Republic of the Philippines
Province of Eastern Samar
Office of the Provincial Engineer
GHANNT CHART AND S-CURVE
Project Title: Construction of Farm-to-Market Road in Llorente, Eastern Samar Phase-2
Project Location: Llorente, Eastern Samar
Duration (Calendar
MONTH 1 MONTH 2 MONTH 3
Days)
Item no. Description Qty. Unit Weight Total Cost WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 1 WEEK 2 WEEK 3 WEEK 4
1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6 1 2 3 4 5 6
B.5 Project Billboard/ Sign Board 1.00 each 0.13% 1 24,425.17 1
Occupational Safety and Health
B.7 3.93 month 0.18% 1 34,303.87 1
Program
B.9 MobilizationDemobilization 1.00 l.s. 0.79% 1 152,318.92 1
B.8(1) Traffic Management 3.93 month 0.74% 1 142,784.18 1
100(1) Clearing and Grubbing 0.68 ha 0.80% 2 154,748.23 1 1
Roadway Excavation (Surplus
102(2)a 12,757.46 cu.m. 13.12% 27 2,527,447.50 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Common)
104(1)a Embankment (from Borrow) 589.38 cu.m. 5.58% 2 1,075,280.98 1 1 1 1 1 1 1
Subgrade Preparation (Common
105(1) 4,843.98 sq.m. 0.58% 3 112,361.92 1 1
Material)
201 Aggregate Base Course 726.60 cu.m 11.84% 2 2,280,500.32 1
PCC Pavement(Plain)- Conventional
311(1)a.2 4,843.98 sq.m. 56.73% 14 10,927,756.31 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Method, 200 mm thk
Reinforcing Street Bar, Grade 40
404 3,792.59 kg 1.99% 4 382,392.84 1 1 1 1 1 1 1 1 1 1 1 1 1
(Minor Structures)
505(5) Grouted Riprap (Class A) 233.38 cu.m. 7.52% 24 1,447,911.29 1 1 1 1 1 1 1 1 1 1
# # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #
Total 100% 19,262,231.52 # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #
PROJECTED WEEKLY ACCOMPLISH (%) 4.58% 2.92% 2.92% 16.75% 21.26% 24.31% 24.31% 6.53% 2.98% 2.25% 1.88% 0.00%
ACCUMULATED WEEKLY PROJECTED ACCOMPLISHMENT (%) 4.58% 7.50% 10.42% 27.16% 48.42% 72.73% 97.05% 103.58% 106.56% 108.80% 110.68% 110.68%
PROJECTED WEEKLY DISBURSEMENT (₱) 883,017.03 561,655.00 561,655.00 3,225,842.94 4,094,460.66 4,683,324.13 4,683,324.13 1,258,545.07 573,589.25 432,514.97 361,977.82 -
ACCUMULATED PROJECTED PROJECTED ACCOMPLISH (₱) 883,017.03 1,444,672.03 2,006,327.04 5,232,169.98 9,326,630.64 14,009,954.77 18,693,278.91 19,951,823.97 20,525,413.23 20,957,928.19 21,319,906.02 21,319,906.02
Prepared by: Checked by: Recommending Approval:
RONULFO M. FABULA JR. RCE, RMP Engr. GODOFREDO C. ESCOTO Engr. SIXTO A. LIMBAUAN JR.
C and M Gen. Foreman Assistant Provincial Engineer Provincial Engineer