DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 103(2)a Bridge Excavation
Unit of Measurement : cu.m.
Output per hour : 20 cu.m.
Designation No. Of Person/s No. of Hour/s Hourly Rate Amount (PhP)
A. Labor
-
a. Construction Foreman 1 1.00 97.25 97.25
b. Skilled Laborer 1 1.00 70.35 70.35
c. Unskilled Laborer 2 1.00 54.14 108.28
-
-
-
Sub-Total for A 275.88
Name and Capacity No. of Unit/s No. of Hours Hourly Rate Amount (PhP)
B. Equipment
-
-
Dump Truck (12 cu.yd.) 2 1.00 3,108.67 6,217.34
Backhoe 1 1.00 2,672.50 2,672.50
-
-
-
-
-
-
-
-
-
Sub-Total for B 8,889.84
C. Total (A+B) 9,165.72
D. Output per Hour= 20.00
E. Direct Unit Cost (C÷D) 458.29
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F. Materials
-
-
-
-
-
-
-
-
-
-
-
Sub-Total for F -
G. Direct Unit Cost (E+F) 458.29
H. Overhead, Contingencies and Miscellaneous (OCM) Expenses 12% of G 54.99
I. Contractor's Profit (CP) 8% of G 36.66
J. Value Added Tax 5% of (G+H+I) 27.50
K. Total Unit Cost (G+H+I+J) 577.44