in repetitive manufacturing?
            There are 2 correct answers to this question.
Response: