Weekly Progress Report: Republic of The Philippines Philippine Rural Development Project (PRDP)

The weekly progress report summarizes the rehabilitation project of the Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road in Ilocos Norte, Philippines. The project involves construction of road networks, drainage systems, and perimeter fences. As of the reporting period from May 9-15, 2018, the project was 0.016% complete, lagging the scheduled accomplishment of 0.136%. Mobilization and site clearing had commenced but major earthworks and road construction activities had not yet started. Safety measures were ongoing on site.

Uploaded by

stella mariz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
154 views73 pages

Weekly Progress Report: Republic of The Philippines Philippine Rural Development Project (PRDP)

The weekly progress report summarizes the rehabilitation project of the Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road in Ilocos Norte, Philippines. The project involves construction of road networks, drainage systems, and perimeter fences. As of the reporting period from May 9-15, 2018, the project was 0.016% complete, lagging the scheduled accomplishment of 0.136%. Mobilization and site clearing had commenced but major earthworks and road construction activities had not yet started. Safety measures were ongoing on site.

Uploaded by

stella mariz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 73

Annex 36 Form No.

Republic of the Philippines


PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 1
Period Covered MAY 09 - 15, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of
vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 0.136% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 0.016% %
Contract Duration : 205 Slippage Previous +/- : 0.000% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -0.120% %
Revised Contract Duration Contract time Elapsed : 7.000 c.d.
Revised Expiry Date : Percent Time Elapse 2.881% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.034 0.034 - 2,004.912 2,004.912 0.004% 0.004%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.000 - - - 0.000% 0.000%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 0.000 - - - 0.000% 0.120%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 0.000 - - - 0.000% 0.000%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 0.000 - - - 0.000% 0.000%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 0.000 - - - 0.000% 0.000%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 0.000 - - - 0.000% 0.000%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 0.000 - - - 0.000% 0.000%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 0.000 - - - 0.000% 0.000%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 0.000 - - - 0.000% 0.000%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.034 0.034 - 6,299.943 6,299.943 0.013% 0.013%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 0.000 - - - 0.000% 0.000%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 0.016% 0.016% 0.016% 0.136%
. SLIPPAGE, +/- -0.120%
- 8,304.86 8,304.86
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 2
Period Covered MAY 16 - 23, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of
vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 0.395% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 0.232% %
Contract Duration : 205 Slippage Previous +/- : -0.120% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -0.163% %
Revised Contract Duration Contract time Elapsed : 15.000 c.d.
Revised Expiry Date : Percent Time Elapse 6.173% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.034 0.039 0.073 2,004.91 2,299.752 4,304.664 0.009% 0.009%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.040 0.040 - 16,439.052 16,439.052 0.033% 0.055%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 0.350 0.350 - 58,587.001 58,587.001 0.116% 0.257%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 0.000 - - - 0.000% 0.000%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 0.000 - - - 0.000% 0.000%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 0.000 - - - 0.000% 0.000%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 0.000 - - - 0.000% 0.000%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 0.000 - - - 0.000% 0.000%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 0.000 - - - 0.000% 0.000%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 0.000 - - - 0.000% 0.000%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.034 0.039 0.073 6,299.94 7,226.406 13,526.349 0.027% 0.027%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 - 23,897.820 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 0.215% 0.232% 0.232% 0.395%
. SLIPPAGE, +/- -0.163%
8,304.86 108,450.03 116,754.89
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 3
Period Covered MAY 24 - 30, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital
facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 0.578% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 0.380% %
Contract Duration : 205 Slippage Previous +/- : -0.163% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -0.198% %
Revised Contract Duration Contract time Elapsed : 22.000 c.d.
Revised Expiry Date : Percent Time Elapse 9.053% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.073 0.034 0.107 4,304.66 2,004.912 6,309.576 0.013% 0.013%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.040 0.040 0.080 16,439.05 16,439.052 32,878.104 0.065% 0.102%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 0.350 0.300 0.650 58,587.00 50,217.429 108,804.430 0.216% 0.377%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 0.000 - - - 0.000% 0.000%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 0.000 - - - 0.000% 0.000%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 0.000 - - - 0.000% 0.000%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 0.000 - - - 0.000% 0.000%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 0.000 - - - 0.000% 0.000%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 0.000 - - - 0.000% 0.000%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 0.000 - - - 0.000% 0.000%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.073 0.034 0.107 13,526.35 6,299.943 19,826.292 0.039% 0.039%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 - 23,897.820 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 0.196% 0.380% 0.380% 0.578%
. SLIPPAGE, +/- -0.198%
92,857.07 98,859.16 191,716.23
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 4
Period Covered MAY 31 - JUNE 06, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital
facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 0.871% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 0.511% %
Contract Duration : 205 Slippage Previous +/- : -0.198% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -0.359% %
Revised Contract Duration Contract time Elapsed : 29.000 c.d.
Revised Expiry Date : Percent Time Elapse 11.934% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.107 0.034 0.141 6,309.58 2,004.912 8,314.488 0.016% 0.016%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.040 0.058 0.098 16,439.05 23,836.625 40,275.677 0.080% 0.149%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 0.650 0.300 0.950 108,804.43 50,217.429 159,021.859 0.316% 0.497%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 0.000 - - - 0.000% 0.000%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 0.000 - - - 0.000% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 0.000 - - - 0.000% 0.000%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 0.000 - - - 0.000% 0.000%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 0.000 - - - 0.000% 0.000%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 0.000 - - - 0.000% 0.000%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 0.000 - - - 0.000% 0.000%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.107 0.034 0.141 19,826.29 6,299.943 26,126.235 0.052% 0.052%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 0.163% 0.511% 0.511% 0.871%
. SLIPPAGE, +/- -0.359%
175,277.17 82,358.91 257,636.08
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 3
Period Covered MAY 24 - 30, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 0.491% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.232% %
Contract Started : 16-May-18 Actual Accomplishment to date : 0.380% %
Contract Duration : 205 DAYS Slippage Previous +/- : -0.163% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -0.110% %
Revised Contract Duration 260 DAYS Contract time Elapsed : 22.000 c.d.
Revised Expiry Date : 30-Jan-19 Percent Time Elapse 10.732% %

PROJECT UPDATE
Rel. Wt.
ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date DATE TO DATE
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.073 - 0.041 0.114 - 11.400% 0.073 0.034 0.107 4,304.66 2,004.912 6,309.576 0.013% 0.013%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.067 - 0.058 0.125 - 12.500% 0.040 0.040 0.080 16,439.05 16,439.052 32,878.104 0.065% 0.102%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 0.544 - 0.476 1.020 - 41.633% 0.350 0.300 0.650 58,587.00 50,217.429 108,804.430 0.216% 0.339%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% - - - - 0.000% 0.000 - - - 0.000% 0.000%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% - - - - 0.000% 0.000 - - - 0.000% 0.000%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% - - - - 0.000% 0.000 - - - 0.000% 0.000%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% - - - - 0.000% 0.000 - - - 0.000% 0.000%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% - - - - 0.000% 0.000 - - - 0.000% 0.000%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% - - - - 0.000% 0.000 - - - 0.000% 0.000%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% - - - - 0.000% 0.000 - - - 0.000% 0.000%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% - - - - 0.000% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - - - - 0.000% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - - - - 0.000% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.047 - 0.041 0.088 - 8.800% 0.073 0.034 0.107 13,526.35 6,299.943 19,826.292 0.039% 0.032%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 0.140 - 0.123 0.263 - 8.767% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.004%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 0.232% 0.149% 0.380% 0.380% 0.491%
. SLIPPAGE, +/- -0.110%
116,754.89 74,961.34 191,716.22
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte
Period Covered MAY 31 - JUNE 06, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date


Revised Contract Amount 50,391,995.74 Previous Accomplishment
Contract Started : 16-May-18 Actual Accomplishment to date
Contract Duration : 205 DAYS Slippage Previous +/-
Contract Expiration : 6-Dec-18 Slippage to Date, +/-
Revised Contract Duration 260 DAYS Contract time Elapsed
Revised Expiry Date : 30-Jan-19 Percent Time Elapse

PROJECT UPDATE
Rel. Wt.
ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original
PART DESCRIPTION Unit Unit Cost Contract Amount
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.088 - 0.041 0.129 - 12.900% 0.088 0.041 0.129 5,189.18
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.125 - 0.058 0.183 - 18.300% 0.080 0.058 0.138 32,878.10
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 1.020 - 0.476 1.496 - 61.061% 0.650 0.300 0.950 108,804.43
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% - - - - 0.000% 0.000 -
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% - - 109.200 109.200 - 100.000% 0.000 -
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% - - - - 0.000% 0.000 -
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% - - - - 0.000% 0.000 -
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% - - - - 0.000% 0.000 -
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% - - - - 0.000% 0.000 -
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% - - - - 0.000% 0.000 -
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% - - - - 0.000% 0.000 -
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.000 -
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000 -
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - - - - 0.000% 0.000 -
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000 -
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - - - - 0.000% 0.000 -
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000 -
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000 -
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000 -
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000 -
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.088 - 0.041 0.129 - 12.900% 0.088 0.041 0.129 16,305.74
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 0.263 - 0.123 0.386 - 12.867% 0.263 0.123 0.386 2,095.04
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 0.328%
. SLIPPAGE,
165,272.50
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE
Title MPMIU Resident Engineer Title MPMIU Engineer
Date Date
Form No.

nage system, perimeter fence.

: 0.823% %
: 0.328% %
: 0.497% %
: -0.016% %
: -0.327% %
: 22.000 c.d.
12.865% %

AMOUNT
% ACTUAL TO % SCHEDULED
This Period To date DATE TO DATE

2,417.688 7,606.872 0.015% 0.015%


23,836.625 56,714.729 0.113% 0.149%
50,217.429 159,021.859 0.316% 0.497%
- - 0.000% 0.000%
- - 0.000% 0.109%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
7,596.990 23,902.726 0.047% 0.047%
979.811 3,074.853 0.006% 0.006%
0.169% 0.497% 0.497% 0.823%
SLIPPAGE, +/- -0.327%
85,048.54 250,321.04

DUDEO C. GALEON
MPMIU Head
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 5
Period Covered AUGUST 30 - SEPTEMBER 05, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital
facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 2.117% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 1.747% %
Contract Duration : 205 C.D. Slippage Previous +/- : -0.359% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -0.370% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 36.000 c.d.
Revised Expiry Date : 21-Feb-19 Percent Time Elapse 14.815% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.141 0.034 0.175 8,314.49 2,004.912 10,319.400 0.020% 0.020%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.098 0.100 0.198 40,275.68 41,097.630 81,373.307 0.161% 0.197%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 0.95 0.600 1.550 159,021.86 100,434.858 259,456.717 0.515% 0.655%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 0.000 - - - 0.000% 0.000%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 54,733.224 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 1300.000 1300.000 - 418,262.000 418,262.000 0.830% 1.024%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 0.000 - - - 0.000% 0.000%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 0.000 - - - 0.000% 0.000%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 0.000 - - - 0.000% 0.000%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 0.000 - - - 0.000% 0.000%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.141 0.034 0.175 26,126.24 6,299.943 32,426.179 0.064% 0.064%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 1.236% 1.747% 1.747% 2.117%
. SLIPPAGE, +/- -0.370%
257,636.08 622,832.57 880,468.66
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 6
Period Covered SEPTEMBER 06-12, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital
facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 3.469% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 2.936% %
Contract Duration : 205 C.D. Slippage Previous +/- : -0.370% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -0.533% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 43.000 c.d.
Revised Expiry Date : 21-Feb-19 Percent Time Elapse 17.695% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.175 0.034 0.209 10,319.40 2,004.912 12,324.312 0.024% 0.024%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.198 0.060 0.258 81,373.31 24,658.578 106,031.885 0.210% 0.244%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 1.550 0.500 2.050 259,456.72 83,695.715 343,152.432 0.681% 0.813%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 0.000 - - - 0.000% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 1300.000 1500.000 2800.000 418,262.00 482,610.000 900,872.000 1.788% 2.049%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 0.000 - - - 0.000% 0.000%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 0.000 - - - 0.000% 0.000%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 0.000 - - - 0.000% 0.000%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 0.000 - - - 0.000% 0.000%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.175 0.034 0.209 32,426.18 6,299.943 38,726.122 0.077% 0.077%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 1.189% 2.936% 2.936% 3.469%
. SLIPPAGE, +/- -0.533%
880,468.65 599,269.15 1,479,737.82
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte
Period Covered AUGUST 30 - SEPTEMBER 05, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date


Revised Contract Amount 50,391,995.74 Previous Accomplishment
Contract Started : 16-May-18 Actual Accomplishment to date
Contract Duration : 205 DAYS Slippage Previous +/-
Contract Expiration : 6-Dec-18 Slippage to Date, +/-
Revised Contract Duration 260 DAYS Contract time Elapsed
Revised Expiry Date : 30-Jan-19 Percent Time Elapse

PROJECT UPDATE
Rel. Wt.
ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMO
Original
PART DESCRIPTION Unit Unit Cost Contract Amount
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.129 - 0.041 0.170 - 17.000% 0.129 0.041 0.17 7,606.87
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.183 - 0.058 0.241 - 24.100% 0.138 0.100 0.238 56,714.73
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 1.496 - 0.476 1.972 - 80.490% 0.950 0.600 1.550 159,021.86
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% - - - - 0.000% 0.000 -
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 - - 109.200 - 100.000% 109.200 109.200 -
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% - - 1,604.418 1,604.418 - 14.000% 1300.000 1300.000 -
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% - - - - 0.000% 0.000 -
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% - - - - 0.000% 0.000 -
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% - - - - 0.000% 0.000 -
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% - - - - 0.000% 0.000 -
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% - - - - 0.000% 0.000 -
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.000 -
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000 -
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - - - - 0.000% 0.000 -
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000 -
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - - - - 0.000% 0.000 -
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000 -
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000 -
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000 -
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000 -
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.129 - 0.041 0.170 - 17.000% 0.129 0.041 0.17 23,902.73
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 0.386 - 0.123 0.509 - 16.967% 0.386 0.123 0.509 3,074.85
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 0.497%
. SLIPPA
250,321.04
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE
Title MPMIU Resident Engineer Title MPMIU Engineer
Date Date
Form No.

16

system, perimeter fence.

: 2.075% %
: 0.497% %
: 1.738% %
: -0.327% %
: -0.337% %
: 29.000 c.d.
16.959% %

AMOUNT
% ACTUAL TO % SCHEDULED
This Period To date DATE TO DATE

2,417.688 10,024.560 0.020% 0.020%


41,097.630 97,812.359 0.194% 0.197%
100,434.858 259,456.717 0.515% 0.655%
- - 0.000% 0.000%
54,733.224 54,733.224 0.109% 0.109%
418,262.000 418,262.000 0.830% 1.024%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
7,596.990 31,499.717 0.063% 0.063%
979.811 4,054.663 0.008% 0.008%
1.241% 1.738% 1.738% 2.075%
SLIPPAGE, +/- -0.337%
625,522.20 875,843.24

DUDEO C. GALEON
MPMIU Head
Annex 36
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte
Period Covered SEPTEMBER 06-12, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date


Revised Contract Amount 50,391,995.74 Previous Accomplishment
Contract Started : 16-May-18 Actual Accomplishment to date
Contract Duration : 205 DAYS Slippage Previous +/-
Contract Expiration : 6-Dec-18 Slippage to Date, +/-
Revised Contract Duration 260 DAYS Contract time Elapsed
Revised Expiry Date : 30-Jan-19 Percent Time Elapse

PROJECT UPDATE
Rel. Wt.
ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMO
Original
PART DESCRIPTION Unit Unit Cost Contract Amount
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.170 - 0.041 0.211 - 21.100% 0.17 0.041 0.211 10,024.56
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.241 - 0.058 0.299 - 29.900% 0.238 0.060 0.298 97,812.36
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 1.972 - 0.476 2.448 - 99.918% 1.550 0.500 2.050 259,456.72
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% - - 1.000 1.000 - 100.000% 0.000 -
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 - - 109.200 - 100.000% 109.200 0.000 109.200 54,733.22
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 1,604.418 - 1,604.418 3,208.836 - 28.000% 1300.000 1500.000 2800.000 418,262.00
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% - - - - 0.000% 0.000 -
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% - - - - 0.000% 0.000 -
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% - - - - 0.000% 0.000 -
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% - - - - 0.000% 0.000 -
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% - - - - 0.000% 0.000 -
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.000 -
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000 -
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - - - - 0.000% 0.000 -
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000 -
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - - - - 0.000% 0.000 -
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000 -
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000 -
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000 -
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000 -
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.170 - 0.041 0.211 - 21.100% 0.170 0.041 0.211 31,499.72
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 0.509 - 0.123 0.632 - 21.067% 0.509 0.123 0.632 4,054.66
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 1.738%
. SLIPPA
875,843.24
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE
Title MPMIU Resident Engineer Title MPMIU Engineer
Date Date
Form No.

17

system, perimeter fence.

: 3.433% %
: 1.738% %
: 2.933% %
: -0.337% %
: -0.500% %
: 36.000 c.d.
21.053% %

AMOUNT
% ACTUAL TO % SCHEDULED
This Period To date DATE TO DATE

2,417.688 12,442.248 0.025% 0.025%


24,658.578 122,470.937 0.243% 0.244%
83,695.715 343,152.432 0.681% 0.813%
- - 0.000% 0.106%
- 54,733.224 0.109% 0.109%
482,610.000 900,872.000 1.788% 2.049%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
7,596.990 39,096.707 0.078% 0.078%
979.811 5,034.474 0.010% 0.010%
1.195% 2.933% 2.933% 3.433%
SLIPPAGE, +/- -0.500%
601,958.78 1,477,802.02

DUDEO C. GALEON
MPMIU Head
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 7
Period Covered SEPTEMBER 18-19, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities
such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 3.795% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 3.385% %
Contract Duration : 205 C.D. Slippage Previous +/- : -0.533% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -0.410% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 45.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 18.519% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.209 0.010 0.219 12,324.31 589.680 12,913.992 0.026% 0.026%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.258 0.030 0.288 106,031.89 12,329.289 118,361.174 0.235% 0.258%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.050 0.300 2.350 343,152.43 50,217.429 393,369.861 0.781% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% - - - - 0.000% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 2,800.000 500.000 3,300.000 900,872.00 160,870.000 1,061,742.000 2.107% 2.341%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% - - - - 0.000% 0.013%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% - - - - 0.000% 0.000%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% - - - - 0.000% 0.000%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% - - - - 0.000% 0.000%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% - - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.209 0.010 0.219 38,726.12 1,852.925 40,579.047 0.081% 0.081%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 0.448% 3.385% 3.385% 3.795%
. SLIPPAGE, +/- -0.410%
1,479,737.79 225,859.32 1,705,597.15
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte
Period Covered SEPTEMBER 18-19, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date


Revised Contract Amount 50,391,995.74 Previous Accomplishment
Contract Started : 16-May-18 Actual Accomplishment to date
Contract Duration : 205 DAYS Slippage Previous +/-
Contract Expiration : 6-Dec-18 Slippage to Date, +/-
Revised Contract Duration 260 DAYS Contract time Elapsed
Revised Expiry Date : 30-Jan-19 Percent Time Elapse

PROJECT UPDATE
Rel. Wt.
ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMO
Original
PART DESCRIPTION Unit Unit Cost Contract Amount
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.211 - 0.012 0.223 - 22.300% 0.211 0.012 0.223 12,442.25
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.299 - 0.017 0.316 - 31.600% 0.298 0.017 0.315 122,470.94
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 - - 2.450 - 100.000% 2.050 0.300 2.350 343,152.43
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 - - 1.000 - 100.000% 0.000 -
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 - - 109.200 - 100.000% 109.200 109.200 54,733.22
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 3,208.836 - 458.405 3,667.241 - 32.000% 2800.000 500.000 3300.000 900,872.00
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% - - 24.400 24.400 - 28.571% 0.000 -
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% - - - - 0.000% 0.000 -
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% - - - - 0.000% 0.000 -
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% - - - - 0.000% 0.000 -
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% - - - - 0.000% 0.000 -
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.000 -
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000 -
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - - - - 0.000% 0.000 -
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000 -
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - - - - 0.000% 0.000 -
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000 -
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000 -
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000 -
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000 -
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.211 - 0.012 0.223 - 22.300% 0.211 0.012 0.223 39,096.71
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 0.632 - 0.035 0.667 - 22.233% 0.632 0.035 0.667 5,034.47
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 2.933%
. SLIPPA
1,477,802.02
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE
Title MPMIU Resident Engineer Title MPMIU Engineer
Date Date
Form No.

18

system, perimeter fence.

: 3.760% %
: 2.933% %
: 3.372% %
: -0.500% %
: -0.388% %
: 38.000 c.d.
22.222% %

AMOUNT
% ACTUAL TO % SCHEDULED
This Period To date DATE TO DATE

707.616 13,149.864 0.026% 0.026%


6,986.597 129,457.535 0.257% 0.258%
50,217.429 393,369.861 0.781% 0.814%
- - 0.000% 0.106%
- 54,733.224 0.109% 0.109%
160,870.000 1,061,742.000 2.107% 2.341%
- - 0.000% 0.013%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
- - 0.000% 0.000%
2,223.509 41,320.216 0.082% 0.082%
278.808 5,313.282 0.011% 0.011%
0.439% 3.372% 3.372% 3.760%
SLIPPAGE, +/- -0.388%
221,283.959 1,699,085.981

DUDEO C. GALEON
MPMIU Head
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 8
Period Covered SEPTEMBER 20-26, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital
facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 4.916% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 4.391% %
Contract Duration : 205 C.D. Slippage Previous +/- : -0.410% %
Contract Expiration : 30-Nov-18 Slippage to Date, +/- : -0.525% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 52.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 21.399% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.219 0.034 0.253 12,913.99 2,004.912 14,918.904 0.030% 0.030%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.288 0.058 0.346 118,361.17 23,836.625 142,197.800 0.282% 0.305%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.35 0.050 2.400 393,369.86 8,369.572 401,739.432 0.797% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 0.000 - - - 0.000% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 3300 1450.000 4750.000 1,061,742.00 466,523.000 1,528,265.000 3.033% 3.366%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 0.000 - - - 0.000% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 0.000 - - - 0.000% 0.000%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 0.000 - - - 0.000% 0.000%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 0.000 - - - 0.000% 0.000%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.219 0.034 0.253 40,579.05 6,299.943 46,878.990 0.093% 0.093%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.00 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 1.006% 4.391% 4.391% 4.916%
. SLIPPAGE, +/- -0.525%
1,705,597.12 507,034.05 2,212,631.21
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 9
Period Covered SEPTEMBER 27 - OCTOBER 03, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities
such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 6.004% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 5.429% %
Contract Duration : 205 C.D. Slippage Previous +/- : -0.525% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -0.575% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 59.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 24.280% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.253 0.034 0.287 14,918.90 2,004.912 16,923.816 0.034% 0.034%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.346 0.058 0.404 142,197.80 23,836.625 166,034.425 0.329% 0.352%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.4 0.050 2.450 401,739.43 8,369.572 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 0.000 - - - 0.000% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 4750 1500.000 6250.000 1,528,265.00 482,610.000 2,010,875.000 3.990% 4.390%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 0.000 - - - 0.000% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 0.000 - - - 0.000% 0.000%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 0.000 - - - 0.000% 0.000%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 0.000 - - - 0.000% 0.000%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.253 0.034 0.287 46,878.99 6,299.943 53,178.933 0.106% 0.106%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 1.038% 5.429% 5.429% 6.004%
. SLIPPAGE, +/- -0.575%
2,212,631.17 523,121.05 2,735,752.28
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte
Period Covered SEPTEMBER 20-26, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date


Revised Contract Amount 50,391,995.74 Previous Accomplishment
Contract Started : 16-May-18 Actual Accomplishment to date
Contract Duration : 205 DAYS Slippage Previous +/-
Contract Expiration : 6-Dec-18 Slippage to Date, +/-
Revised Contract Duration 260 DAYS Contract time Elapsed
Revised Expiry Date : 30-Jan-19 Percent Time Elapse

PROJECT UPDATE
Rel. Wt.
ACCOMPLISHMENT ACCOMPLISHMENT (QTY)
Original
PART DESCRIPTION Unit Unit Cost Contract Amount
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.223 - 0.041 0.264 - 26.400% 0.223 0.041 0.264
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.316 - 0.058 0.374 - 37.400% 0.315 0.058 0.373
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 - - 2.450 - 100.000% 2.350 0.050 2.400
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 - - 1.000 - 100.000% 0.000
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 - - 109.200 - 100.000% 109.200 109.200
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 3,667.241 - 1,604.418 5,271.659 - 46.000% 3,300.00 1,450.00 4,750.00
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 24.400 - 61.000 85.400 - 100.000% 0.000
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% - - - - 0.000% 0.000
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% - - - - 0.000% 0.000
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% - - - - 0.000% 0.000
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% - - - - 0.000% 0.000
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.000
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - - - - 0.000% 0.000
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - - - - 0.000% 0.000
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.223 - 0.041 0.264 - 26.400% 0.223 0.041 0.264
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 0.667 - 0.123 0.790 - 26.333% 0.667 0.123 0.790
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00%
.

PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE
Title MPMIU Resident Engineer Title MPMIU Engineer
Date Date
Form No.

19

side, drainage system, perimeter fence.

mplishment to Date : 4.886% %


: 3.372% %
: 4.383% %
: -0.388% %
: -0.503% %
: 45.000 c.d.
26.316% %

AMOUNT
% ACTUAL TO % SCHEDULED
Previous This Period To date DATE TO DATE

13,149.86 2,417.688 15,567.552 0.031% 0.031%


129,457.53 23,836.625 153,294.160 0.304% 0.305%
393,369.86 8,369.572 401,739.432 0.797% 0.814%
- - - 0.000% 0.106%
54,733.22 - 54,733.224 0.109% 0.109%
1,061,742.00 466,523.000 1,528,265.000 3.033% 3.366%
- - - 0.000% 0.046%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
41,320.22 7,596.990 48,917.207 0.097% 0.097%
5,313.28 979.811 6,293.093 0.012% 0.012%
3.372% 1.012% 4.383% 4.383% 4.886%
SLIPPAGE, +/- -0.503%
1,699,085.98 509,723.686 2,208,809.667

DUDEO C. GALEON
MPMIU Head
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 10
Period Covered OCTOBER 04-10, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital
facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 6.890% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 6.370% %
Contract Duration : 205 C.D. Slippage Previous +/- : -0.575% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -0.520% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 66.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 27.160% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.287 0.034 0.321 16,923.82 2,004.912 18,928.728 0.038% 0.038%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.404 0.058 0.462 166,034.43 23,836.625 189,871.051 0.377% 0.400%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 0.000 - - - 0.000% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 6250 1200.000 7450.000 2,010,875.00 386,088.000 2,396,963.000 4.757% 5.122%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 0.000 - - - 0.000% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 0.000 - - - 0.000% 0.000%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 3200.000 3200.000 - 55,936.000 55,936.000 0.111% 0.091%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 0.000 - - - 0.000% 0.000%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.287 0.034 0.321 53,178.93 6,299.943 59,478.876 0.118% 0.118%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 0.941% 6.370% 6.370% 6.890%
. SLIPPAGE, +/- -0.520%
2,735,752.22 474,165.48 3,209,917.77
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte
Period Covered SEPTEMBER 27 - OCTOBER 03, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date


Revised Contract Amount 50,391,995.74 Previous Accomplishment
Contract Started : 16-May-18 Actual Accomplishment to date
Contract Duration : 205 DAYS Slippage Previous +/-
Contract Expiration : 6-Dec-18 Slippage to Date, +/-
Revised Contract Duration 260 DAYS Contract time Elapsed
Revised Expiry Date : 30-Jan-19 Percent Time Elapse

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY)
Original
PART DESCRIPTION Unit Unit Cost Contract Amount
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.264 0.264 0.041 0.041 0.305 0.305 30.500% 30.500% 0.264 0.041 0.305
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.374 0.373 0.058 0.058 0.432 0.431 43.200% 43.100% 0.373 0.058 0.431
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.500 - 0.050 2.450 2.550 100.000% 104.082% 2.400 0.050 2.450
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 - - 1.000 - 100.000% 0.000% 0.000
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 5,271.659 4,750.000 1,604.418 1,500.000 6,876.077 6,250.000 60.000% 54.537% 4,750.00 1,500.00 6,250.00
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 - - 85.400 - 100.000% 0.000% 0.000
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% - - - - 0.000% 0.000% 0.000
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% - - - - 0.000% 0.000% 0.000
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% - - - - 0.000% 0.000% 0.000
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% - - - - 0.000% 0.000% 0.000
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.000% 0.000
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000% 0.000
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - - - - 0.000% 0.000% 0.000
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000% 0.000
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - - - - 0.000% 0.000% 0.000
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.264 0.264 0.041 0.041 0.305 0.305 30.500% 30.500% 0.264 0.041 0.305
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 0.790 0.790 0.123 0.123 0.913 0.913 30.433% 30.433% 0.790 0.123 0.913
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00%
.

PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE
Title MPMIU Resident Engineer Title MPMIU Engineer
Date Date
Form No.

20

side, drainage system, perimeter fence.

mplishment to Date : 5.980% %


: 4.383% %
: 5.427% %
: -0.503% %
: -0.553% %
: 52.000 c.d.
30.409% %

AMOUNT
% ACTUAL TO % SCHEDULED
Previous This Period To date DATE TO DATE

15,567.55 2,417.688 17,985.240 0.036% 0.036%


153,294.16 23,836.625 177,130.785 0.352% 0.352%
401,739.43 8,369.572 410,109.004 0.814% 0.814%
- - - 0.000% 0.106%
54,733.22 - 54,733.224 0.109% 0.109%
1,528,265.00 482,610.000 2,010,875.000 3.990% 4.390%
- - - 0.000% 0.046%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
- - - 0.000% 0.000%
48,917.21 7,596.990 56,514.197 0.112% 0.112%
6,293.09 979.811 7,272.903 0.014% 0.014%
4.383% 1.043% 5.427% 5.427% 5.980%
SLIPPAGE, +/- -0.553%
2,208,809.67 525,810.686 2,734,620.353

DUDEO C. GALEON
MPMIU Head
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 21
Period Covered OCTOBER 04-10, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 6.871% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 5.427% %
Contract Started : 16-May-18 Actual Accomplishment to date : 6.373% %
Contract Duration : 205 DAYS Slippage Previous +/- : -0.553% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -0.498% %
Revised Contract Duration 260 DAYS Contract time Elapsed : 59.000 c.d.
Revised Expiry Date : 30-Jan-19 Percent Time Elapse 34.503% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date DATE TO DATE
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.305 0.305 0.041 0.041 0.346 0.346 34.600% 34.600% 0.305 0.041 0.346 17,985.24 2,417.688 20,402.928 0.040% 0.040%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.432 0.431 0.058 0.058 0.490 0.489 49.000% 48.900% 0.431 0.058 0.489 177,130.79 23,836.625 200,967.411 0.399% 0.400%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 - - 1.000 - 100.000% 0.000% 0.000 - - - 0.000% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 6,876.077 6,250.000 1,146.013 1,200.000 8,022.090 7,450.000 70.000% 65.008% 6,250.00 1,200.000 7,450.00 2,010,875.00 386,088.000 2,396,963.000 4.757% 5.122%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 - 85.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% - - 2,614.400 3,200.000 2,614.400 3,200.000 6.667% 8.160% 3,200.000 3,200.00 - 55,936.000 55,936.000 0.111% 0.091%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.305 0.305 0.041 0.041 0.346 0.346 34.600% 34.600% 0.305 0.041 0.346 56,514.20 7,596.990 64,111.188 0.127% 0.127%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 0.913 0.913 0.123 0.123 1.036 1.036 34.533% 34.533% 0.913 0.123 1.036 7,272.90 979.811 8,252.714 0.016% 0.016%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 5.427% 0.946% 6.373% 6.373% 6.871%
. SLIPPAGE, +/- -0.498%
2,734,620.35 476,855.114 3,211,475.468
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 11
Period Covered OCTOBER 11-17, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities
such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 8.566% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 7.505% %
Contract Duration : 205 C.D. Slippage Previous +/- : -0.520% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -1.061% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 73.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 30.041% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.321 0.034 0.355 18,928.73 2,004.912 20,933.640 0.042% 0.042%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.462 0.038 0.500 189,871.05 15,617.099 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 0.000 - - - 0.000% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 7450 1350.000 8800.000 2,396,963.00 434,349.000 2,831,312.000 5.619% 5.854%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 0.000 - - - 0.000% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 0.000 - - - 0.000% 0.000%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 3200 6500.000 9700.000 55,936.00 113,620.000 169,556.000 0.336% 0.302%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 0.000 - - - 0.000% 0.708%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.321 0.034 0.355 59,478.88 6,299.943 65,778.820 0.131% 0.131%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 1.135% 7.505% 7.505% 8.566%
. SLIPPAGE, +/- -1.061%
3,209,917.70 571,890.95 3,781,808.73
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 12
Period Covered OCTOBER 18-24, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital
facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 12.964% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 9.496% %
Contract Duration : 205 C.D. Slippage Previous +/- : -1.061% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -3.468% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 80.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 32.922% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.355 0.034 0.389 20,933.64 2,004.912 22,938.552 0.046% 0.046%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 0.000 - - - 0.000% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 8800 1350.000 10150.000 2,831,312.00 434,349.000 3,265,661.000 6.481% 6.585%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 0.000 - - - 0.000% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 200.000 200.000 - 40,396.000 40,396.000 0.080% 0.962%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 9700 7000.000 16700.000 169,556.00 122,360.000 291,916.000 0.579% 0.514%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 500.000 500.000 - 398,090.000 398,090.000 0.790% 3.185%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.355 0.034 0.389 65,778.82 6,299.943 72,078.763 0.143% 0.143%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 1.991% 9.496% 9.496% 12.964%
. SLIPPAGE, +/- -3.468%
3,781,808.66 1,003,499.86 4,785,308.61
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 22
Period Covered OCTOBER 11-17, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 8.548% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 6.373% %
Contract Started : 16-May-18 Actual Accomplishment to date : 7.487% %
Contract Duration : 205 DAYS Slippage Previous +/- : -0.498% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -1.061% %
Revised Contract Duration 260 DAYS Contract time Elapsed : 66.000 c.d.
Revised Expiry Date : 30-Jan-19 Percent Time Elapse 38.596% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date DATE TO DATE
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.346 0.346 0.041 0.041 0.387 0.387 38.700% 38.700% 0.346 0.041 0.387 20,402.93 2,417.688 22,820.616 0.045% 0.045%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.490 0.489 0.005 0.006 0.495 0.495 49.500% 49.500% 0.489 0.006 0.495 200,967.41 2,465.858 203,433.269 0.404% 0.404%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 - - 1.000 - 100.000% 0.000% 0.000 - - - 0.000% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 8,022.090 7,450.000 1,146.013 1,350.000 9,168.103 8,800.000 80.000% 76.788% 7,450.00 1,350.000 8,800.00 2,396,963.00 434,349.000 2,831,312.000 5.619% 5.854%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 - 85.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 2,614.400 3,200.000 6,100.267 6,500.000 8,714.667 9,700.000 22.222% 24.735% 3,200.00 6,500.000 9,700.00 55,936.00 113,620.000 169,556.000 0.336% 0.302%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% - - 447.928 447.928 - 3.774% 0.000% 0.000 - - - 0.000% 0.708%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.346 0.346 0.041 0.041 0.387 0.387 38.700% 38.700% 0.346 0.041 0.387 64,111.19 7,596.990 71,708.178 0.142% 0.142%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 1.036 1.036 0.123 0.123 1.159 1.159 38.633% 38.633% 1.036 0.123 1.159 8,252.71 979.811 9,232.524 0.018% 0.018%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 6.373% 1.114% 7.487% 7.487% 8.548%
. SLIPPAGE, +/- -1.061%
3,211,475.47 561,429.347 3,772,904.815
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 23
Period Covered OCTOBER 18-24, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 12.956% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 7.487% %
Contract Started : 16-May-18 Actual Accomplishment to date : 9.488% %
Contract Duration : 205 DAYS Slippage Previous +/- : -1.061% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -3.468% %
Revised Contract Duration 260 DAYS Contract time Elapsed : 73.000 c.d.
Revised Expiry Date : 30-Jan-19 Percent Time Elapse 42.690% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.387 0.387 0.041 0.041 0.428 0.428 42.800% 42.800% 0.387 0.041 0.428 22,820.62 2,417.688 25,238.304 0.050% 0.050%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.495 0.495 0.005 0.005 0.500 0.500 50.000% 50.000% 0.495 0.005 0.500 203,433.27 2,054.882 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 - - 1.000 - 100.000% 0.000% 0.000 - - - 0.000% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 9,168.103 8,800.000 1,146.013 1,350.000 10,314.116 10,150.000 90.000% 88.568% 8,800.00 1,350.000 10,150.00 2,831,312.00 434,349.000 3,265,661.000 6.481% 6.585%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 - 85.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% - - 2,399.680 200.000 2,399.680 200.000 50.000% 4.167% 200.000 200.000 - 40,396.000 40,396.000 0.080% 0.962%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 8,714.667 9,700.000 6,100.267 7,000.000 14,814.934 16,700.000 37.778% 42.585% 9,700.00 7,000.000 16,700.00 169,556.00 122,360.000 291,916.000 0.579% 0.514%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 447.928 - 1,567.746 500.000 2,015.674 500.000 16.981% 4.212% 500.000 500.00 - 398,090.000 398,090.000 0.790% 3.185%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.387 0.387 0.041 0.041 0.428 0.428 42.800% 42.800% 0.387 0.041 0.428 71,708.18 7,596.990 79,305.169 0.157% 0.157%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 1.159 1.159 0.123 0.123 1.282 1.282 42.733% 42.733% 1.159 0.123 1.282 9,232.52 979.811 10,212.335 0.020% 0.020%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 7.487% 2.001% 9.488% 9.488% 12.956%
. SLIPPAGE, +/- -3.468%
3,772,904.81 1,008,244.371 4,781,149.185
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 13
Period Covered OCTOBER 25-31, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital
facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 15.485% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 11.832% %
Contract Duration : 205 C.D. Slippage Previous +/- : -3.468% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -3.653% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 87.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 35.802% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.389 0.034 0.423 22,938.55 2,004.912 24,943.464 0.049% 0.049%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 0.000 - - - 0.000% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 10150 600.000 10750.000 3,265,661.00 193,044.000 3,458,705.000 6.864% 7.003%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 0.000 - - - 0.000% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 200 500.000 700.000 40,396.00 100,990.000 141,386.000 0.281% 1.511%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 16700 4500.000 21200.000 291,916.00 78,660.000 370,576.000 0.735% 0.635%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 500 1000.000 1500.000 398,090.00 796,180.000 1,194,270.000 2.370% 4.600%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.389 0.034 0.423 72,078.76 6,299.943 78,378.706 0.156% 0.156%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 2.336% 11.832% 11.832% 15.485%
. SLIPPAGE, +/- -3.653%
4,785,308.51 1,177,178.86 5,962,487.49
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 14
Period Covered NOVEMBER 01-07, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities
such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 18.148% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 15.779% %
Contract Duration : 205 C.D. Slippage Previous +/- : -3.653% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -2.369% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 94.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 38.683% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.423 0.034 0.457 24,943.46 2,004.912 26,948.376 0.053% 0.053%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 0.000 - - - 0.000% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 10750 400.000 11150.000 3,458,705.00 128,696.000 3,587,401.000 7.119% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 0.000 - - - 0.000% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 700 500.000 1200.000 141,386.00 100,990.000 242,376.000 0.481% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 21200 4500.000 25700.000 370,576.00 78,660.000 449,236.000 0.891% 0.786%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 1500 2100.000 3600.000 1,194,270.00 1,671,978.000 2,866,248.000 5.688% 6.369%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.423 0.034 0.457 78,378.71 6,299.943 84,678.650 0.168% 0.168%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 3.946% 15.779% 15.779% 18.148%
. SLIPPAGE, +/- -2.369%
5,962,487.37 1,988,628.86 7,951,116.38
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 24
Period Covered OCTOBER 25-28, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 15.472% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 9.488% %
Contract Started : 16-May-18 Actual Accomplishment to date : 11.820% %
Contract Duration : 205 DAYS Slippage Previous +/- : -3.468% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -3.653% %
Revised Contract Duration 21-Sep-00 Contract time Elapsed : 77.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 45.029% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.428 0.428 0.023 0.023 0.451 0.451 45.100% 45.100% 0.428 0.023 0.451 25,238.30 1,356.264 26,594.568 0.053% 0.053%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 - - 1.000 - 100.000% 0.000% 0.000 - - - 0.000% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 10,314.116 10,150.000 654.865 600.000 10,968.981 10,750.000 95.714% 93.803% 10,150.00 600.000 10,750.00 3,265,661.00 193,044.000 3,458,705.000 6.864% 7.003%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 - 85.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 2,399.680 200.000 1,371.246 500.000 3,770.926 700.000 78.571% 14.585% 200.000 500.000 700.00 40,396.00 100,990.000 141,386.000 0.281% 1.511%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 14,814.934 16,700.000 3,485.867 4,500.000 18,300.801 21,200.000 46.667% 54.060% 16,700.00 4,500.000 21,200.00 291,916.00 78,660.000 370,576.000 0.735% 0.635%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 2,015.674 500.000 895.855 1,000.000 2,911.529 1,500.000 24.528% 12.637% 500.00 1,000.000 1,500.00 398,090.00 796,180.000 1,194,270.000 2.370% 4.600%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.428 0.428 0.023 0.023 0.451 0.451 45.100% 45.100% 0.428 0.023 0.451 79,305.17 4,261.726 83,566.895 0.166% 0.166%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 1.282 1.282 0.070 0.070 1.352 1.352 45.067% 45.067% 1.282 0.070 1.352 10,212.34 557.616 10,769.951 0.021% 0.021%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 9.488% 2.332% 11.820% 11.820% 15.472%
. SLIPPAGE, +/- -3.653%
4,781,149.19 1,175,049.606 5,956,198.791
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 25
Period Covered NOVEMBER 03-07, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 18.133% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 11.820% %
Contract Started : 16-May-18 Actual Accomplishment to date : 15.764% %
Contract Duration : 205 DAYS Slippage Previous +/- : -3.653% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -2.369% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 82.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 47.953% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.451 0.451 0.023 0.023 0.474 0.474 47.400% 47.400% 0.451 0.023 0.474 26,594.57 1,356.264 27,950.832 0.055% 0.055%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 - - 1.000 - 100.000% 0.000% 0.000 - - - 0.000% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 10,968.981 10,750.000 491.148 400.000 11,460.129 11,150.000 100.000% 97.294% 10,750.00 400.000 11,150.00 3,458,705.00 128,696.000 3,587,401.000 7.119% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 - 85.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 3,770.926 700.000 1,028.434 500.000 4,799.360 1,200.000 100.000% 25.003% 700.000 500.000 1,200.00 141,386.00 100,990.000 242,376.000 0.481% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 18,300.801 21,200.000 4,357.333 4,500.000 22,658.134 25,700.000 57.778% 65.534% 21,200.00 4,500.000 25,700.00 370,576.00 78,660.000 449,236.000 0.891% 0.786%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 2,911.529 1,500.000 1,119.819 2,100.000 4,031.348 3,600.000 33.962% 30.328% 1,500.00 2,100.000 3,600.00 1,194,270.00 1,671,978.000 2,866,248.000 5.688% 6.369%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.451 0.451 0.029 0.029 0.480 0.480 48.000% 48.000% 0.451 0.029 0.48 83,566.89 5,373.481 88,940.376 0.176% 0.176%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 1.352 1.352 0.088 0.088 1.440 1.440 48.000% 48.000% 1.352 0.088 1.440 10,769.95 701.003 11,470.954 0.023% 0.023%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 11.820% 3.945% 15.764% 15.764% 18.133%
. SLIPPAGE, +/- -2.369%
5,956,198.79 1,987,754.748 7,943,953.539
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 15
Period Covered NOVEMBER 08-14, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such
as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 22.260% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 21.852% %
Contract Duration : 205 C.D. Slippage Previous +/- : -2.369% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -0.408% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 101.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 49.268% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.457 0.034 0.491 26,948.38 2,004.912 28,953.288 0.057% 0.057%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 53,524.800 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11150 100.000 11250.000 3,587,401.00 32,174.000 3,619,575.000 7.183% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 30.000 30.000 - 8,182.500 8,182.500 0.016% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 1200 500.000 1700.000 242,376.00 100,990.000 343,366.000 0.681% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 25700 6500.000 32200.000 449,236.00 113,620.000 562,856.000 1.117% 0.998%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 3600 3000.000 6600.000 2,866,248.00 2,388,540.000 5,254,788.000 10.428% 8.846%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 292.500 292.500 - 355,326.075 355,326.075 0.705% 1.408%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.457 0.034 0.491 84,678.65 6,299.943 90,978.593 0.181% 0.181%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 6.074% 21.852% 21.852% 22.260%
. SLIPPAGE, +/- -0.408%
7,951,116.22 3,060,662.23 11,011,778.67
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 16
Period Covered NOVEMBER 15-21, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities
such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 29.601% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 27.926% %
Contract Duration : 205 C.D. Slippage Previous +/- : -0.408% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -1.675% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 108.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 44.444% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.491 0.034 0.525 28,953.29 2,004.912 30,958.200 0.061% 0.061%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11250 100.000 11350.000 3,619,575.00 32,174.000 3,651,749.000 7.247% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 30 30.000 60.000 8,182.50 8,182.500 16,365.000 0.032% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 1700 1000.000 2700.000 343,366.00 201,980.000 545,346.000 1.082% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 32200 6000.000 38200.000 562,856.00 104,880.000 667,736.000 1.325% 1.209%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 6600 2000.000 8600.000 5,254,788.00 1,592,360.000 6,847,148.000 13.588% 11.323%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 292.5 798.750 1091.250 355,326.08 970,313.513 1,325,639.588 2.631% 5.795%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.005%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.049%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 35.000 35.000 - 142,655.450 142,655.450 0.283% 0.194%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.491 0.034 0.525 90,978.59 6,299.943 97,278.536 0.193% 0.193%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 6.074% 27.926% 27.926% 29.601%
. SLIPPAGE, +/- -1.675%
11,011,778.45 3,060,850.32 14,072,629.05
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 26
Period Covered NOVEMBER 08-14, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 22.252% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 15.764% %
Contract Started : 16-May-18 Actual Accomplishment to date : 21.843% %
Contract Duration : 205 DAYS Slippage Previous +/- : -2.369% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -0.408% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 89.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 52.047% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 0.12% 0.474 0.474 0.041 0.041 0.515 0.515 51.500% 51.500% 0.474 0.041 0.515 27,950.83 2,417.688 30,368.520 0.060% 0.060%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 0.11% 1.000 - - 1.000 1.000 1.000 100.000% 100.000% 1.000 1.000 - 53,524.800 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 7.32% 11,460.129 11,150.000 100.000 11,460.129 11,250.000 100.000% 98.166% 11,150.00 100.000 11,250.00 3,587,401.00 32,174.000 3,619,575.000 7.183% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 0.05% 85.400 - 30.000 85.400 30.000 100.000% 35.129% 30.000 30.000 - 8,182.500 8,182.500 0.016% 0.046%
104 EMBANKMENT 4,799.36 cu.m 1.92% 4,799.360 1,200.000 500.000 4,799.360 1,700.000 100.000% 35.421% 1200.000 500.000 1,700.00 242,376.00 100,990.000 343,366.000 0.681% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 1.36% 22,658.134 25,700.000 6,100.267 6,500.000 28,758.401 32,200.000 73.333% 82.109% 25,700.00 6,500.000 32,200.00 449,236.00 113,620.000 562,856.000 1.117% 0.998%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 18.75% 4,031.348 3,600.000 1,567.746 3,000.000 5,599.094 6,600.000 47.170% 55.602% 3,600.00 3,000.000 6,600.00 2,866,248.00 2,388,540.000 5,254,788.000 10.428% 8.846%
311 PCCP 24,524.95 sq.m. 59.12% - - 583.927 292.500 583.927 292.500 2.381% 1.193% 292.500 292.500 - 355,326.075 355,326.075 0.705% 1.408%
404 REINFORCING STEEL 104.30 kgs. 0.03% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
405 STRUCTURAL CONCRETE 2.40 cu.m 0.09% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 0.35% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
505 GROUTED RIPRAP 286.75 cu.m 1.77% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4.53% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 0.37% 0.480 0.480 0.041 0.041 0.521 0.521 52.100% 52.100% 0.480 0.041 0.521 88,940.38 7,596.990 96,537.366 0.192% 0.192%
SPL-4 BILLBOARD 3.00 each 0.05% 1.440 1.440 0.123 0.123 1.563 1.563 52.100% 52.100% 1.440 0.123 1.563 11,470.95 979.811 12,450.764 0.025% 0.025%
TOTAL CONTRACT AMOUNT 100.00% 15.764% 6.079% 21.843% 21.843% 22.252%
. SLIPPAGE, +/- -0.408%
7,943,953.54 3,063,351.864 11,007,305.403
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certifi

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 17
Period Covered NOVEMBER 22-28, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities
such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 38.135% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 35.248% %
Contract Duration : 205 C.D. Slippage Previous +/- : -1.675% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -2.887% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 115.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 47.325% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.525 0.034 0.559 30,958.20 2,004.912 32,963.112 0.065% 0.065%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11350 50.000 11400.000 3,651,749.00 16,087.000 3,667,836.000 7.279% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 60 10.000 70.000 16,365.00 2,727.500 19,092.500 0.038% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 2700 850.000 3550.000 545,346.00 171,683.000 717,029.000 1.423% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 38200 300.000 38500.000 667,736.00 5,244.000 672,980.000 1.335% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 8600 2000.000 10600.000 6,847,148.00 1,592,360.000 8,439,508.000 16.748% 13.800%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 1091.25 971.250 2062.500 1,325,639.59 1,179,864.788 2,505,504.375 4.972% 10.183%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.013%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 0.000 - - - 0.000% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 35 175.000 210.000 142,655.45 713,277.250 855,932.700 1.699% 1.359%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.525 0.034 0.559 97,278.54 6,299.943 103,578.480 0.206% 0.206%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 7.322% 35.248% 35.248% 38.135%
. SLIPPAGE, +/- -2.887%
14,072,628.77 3,689,548.39 17,762,177.52
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 27
Period Covered NOVEMBER 15-21, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 29.618% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 21.866% %
Contract Started : 16-May-18 Actual Accomplishment to date : 27.944% %
Contract Duration : 205 DAYS Slippage Previous +/- : -0.408% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -1.675% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 96.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 56.140% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.515 0.515 0.041 0.041 0.556 0.556 55.600% 55.600% 0.515 0.041 0.556 30,368.52 2,417.688 32,786.208 0.065% 0.065%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,250.000 100.000 11,460.129 11,350.000 100.000% 99.039% 11,250.00 100.000 11,350.00 3,619,575.00 32,174.000 3,651,749.000 7.247% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 30.000 30.000 85.400 60.000 100.000% 70.258% 30 30.000 60.000 8,182.50 8,182.500 16,365.000 0.032% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 1,700.000 1,000.000 4,799.360 2,700.000 100.000% 56.258% 1,700.00 1,000.000 2,700.00 343,366.00 201,980.000 545,346.000 1.082% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 28,758.401 32,200.000 6,100.267 6,000.000 34,858.668 38,200.000 88.889% 97.409% 32,200.00 6,000.000 38,200.00 562,856.00 104,880.000 667,736.000 1.325% 1.209%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 5,599.094 6,600.000 1,567.746 2,000.000 7,166.840 8,600.000 60.377% 72.451% 6,600.00 2,000.000 8,600.00 5,254,788.00 1,592,360.000 6,847,148.000 13.588% 11.323%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 583.927 292.500 1,820.000 798.750 2,403.927 1,091.250 9.802% 4.450% 292.5 798.750 1,091.25 355,326.08 970,313.513 1,325,639.588 2.631% 5.795%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - 14.900 14.900 - 14.286% 0.000% 0.000 - - - 0.000% 0.005%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - 5.714 5.714 - 14.285% 0.000% 0.000 - - - 0.000% 0.049%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - 24.008 35.000 24.008 35.000 4.286% 6.248% 35.000 35.000 - 142,655.450 142,655.450 0.283% 0.194%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.521 0.521 0.041 0.041 0.562 0.562 56.200% 56.200% 0.521 0.041 0.562 96,537.37 7,596.990 104,134.357 0.207% 0.207%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 1.563 1.563 1.437 1.437 3.000 3.000 100.000% 100.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 21.866% 6.077% 27.944% 27.944% 29.618%
. SLIPPAGE, +/- -1.675%
11,018,752.46 3,062,560.141 14,081,312.600
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 27
Period Covered NOVEMBER 15-21, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 29.618% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 21.866% %
Contract Started : 16-May-18 Actual Accomplishment to date : 27.944% %
Contract Duration : 205 DAYS Slippage Previous +/- : -0.408% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -1.675% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 112.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 65.497% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.515 0.515 0.041 0.041 0.556 0.556 55.600% 55.600% 0.515 0.041 0.556 30,368.52 2,417.688 32,786.208 0.065% 0.065%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,250.000 100.000 11,460.129 11,350.000 100.000% 99.039% 11,250.00 100.000 11,350.00 3,619,575.00 32,174.000 3,651,749.000 7.247% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 30.000 30.000 85.400 60.000 100.000% 70.258% 30 30.000 60.000 8,182.50 8,182.500 16,365.000 0.032% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 1,700.000 1,000.000 4,799.360 2,700.000 100.000% 56.258% 1,700.00 1,000.000 2,700.00 343,366.00 201,980.000 545,346.000 1.082% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 28,758.401 32,200.000 6,100.267 6,000.000 34,858.668 38,200.000 88.889% 97.409% 32,200.00 6,000.000 38,200.00 562,856.00 104,880.000 667,736.000 1.325% 1.209%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 5,599.094 6,600.000 1,567.746 2,000.000 7,166.840 8,600.000 60.377% 72.451% 6,600.00 2,000.000 8,600.00 5,254,788.00 1,592,360.000 6,847,148.000 13.588% 11.323%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 583.927 292.500 1,820.000 798.750 2,403.927 1,091.250 9.802% 4.450% 292.5 798.750 1,091.25 355,326.08 970,313.513 1,325,639.588 2.631% 5.795%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - 14.900 14.900 - 14.286% 0.000% 0.000 - - - 0.000% 0.005%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% - 5.714 5.714 - 14.285% 0.000% 0.000 - - - 0.000% 0.049%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% - 24.008 35.000 24.008 35.000 4.286% 6.248% 35.000 35.000 - 142,655.450 142,655.450 0.283% 0.194%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.521 0.521 0.041 0.041 0.562 0.562 56.200% 56.200% 0.521 0.041 0.562 96,537.37 7,596.990 104,134.357 0.207% 0.207%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 1.563 1.563 1.437 1.437 3.000 3.000 100.000% 100.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 21.866% 6.077% 27.944% 27.944% 29.618%
. SLIPPAGE, +/- -1.675%
11,018,752.46 3,062,560.141 14,081,312.600
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 18
Period Covered NOVEMBER 29-DECEMBER 05, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities
such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 45.091% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 37.439% %
Contract Duration : 205 C.D. Slippage Previous +/- : -2.887% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -7.652% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 122.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 49.796% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.559 0.034 0.593 32,963.11 2,004.912 34,968.024 0.069% 0.069%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11400 50.000 11450.000 3,667,836.00 16,087.000 3,683,923.000 7.311% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 70 10.000 80.000 19,092.50 2,727.500 21,820.000 0.043% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 3550 850.000 4400.000 717,029.00 171,683.000 888,712.000 1.764% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 38500 300.000 38800.000 672,980.00 5,244.000 678,224.000 1.346% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 300.000 9900.000 7,643,328.00 238,854.000 7,882,182.000 15.642% 16.277%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 2062.5 472.500 2535.000 2,505,504.38 573,988.275 3,079,492.650 6.111% 14.570%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 25.000 25.000 - 109,001.000 109,001.000 0.216% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 210 190.000 400.000 855,932.70 774,415.300 1,630,348.000 3.235% 1.359%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.559 0.034 0.593 103,578.48 6,299.943 109,878.423 0.218% 0.218%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 3.771% 37.439% 37.439% 45.091%
. SLIPPAGE, +/- -7.652%
16,965,997.16 1,900,304.93 18,866,302.47
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 28
Period Covered NOVEMBER 22-28, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 38.156% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 27.944% %
Contract Started : 16-May-18 Actual Accomplishment to date : 35.269% %
Contract Duration : 205 DAYS Slippage Previous +/- : -1.675% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -2.887% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 103.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 60.234% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.556 0.556 0.041 0.041 0.597 0.597 59.700% 59.700% 0.556 0.041 0.597 32,786.21 2,417.688 35,203.896 0.070% 0.070%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,350.000 50.000 11,460.129 11,400.000 100.000% 99.475% 11,350.00 50.000 11,400.00 3,651,749.00 16,087.000 3,667,836.000 7.279% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 60.000 10.000 85.400 70.000 100.000% 81.967% 60.000 10.000 70.000 16,365.00 2,727.500 19,092.500 0.038% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 2,700.000 850.000 4,799.360 3,550.000 100.000% 73.968% 2,700.00 850.000 3,550.00 545,346.00 171,683.000 717,029.000 1.423% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 34,858.668 38,200.000 4,357.333 300.000 39,216.001 38,500.000 100.000% 98.174% 38,200.00 300.000 38,500.00 667,736.00 5,244.000 672,980.000 1.335% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 7,166.840 8,600.000 1,567.746 2,000.000 8,734.586 10,600.000 73.585% 89.300% 8,600.00 2,000.000 10,600.00 6,847,148.00 1,592,360.000 8,439,508.000 16.748% 13.800%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 2,403.927 1,091.250 1,820.000 971.250 4,223.927 2,062.500 17.223% 8.410% 1,091.25 971.250 2,062.50 1,325,639.59 1,179,864.788 2,505,504.375 4.972% 10.183%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 14.900 - 89.400 104.300 - 100.000% 0.000% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - 0.343 0.343 - 14.292% 0.000% 0.000 - - - 0.000% 0.013%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 5.714 - 34.286 40.000 - 100.000% 0.000% 0.000 - - - 0.000% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 24.008 35.000 144.049 175.000 168.057 210.000 30.000% 37.487% 35.00 175.000 210.000 142,655.45 713,277.250 855,932.700 1.699% 1.359%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.562 0.562 0.041 0.041 0.603 0.603 60.300% 60.300% 0.562 0.041 0.603 104,134.36 7,596.990 111,731.347 0.222% 0.222%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 3.000 3.000 100.000% 100.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 27.944% 7.325% 35.269% 35.269% 38.156%
. SLIPPAGE, +/- -2.887%
14,081,312.60 3,691,258.216 17,772,570.816
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 28
Period Covered NOVEMBER 22-28, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 38.156% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 27.944% %
Contract Started : 16-May-18 Actual Accomplishment to date : 35.269% %
Contract Duration : 205 DAYS Slippage Previous +/- : -2.219% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -2.887% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 119.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 69.591% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.556 0.556 0.041 0.041 0.597 0.597 59.700% 59.700% 0.556 0.041 0.597 32,786.21 2,417.688 35,203.896 0.070% 0.070%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,350.000 50.000 11,460.129 11,400.000 100.000% 99.475% 11,350.00 50.000 11,400.00 3,651,749.00 16,087.000 3,667,836.000 7.279% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 60.000 10.000 85.400 70.000 100.000% 81.967% 60.000 10.000 70.000 16,365.00 2,727.500 19,092.500 0.038% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 2,700.000 850.000 4,799.360 3,550.000 100.000% 73.968% 2,700.00 850.000 3,550.00 545,346.00 171,683.000 717,029.000 1.423% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 34,858.668 38,200.000 4,357.333 300.000 39,216.001 38,500.000 100.000% 98.174% 38,200.00 300.000 38,500.00 667,736.00 5,244.000 672,980.000 1.335% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 7,166.840 8,600.000 1,567.746 2,000.000 8,734.586 10,600.000 73.585% 89.300% 8,600.00 2,000.000 10,600.00 6,847,148.00 1,592,360.000 8,439,508.000 16.748% 13.800%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 2,403.927 1,091.250 1,820.000 971.250 4,223.927 2,062.500 17.223% 8.410% 1,091.25 971.250 2,062.50 1,325,639.59 1,179,864.788 2,505,504.375 4.972% 10.183%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 14.900 - 89.400 104.300 - 100.000% 0.000% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - 0.343 0.343 - 14.292% 0.000% 0.000 - - - 0.000% 0.013%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 5.714 - 34.286 40.000 - 100.000% 0.000% 0.000 - - - 0.000% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 24.008 35.000 144.049 175.000 168.057 210.000 30.000% 37.487% 35.00 175.000 210.000 142,655.45 713,277.250 855,932.700 1.699% 1.359%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.562 0.562 0.041 0.041 0.603 0.603 60.300% 60.300% 0.562 0.041 0.603 104,134.36 7,596.990 111,731.347 0.222% 0.222%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 3.000 3.000 100.000% 100.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 27.944% 7.325% 35.269% 35.269% 38.156%
. SLIPPAGE, +/- -2.887%
14,081,312.60 3,691,258.216 17,772,570.816
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 29
Period Covered NOVEMBER 29-DECEMBER 05, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 45.139% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 35.269% %
Contract Started : 16-May-18 Actual Accomplishment to date : 41.514% %
Contract Duration : 205 DAYS Slippage Previous +/- : -2.887% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -3.625% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 110.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 64.327% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.597 0.597 0.041 0.041 0.638 0.638 63.800% 63.800% 0.597 0.041 0.638 35,203.90 2,417.688 37,621.584 0.075% 0.075%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,400.000 50.000 11,460.129 11,450.000 100.000% 99.912% 11,400.00 50.000 11,450.00 3,667,836.00 16,087.000 3,683,923.000 7.311% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 70.000 10.000 85.400 80.000 100.000% 93.677% 70.000 10.000 80.000 19,092.50 2,727.500 21,820.000 0.043% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 3,550.000 850.000 4,799.360 4,400.000 100.000% 91.679% 3,550.00 850.000 4,400.00 717,029.00 171,683.000 888,712.000 1.764% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.001 38,500.000 300.000 39,216.001 38,800.000 100.000% 98.939% 38,500.00 300.000 38,800.00 672,980.00 5,244.000 678,224.000 1.346% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 8,734.586 10,600.000 1,567.746 800.000 10,302.332 11,400.000 86.792% 96.040% 10,600.00 750.000 11,350.00 8,439,508.00 597,135.000 9,036,643.000 17.933% 16.277%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 4,233.927 2,062.500 1,820.000 1,202.500 6,053.927 3,265.000 24.685% 13.313% 2,062.50 1202.500 3,265.00 2,505,504.38 1,460,784.975 3,966,289.350 7.871% 14.594%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 104.300 - 104.300 - 100.000% 0.000% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.343 - 2.057 2.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 - 15.000 40.000 15.000 100.000% 37.500% 25.000 25.000 - 109,001.000 109,001.000 0.216% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 168.057 210.000 115.000 168.057 325.000 30.000% 58.016% 210.000 190.000 400.000 855,932.70 774,415.300 1,630,348.000 3.235% 1.359%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.603 0.603 0.041 0.041 0.644 0.644 64.400% 64.400% 0.603 0.041 0.644 111,731.35 7,596.990 119,328.338 0.237% 0.237%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 3.000 3.000 100.000% 100.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 35.269% 6.245% 41.514% 41.514% 45.139%
. SLIPPAGE, +/- -3.625%
17,772,570.82 3,147,092.453 20,919,663.269
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 29
Period Covered NOVEMBER 29-DECEMBER 05, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 45.115% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 35.269% %
Contract Started : 16-May-18 Actual Accomplishment to date : 41.514% %
Contract Duration : 205 DAYS Slippage Previous +/- : -3.723% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -3.601% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 126.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 73.684% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.597 0.597 0.041 0.041 0.638 0.638 63.800% 63.800% 0.597 0.041 0.638 35,203.90 2,417.688 37,621.584 0.075% 0.075%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,400.000 50.000 11,460.129 11,450.000 100.000% 99.912% 11,400.00 50.000 11,450.00 3,667,836.00 16,087.000 3,683,923.000 7.311% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 70.000 10.000 85.400 80.000 100.000% 93.677% 70.000 10.000 80.000 19,092.50 2,727.500 21,820.000 0.043% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 3,550.000 850.000 4,799.360 4,400.000 100.000% 91.679% 3,550.00 850.000 4,400.00 717,029.00 171,683.000 888,712.000 1.764% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.001 38,500.000 300.000 39,216.001 38,800.000 100.000% 98.939% 38,500.00 300.000 38,800.00 672,980.00 5,244.000 678,224.000 1.346% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 8,734.586 10,600.000 1,567.746 750.000 10,302.332 11,350.000 86.792% 95.619% 10,600.00 750.000 11,350.00 8,439,508.00 597,135.000 9,036,643.000 17.933% 16.277%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 4,223.927 2,062.500 1,820.000 1,202.500 6,043.927 3,265.000 24.644% 13.313% 2,062.50 1202.500 3,265.00 2,505,504.38 1,460,784.975 3,966,289.350 7.871% 14.570%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 104.300 - 104.300 - 100.000% 0.000% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.343 - 2.057 2.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 - 15.000 40.000 15.000 100.000% 37.500% 25.000 25.000 - 109,001.000 109,001.000 0.216% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 168.057 210.000 115.000 168.057 325.000 30.000% 58.016% 210.000 190.000 400.000 855,932.70 774,415.300 1,630,348.000 3.235% 1.359%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.603 0.603 0.041 0.041 0.644 0.644 64.400% 64.400% 0.603 0.041 0.644 111,731.35 7,596.990 119,328.338 0.237% 0.237%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 3.000 3.000 100.000% 100.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 35.269% 6.245% 41.514% 41.514% 45.115%
. SLIPPAGE, +/- -3.601%
17,772,570.82 3,147,092.453 20,919,663.269
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 19
Period Covered DECEMBER 06-12, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such
as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 46.074% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 38.326% %
Contract Duration : 205 C.D. Slippage Previous +/- : -7.652% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -7.748% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 123.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 50.617% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.593 0.005 0.598 34,968.02 294.840 35,262.864 0.070% 0.070%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11450 10.129 11460.129 3,683,923.00 3,258.904 3,687,181.904 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 80 5.400 85.400 21,820.00 1,472.850 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4400 300.000 4700.000 888,712.00 60,594.000 949,306.000 1.884% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 38800 300.000 39100.000 678,224.00 5,244.000 683,468.000 1.356% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 16.631%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 2535 487.500 3022.500 3,079,492.65 592,210.125 3,671,702.775 7.286% 15.197%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 15 15.000 30.000 65,400.60 65,400.600 130,801.200 0.260% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 400 400.000 1,630,348.00 - 1,630,348.000 3.235% 1.359%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.593 0.005 0.598 109,878.42 926.462 110,804.885 0.220% 0.220%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 1.447% 38.326% 38.326% 46.074%
. SLIPPAGE, +/- -7.748%
18,583,847.69 729,401.78 19,313,249.86
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 30
Period Covered DECEMBER 06-12, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 52.847% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 40.810% %
Contract Started : 16-May-18 Actual Accomplishment to date : 44.209% %
Contract Duration : 205 DAYS Slippage Previous +/- : -3.625% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -8.639% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 117.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 68.421% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.638 0.638 0.041 0.041 0.679 0.679 67.900% 67.900% 0.638 0.041 0.679 37,621.58 2,417.688 40,039.272 0.079% 0.079%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,450.000 10.129 11,460.129 11,460.129 100.000% 100.000% 11,450.00 10.129 11,460.13 3,683,923.00 3,258.904 3,687,181.904 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 80.000 5.400 85.400 85.400 100.000% 100.000% 80.000 5.400 85.400 21,820.00 1,472.850 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 4,400.000 300.000 4,799.360 4,700.000 100.000% 97.930% 4,400.00 300.000 4,700.00 888,712.00 60,594.000 949,306.000 1.884% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.001 38,500.000 300.000 39,216.001 38,800.000 100.000% 98.939% 38,500.00 300.000 38,800.00 672,980.00 5,244.000 678,224.000 1.346% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 10,302.332 11,350.000 1,567.746 200.000 11,870.078 11,550.000 100.000% 97.303% 11,350.00 200.000 11,550.00 9,036,643.00 159,236.000 9,195,879.000 18.249% 18.754%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 6,053.927 3,265.000 1,820.000 487.500 7,873.927 3,752.500 32.106% 15.301% 3,265.00 487.500 3,752.50 3,966,289.35 592,210.125 4,558,499.475 9.046% 18.982%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 104.300 - 104.300 - 100.000% 0.000% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 2.400 - 2.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 15.000 15.000 40.000 30.000 100.000% 75.000% 15.00 15.000 30.000 65,400.60 65,400.600 130,801.200 0.260% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - 133.817 133.817 - 46.667% 0.000% 0.000 - - - 0.000% 0.824%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 168.057 325.000 200.000 168.057 525.000 30.000% 93.718% 325.000 200.000 525.000 1,324,657.75 815,174.000 2,139,831.750 4.246% 1.359%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.644 0.644 0.041 0.041 0.685 0.685 68.500% 68.500% 0.644 0.041 0.685 119,328.34 7,596.990 126,925.328 0.252% 0.252%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 - 3.000 - 100.000% 0.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 40.810% 3.399% 44.209% 44.209% 52.847%
. SLIPPAGE, +/- -8.639%
20,565,128.62 1,712,605.158 22,277,733.777
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 20
Period Covered DECEMBER 13-19, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital
facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 46.192% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 38.977% %
Contract Duration : 205 C.D. Slippage Previous +/- : -7.748% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -7.215% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 123.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 50.617% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.598 0.598 35,262.86 - 35,262.864 0.070% 0.070%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11460.13 11460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.4 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4700 4700.000 949,306.00 - 949,306.000 1.884% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39100 39100.000 683,468.00 - 683,468.000 1.356% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 16.631%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 3022.5 270.000 3292.500 3,671,702.78 327,993.300 3,999,696.075 7.937% 15.197%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 30 30.000 130,801.20 - 130,801.200 0.260% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.118%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 400 400.000 1,630,348.00 - 1,630,348.000 3.235% 1.359%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.598 0.598 110,804.89 - 110,804.885 0.220% 0.220%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 0.651% 38.977% 38.977% 46.192%
. SLIPPAGE, +/- -7.215%
19,313,249.80 327,993.30 19,641,243.49
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 31
Period Covered DECEMBER 13-19, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 59.004% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 44.209% %
Contract Started : 16-May-18 Actual Accomplishment to date : 45.313% %
Contract Duration : 205 DAYS Slippage Previous +/- : -8.639% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -13.690% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 124.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 72.515% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.679 0.679 0.041 0.041 0.720 0.720 72.000% 72.000% 0.679 0.041 0.720 40,039.27 2,417.688 42,456.960 0.084% 0.084%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,460.129 11,460.129 11,460.129 100.000% 100.000% 11,460.13 11,460.13 3,687,181.90 - 3,687,181.904 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 85.400 85.400 85.400 100.000% 100.000% 85.400 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 4,700.000 50.000 4,799.360 4,750.000 100.000% 98.972% 4,700.00 50.000 4,750.00 949,306.00 10,099.000 959,405.000 1.904% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.001 38,800.000 200.000 39,216.001 39,000.000 100.000% 99.449% 38,800.00 200.000 39,000.00 678,224.00 3,496.000 681,720.000 1.353% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 11,870.078 11,550.000 50.000 11,870.078 11,600.000 100.000% 97.725% 11,550.00 50.000 11,600.00 9,195,879.00 39,809.000 9,235,688.000 18.328% 18.754%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 7,873.927 3,752.500 1,820.000 270.000 9,693.927 4,022.500 39.527% 16.402% 3,752.50 270.000 4,022.50 4,558,499.48 327,993.300 4,886,492.775 9.697% 23.369%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 104.300 - 104.300 - 100.000% 0.000% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 2.400 - 2.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 30.000 5.000 40.000 35.000 100.000% 87.500% 30.00 5.000 35.000 130,801.20 21,800.200 152,601.400 0.303% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 133.817 - 133.817 267.634 - 93.334% 0.000% 0.000 - - - 0.000% 1.648%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 168.057 525.000 114.372 35.190 282.429 560.190 50.417% 100.000% 525.000 35.190 560.190 2,139,831.75 143,429.865 2,283,261.615 4.531% 2.284%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.685 0.685 0.041 0.041 0.726 0.726 72.600% 72.600% 0.685 0.041 0.726 126,925.33 7,596.990 134,522.319 0.267% 0.267%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 - 3.000 - 100.000% 0.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 44.209% 1.105% 45.313% 45.313% 59.004%
. SLIPPAGE, +/- -13.690%
22,277,733.78 556,642.044 22,834,375.821
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 21
Period Covered DECEMBER 20-26, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital
facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 46.074% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 38.977% %
Contract Duration : 205 C.D. Slippage Previous +/- : -7.215% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -7.097% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 123.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 50.617% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.598 0.598 35,262.86 - 35,262.864 0.070% 0.070%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11460.13 11460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.4 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4700 4700.000 949,306.00 - 949,306.000 1.884% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39100 39100.000 683,468.00 - 683,468.000 1.356% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 16.631%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 3292.5 3292.500 3,999,696.08 - 3,999,696.075 7.937% 15.197%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 30 30.000 130,801.20 - 130,801.200 0.260% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 400 400.000 1,630,348.00 - 1,630,348.000 3.235% 1.359%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.598 0.598 110,804.89 - 110,804.885 0.220% 0.220%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 0.000% 38.977% 38.977% 46.074%
. SLIPPAGE, +/- -7.097%
19,641,243.10 - 19,641,243.49
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 22
Period Covered DECEMBER 27, 2018 - JANUARY 02, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities
such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 46.074% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 40.110% %
Contract Duration : 205 C.D. Slippage Previous +/- : -7.097% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -5.964% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 123.000 c.d.
Revised Expiry Date : 26-Feb-19 Percent Time Elapse 50.617% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.598 0.598 35,262.86 - 35,262.864 0.070% 0.070%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11460.13 11460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.4 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4700 4700.000 949,306.00 - 949,306.000 1.884% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39100 39100.000 683,468.00 - 683,468.000 1.356% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 16.631%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 3292.5 470.000 3762.500 3,999,696.08 570,951.300 4,570,647.375 9.070% 15.197%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 30 30.000 130,801.20 - 130,801.200 0.260% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 400 400.000 1,630,348.00 - 1,630,348.000 3.235% 1.359%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.598 0.598 110,804.89 - 110,804.885 0.220% 0.220%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 1.133% 40.110% 40.110% 46.074%
. SLIPPAGE, +/- -5.964%
19,641,243.10 570,951.30 20,212,194.80
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 32
Period Covered DECEMBER 20-26, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 64.454% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 45.313% %
Contract Started : 16-May-18 Actual Accomplishment to date : 45.479% %
Contract Duration : 205 DAYS Slippage Previous +/- : -15.438% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -18.975% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 131.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 76.608% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.720 0.720 0.041 0.041 0.761 0.761 76.100% 76.100% 0.72 0.041 0.761 42,456.96 2,417.688 44,874.648 0.089% 0.089%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,460.129 11,460.129 11,460.129 100.000% 100.000% 11,460.13 11,460.13 3,687,181.90 - 3,687,181.904 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 85.400 85.400 85.400 100.000% 100.000% 85.400 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 4,750.000 49.360 4,799.360 4,799.360 100.000% 100.000% 4,750.00 49.360 4,799.36 959,405.00 9,969.733 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.001 39,000.000 100.000 39,216.001 39,100.000 100.000% 99.704% 39,000.00 100.000 39,100.00 681,720.00 1,748.000 683,468.000 1.356% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 11,870.078 11,600.000 50.000 11,870.078 11,650.000 100.000% 98.146% 11,600.00 50.000 11,650.00 9,235,688.00 39,809.000 9,275,497.000 18.407% 18.754%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 9,693.927 4,022.500 1,820.000 - 11,513.927 4,022.500 46.948% 16.402% 4,022.50 4,022.50 4,886,492.78 - 4,886,492.775 9.697% 27.756%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 104.300 - 104.300 - 100.000% 0.000% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 2.400 - 2.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 35.000 5.000 40.000 40.000 100.000% 100.000% 35.00 5.000 40.000 152,601.40 21,800.200 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 267.634 - 19.117 286.751 - 100.000% 0.000% 0.000 - - - 0.000% 1.765%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 282.429 560.190 114.372 - 396.801 560.190 70.833% 100.000% 560.190 560.190 2,283,261.62 - 2,283,261.615 4.531% 3.209%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.726 0.726 0.041 0.041 0.767 0.767 76.700% 76.700% 0.726 0.041 0.767 134,522.32 7,596.990 142,119.309 0.282% 0.282%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 - 3.000 - 100.000% 0.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 45.313% 0.165% 45.479% 45.479% 64.454%
. SLIPPAGE, +/- -18.975%
22,834,375.82 83,341.611 22,917,717.432
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 33
Period Covered DECEMBER 27, 2018 - JANUARY 02, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 69.786% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 45.436% %
Contract Started : 16-May-18 Actual Accomplishment to date : 46.997% %
Contract Duration : 205 DAYS Slippage Previous +/- : -18.975% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -22.789% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 138.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 80.702% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.761 0.761 0.041 0.041 0.802 0.802 80.200% 80.200% 0.761 0.041 0.802 44,874.65 2,417.688 47,292.336 0.094% 0.094%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,460.129 11,460.129 11,460.129 100.000% 100.000% 11,460.13 11,460.13 3,687,181.90 - 3,687,181.904 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 85.400 85.400 85.400 100.000% 100.000% 85.400 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 4,799.360 4,799.360 4,799.360 100.000% 100.000% 4,800.00 4,800.00 969,504.00 - 969,504.000 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.001 39,100.000 50.000 39,216.001 39,150.000 100.000% 99.832% 39,100.00 50.000 39,150.00 683,468.00 874.000 684,342.000 1.358% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 11,870.078 11,650.000 50.000 11,870.078 11,700.000 100.000% 98.567% 11,650.00 50.000 11,700.00 9,275,497.00 39,809.000 9,315,306.000 18.486% 18.754%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 11,513.927 4,022.500 1,820.000 470.000 13,333.927 4,492.500 54.369% 18.318% 4,022.50 470.000 4,492.50 4,886,492.78 570,951.300 5,457,444.075 10.830% 32.144%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 104.300 - 104.300 - 100.000% 0.000% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 2.400 - 2.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 40.000 40.000 40.000 100.000% 100.000% 35.00 5.000 40.000 152,601.40 21,800.200 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 286.751 - 286.751 - 100.000% 0.000% 0.000 - - - 0.000% 1.765%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 396.801 560.190 114.372 - 511.173 560.190 91.250% 100.000% 560.190 35.190 595.380 2,283,261.62 143,429.865 2,426,691.481 4.816% 4.135%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.767 0.767 0.041 0.041 0.808 0.808 80.800% 80.800% 0.767 0.041 0.808 142,119.31 7,596.990 149,716.300 0.297% 0.297%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 - 3.000 - 100.000% 0.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 45.436% 1.562% 46.997% 46.997% 69.786%
. SLIPPAGE, +/- -22.789%
22,896,046.50 786,879.044 23,682,925.543
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 23
Period Covered JANUARY 03 - 09, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital
facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 48.986% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 42.345% %
Contract Duration : 205 C.D. Slippage Previous +/- : -5.964% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -6.641% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 126.000 c.d.
Revised Expiry Date : 29-Mar-19 Percent Time Elapse 51.852% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.598 0.015 0.613 35,262.86 884.520 36,147.384 0.072% 0.072%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11460.13 11460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.4 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4700 50.000 4750.000 949,306.00 10,099.000 959,405.000 1.904% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39100 50.000 39150.000 683,468.00 874.000 684,342.000 1.358% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 17.693%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 3762.5 543.750 4306.250 4,570,647.38 660,542.063 5,231,189.438 10.381% 16.643%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 30 10.000 40.000 130,801.20 43,600.400 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 400 100.000 500.000 1,630,348.00 407,587.000 2,037,935.000 4.044% 1.756%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.598 0.015 0.613 110,804.89 2,779.387 113,584.272 0.225% 0.225%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 2.235% 42.345% 42.345% 48.986%
. SLIPPAGE, +/- -6.641%
20,212,194.40 1,126,366.37 21,338,561.19
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 34
Period Covered JANUARY 03 - 09, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 74.590% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 46.713% %
Contract Started : 16-May-18 Actual Accomplishment to date : 48.121% %
Contract Duration : 205 DAYS Slippage Previous +/- : -22.789% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -26.469% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 145.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 84.795% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.802 0.802 0.041 0.041 0.843 0.843 84.300% 84.300% 0.802 0.041 0.843 47,292.34 2,417.688 49,710.024 0.099% 0.099%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,460.129 11,460.129 11,460.129 100.000% 100.000% 11,460.13 11,460.13 3,687,181.90 - 3,687,181.904 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 85.400 85.400 85.400 100.000% 100.000% 85.400 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 4,799.360 4,799.360 4,799.360 100.000% 100.000% 4,800.00 4,800.00 969,504.00 - 969,504.000 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.001 39,150.000 50.000 39,216.001 39,200.000 100.000% 99.959% 39,150.00 50.000 39,200.00 684,342.00 874.000 685,216.000 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 11,870.078 11,700.000 50.000 11,870.078 11,750.000 100.000% 98.988% 11,700.00 50.000 11,750.00 9,315,306.00 39,809.000 9,355,115.000 18.565% 18.754%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 13,333.927 4,492.500 1,820.000 542.500 15,153.927 5,035.000 61.790% 20.530% 4,492.50 542.500 5,035.00 5,457,444.08 659,023.575 6,116,467.650 12.138% 36.531%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 104.300 - 104.300 - 100.000% 0.000% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 2.400 - 2.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 40.000 40.000 40.000 100.000% 100.000% 40.00 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 286.751 - 286.751 - 100.000% 0.000% 0.000 - - - 0.000% 1.765%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 511.173 560.190 49.017 - 560.190 560.190 100.000% 100.000% 560.190 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.808 0.808 0.041 0.041 0.849 0.849 84.900% 84.900% 0.808 0.041 0.849 149,716.30 7,596.990 157,313.290 0.312% 0.312%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 - 3.000 - 100.000% 0.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 46.713% 1.408% 48.121% 48.121% 74.590%
. SLIPPAGE, +/- -26.469%
23,539,495.68 709,721.253 24,249,216.931
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 24
Period Covered JANUARY 10-16, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such
as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 54.364% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 45.754% %
Contract Duration : 205 C.D. Slippage Previous +/- : -6.641% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -8.610% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 133.000 c.d.
Revised Expiry Date : 29-Mar-19 Percent Time Elapse 54.733% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.613 0.034 0.647 36,147.38 2,004.912 38,152.296 0.076% 0.076%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11460.13 11460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.4 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4750 49.360 4799.360 959,405.00 9,969.733 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39150 66.000 39216.000 684,342.00 1,153.680 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 18.754%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 4306.25 1196.250 5502.500 5,231,189.44 1,453,192.538 6,684,381.975 13.265% 20.018%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 500 60.190 560.190 2,037,935.00 245,326.615 2,283,261.615 4.531% 2.681%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.613 0.034 0.647 113,584.27 6,299.943 119,884.215 0.238% 0.238%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 3.409% 45.754% 45.754% 54.364%
. SLIPPAGE, +/- -8.610%
21,338,560.77 1,717,947.42 23,056,508.65
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post
*ROW

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 35
Period Covered JANUARY 10-16, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 81.548% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 48.121% %
Contract Started : 16-May-18 Actual Accomplishment to date : 51.104% %
Contract Duration : 205 DAYS Slippage Previous +/- : -26.469% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -30.444% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 152.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 88.889% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.843 0.843 0.041 0.041 0.884 0.884 88.400% 88.400% 0.843 0.041 0.884 49,710.02 2,417.688 52,127.712 0.103% 0.103%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.071 0.571 0.500 57.100% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.466%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,460.129 11,460.129 11,460.129 100.000% 100.000% 11,460.13 11,460.13 3,687,181.90 - 3,687,181.904 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 85.400 85.400 85.400 100.000% 100.000% 85.400 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 4,799.360 4,799.360 4,799.360 100.000% 100.000% 4,800.00 4,800.00 969,504.00 - 969,504.000 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.001 39,200.000 16.000 39,216.001 39,216.000 100.000% 100.000% 39,200.00 16.000 39,216.00 685,216.00 279.680 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 11,870.078 11,750.000 50.000 11,870.078 11,800.000 100.000% 99.410% 11,750.00 50.000 11,800.00 9,355,115.00 39,809.000 9,394,924.000 18.644% 18.754%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 15,153.927 5,035.000 2,525.970 1,196.250 17,679.897 6,231.250 72.089% 25.408% 5,035.00 1196.250 6,231.25 6,116,467.65 1,453,192.538 7,569,660.188 15.022% 42.621%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 104.300 - 104.300 - 100.000% 0.000% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 2.400 - 2.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 40.000 40.000 40.000 100.000% 100.000% 40.00 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 286.751 - 286.751 - 100.000% 0.000% 0.000 - - - 0.000% 1.765%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.190 560.190 - 560.190 560.190 100.000% 100.000% 560.190 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - 12.000 12.000 - 28.571% 0.000% 0.000 - - - 0.000% 0.218%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - 1.000 1.000 - 50.000% 0.000% 0.000 - - - 0.000% 0.032%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - 122.625 122.625 - 50.000% 0.000% 0.000 - - - 0.000% 0.327%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - 12.000 12.000 - 25.000% 0.000% 0.000 - - - 0.000% 0.214%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.849 0.849 0.041 0.041 0.890 0.890 89.000% 89.000% 0.849 0.041 0.89 157,313.29 7,596.990 164,910.281 0.327% 0.327%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 - 3.000 - 100.000% 0.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 48.121% 2.983% 51.104% 51.104% 81.548%
. SLIPPAGE, +/- -30.444%
24,249,216.93 1,503,295.896 25,752,512.827
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 25
Period Covered JANUARY 17-23, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities
such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 58.681% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 50.375% %
Contract Duration : 205 C.D. Slippage Previous +/- : -8.610% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -8.305% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 140.000 c.d.
Revised Expiry Date : 29-Mar-19 Percent Time Elapse 57.613% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.647 0.034 0.681 38,152.30 2,004.912 40,157.208 0.080% 0.080%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11460.13 11460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.4 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4799.36 4799.360 969,374.73 - 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39216 39216.000 685,495.68 - 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 18.754%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 5502.5 1910.000 7412.500 6,684,381.98 2,320,248.900 9,004,630.875 17.869% 23.393%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.19 560.190 2,283,261.62 - 2,283,261.615 4.531% 3.606%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.647 0.034 0.681 119,884.22 6,299.943 126,184.158 0.250% 0.250%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 4.621% 50.375% 50.375% 58.681%
. SLIPPAGE, +/- -8.305%
23,056,508.19 2,328,553.76 25,385,062.45
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 26
Period Covered JANUARY 24-30, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities
such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 62.997% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 54.984% %
Contract Duration : 205 C.D. Slippage Previous +/- : -8.305% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -8.013% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 147.000 c.d.
Revised Expiry Date : 29-Mar-19 Percent Time Elapse 60.494% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.681 0.034 0.715 40,157.21 2,004.912 42,162.120 0.084% 0.084%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11460.13 11460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.4 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4799.36 4799.360 969,374.73 - 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39216 39216.000 685,495.68 - 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 18.754%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 7412.5 1905.000 9317.500 9,004,630.88 2,314,174.950 11,318,805.825 22.462% 26.768%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.19 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.681 0.034 0.715 126,184.16 6,299.943 132,484.102 0.263% 0.263%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 4.609% 54.984% 54.984% 62.997%
. SLIPPAGE, +/- -8.013%
25,385,061.94 2,322,479.81 27,707,542.30
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 27
Period Covered JANUARY 31 - FEBRUARY 06, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities
such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 66.389% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 58.024% %
Contract Duration : 205 C.D. Slippage Previous +/- : -8.013% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -8.364% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 154.000 c.d.
Revised Expiry Date : 29-Mar-19 Percent Time Elapse 63.374% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.715 0.034 0.749 42,162.12 2,004.912 44,167.032 0.088% 0.088%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11460.13 11460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.4 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4799.36 4799.360 969,374.73 - 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39216 39216.000 685,495.68 - 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 18.754%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 9317.5 1254.250 10571.750 11,318,805.83 1,523,650.358 12,842,456.183 25.485% 30.143%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.19 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.715 0.034 0.749 132,484.10 6,299.943 138,784.045 0.275% 0.275%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 3.040% 58.024% 58.024% 66.389%
. SLIPPAGE, +/- -8.364%
27,707,541.75 1,531,955.21 29,239,497.54
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 28
Period Covered FEBRUARY 07-13, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such
as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 69.780% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 61.358% %
Contract Duration : 205 C.D. Slippage Previous +/- : -8.364% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -8.422% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 161.000 c.d.
Revised Expiry Date : 29-Mar-19 Percent Time Elapse 66.255% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.749 0.034 0.783 44,167.03 2,004.912 46,171.944 0.092% 0.092%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11460.13 11460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.4 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4799.36 4799.360 969,374.73 - 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39216 39216.000 685,495.68 - 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 18.754%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 10571.75 1376.130 11947.880 12,842,456.18 1,671,708.963 14,514,165.145 28.803% 33.518%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.19 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.749 0.034 0.783 138,784.05 6,299.943 145,083.988 0.288% 0.288%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 3.334% 61.358% 61.358% 69.780%
. SLIPPAGE, +/- -8.422%
29,239,496.96 1,680,013.82 30,919,511.39
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 29
Period Covered FEBRUARY 14-20, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such
as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 72.806% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 64.888% %
Contract Duration : 205 C.D. Slippage Previous +/- : -8.422% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -7.918% %
Revised Contract Duration 205 C.D. Contract time Elapsed : 168.000 c.d.
Revised Expiry Date : 29-Mar-19 Percent Time Elapse 69.136% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.783 0.023 0.806 46,171.94 1,356.264 47,528.208 0.094% 0.094%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11460.13 11460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.4 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4799.36 4799.360 969,374.73 - 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39216 39216.000 685,495.68 - 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 18.754%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 11947.88 1459.880 13407.760 14,514,165.15 1,773,447.625 16,287,612.770 32.322% 36.533%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.19 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.783 0.023 0.806 145,083.99 4,261.726 149,345.715 0.296% 0.296%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 3.530% 64.888% 64.888% 72.806%
. SLIPPAGE, +/- -7.918%
30,919,510.78 1,779,065.62 32,698,577.04
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 30
Period Covered FEBRUARY 21-27, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such
as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 75.407% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 16-May-18 Actual Accomplishment to date : 68.486% %
Contract Duration : 205 DAYS Slippage Previous +/- : -7.918% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -6.922% %
Revised Contract Duration 260 DAYS Contract time Elapsed : 175.000 c.d.
Revised Expiry Date : 30-Jan-19 Percent Time Elapse 72.016% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.806 0.018 0.824 47,528.21 1,061.424 48,589.632 0.096% 0.096%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11460.13 11460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.4 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4799.36 4799.360 969,374.73 - 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39216 39216.000 685,495.68 - 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 18.754%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 13407.76 1488.630 14896.390 16,287,612.77 1,808,372.838 18,095,985.608 35.910% 39.125%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.19 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.806 0.018 0.824 149,345.71 3,335.264 152,680.979 0.303% 0.303%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 3.597% 68.486% 68.486% 75.407%
. SLIPPAGE, +/- -6.922%
32,698,576.39 1,812,769.53 34,511,346.61
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 31
Period Covered FEBRUARY 28 - MARCH 6, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such
as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 78.008% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 72.139% %
Contract Duration : 205 C.D. Slippage Previous +/- : -6.922% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -5.870% %
Revised Contract Duration 243 C.D. Contract time Elapsed : 182.000 c.d.
Revised Expiry Date : 6-May-19 Percent Time Elapse 74.897% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.824 0.018 0.842 48,589.63 1,061.424 49,651.056 0.099% 0.099%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11460.13 11460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.4 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4799.36 4799.360 969,374.73 - 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39216 39216.000 685,495.68 - 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 18.754%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 14896.39 1511.630 16408.020 18,095,985.61 1,836,313.008 19,932,298.616 39.554% 41.718%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.19 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.824 0.018 0.842 152,680.98 3,335.264 156,016.243 0.310% 0.310%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 3.653% 72.139% 72.139% 78.008%
. SLIPPAGE, +/- -5.870%
34,511,345.92 1,840,709.70 36,352,056.34
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 32
Period Covered MARCH 07-13, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such
as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 80.609% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 73.558% %
Contract Duration : 205 C.D. Slippage Previous +/- : -5.597% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -7.051% %
Revised Contract Duration 243 C.D. Contract time Elapsed : 189.000 c.d.
Revised Expiry Date : 6-May-19 Percent Time Elapse 77.778% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.842 0.018 0.86 49,651.06 1,061.424 50,712.480 0.101% 0.101%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11460.13 11460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.4 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4799.36 4799.360 969,374.73 - 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39216 39216.000 685,495.68 - 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 18.754%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 16408.02 585.000 16993.020 19,932,298.62 710,652.150 20,642,950.766 40.965% 44.310%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.19 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.842 0.018 0.86 156,016.24 3,335.264 159,351.507 0.316% 0.316%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 1.419% 73.558% 73.558% 80.609%
. SLIPPAGE, +/- -7.051%
36,352,055.62 715,048.84 37,067,105.19
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 32
Period Covered AS OF MARCH 15, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such
as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 80.609% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 74.680% %
Contract Duration : 205 C.D. Slippage Previous +/- : -5.597% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -5.929% %
Revised Contract Duration 243 C.D. Contract time Elapsed : 189.000 c.d.
Revised Expiry Date : 6-May-19 Percent Time Elapse 77.778% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.842 0.018 0.86 49,651.06 1,061.424 50,712.480 0.101% 0.101%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.5 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.45 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.2 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11460.13 11460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.4 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4799.36 4799.360 969,374.73 - 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39216 39216.000 685,495.68 - 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9600 9600.000 7,643,328.00 - 7,643,328.000 15.168% 18.754%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 16408.02 1050.630 17458.650 19,932,298.62 1,276,294.818 21,208,593.434 42.087% 44.310%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.19 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.842 0.018 0.86 156,016.24 3,335.264 159,351.507 0.316% 0.316%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 2.541% 74.680% 74.680% 80.609%
. SLIPPAGE, +/- -5.929%
36,352,055.62 1,280,691.51 37,632,747.87
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 33
Period Covered MARCH 14-20, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as
road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 83.210% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 75.792% %
Contract Duration : 205 C.D. Slippage Previous +/- : -7.051% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -7.418% %
Revised Contract Duration 243 C.D. Contract time Elapsed : 196.000 c.d.
Revised Expiry Date : 6-May-19 Percent Time Elapse 80.658% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.860 0.018 0.878 50,712.48 1,061.424 51,773.904 0.103% 0.103%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.130 11,460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 4,799.360 969,374.73 - 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.000 39,216.000 685,495.68 - 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9,600.000 9,600.000 7,643,328.00 - 7,643,328.000 15.168% 18.754%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 16,993.020 923.130 17,916.150 20,642,950.77 1,121,409.093 21,764,359.859 43.190% 46.902%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.190 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.860 0.018 0.878 159,351.51 3,335.264 162,686.771 0.323% 0.323%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 2.234% 75.792% 75.792% 83.210%
. SLIPPAGE, +/- -7.418%
37,067,104.45 1,125,805.78 38,192,910.99
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 34
Period Covered MARCH 21-27, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as
road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 85.811% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 77.397% %
Contract Duration : 205 C.D. Slippage Previous +/- : -7.418% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -8.413% %
Revised Contract Duration 243 C.D. Contract time Elapsed : 203.000 c.d.
Revised Expiry Date : 6-May-19 Percent Time Elapse 83.539% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.878 0.018 0.896 51,773.90 1,061.424 52,835.328 0.105% 0.105%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.130 11,460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 4,799.360 969,374.73 - 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.000 39,216.000 685,495.68 - 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9,600.000 9,600.000 7,643,328.00 - 7,643,328.000 15.168% 18.754%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 17,916.150 662.500 18,578.650 21,764,359.86 804,798.375 22,569,158.234 44.787% 49.494%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.000%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.190 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.878 0.018 0.896 162,686.77 3,335.264 166,022.035 0.329% 0.329%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 1.606% 77.397% 77.397% 85.811%
. SLIPPAGE, +/- -8.413%
38,192,910.24 809,195.06 39,002,106.07
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 35
Period Covered MARCH 28 - APRIL 03, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as
road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 88.765% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 79.624% %
Contract Duration : 205 C.D. Slippage Previous +/- : -8.413% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -9.141% %
Revised Contract Duration 243 C.D. Contract time Elapsed : 210.000 c.d.
Revised Expiry Date : 6-May-19 Percent Time Elapse 86.420% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.896 0.018 0.914 52,835.33 1,061.424 53,896.752 0.107% 0.107%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.130 11,460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 4,799.360 969,374.73 - 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.000 39,216.000 685,495.68 - 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9,600.000 9,600.000 7,643,328.00 - 7,643,328.000 15.168% 18.754%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 18,578.650 920.000 19,498.650 22,569,158.23 1,117,606.800 23,686,765.034 47.005% 52.086%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 0.353%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.190 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.896 0.018 0.914 166,022.04 3,335.264 169,357.299 0.336% 0.336%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 2.227% 79.624% 79.624% 88.765%
. SLIPPAGE, +/- -9.141%
39,002,105.30 1,122,003.49 40,124,109.58
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 36
Period Covered APRIL 04-10, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :
The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as
road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 92.153% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 0.000% %
Contract Started : 9-May-18 Actual Accomplishment to date : 80.482% %
Contract Duration : 205 C.D. Slippage Previous +/- : -9.141% %
Contract Expiration : 29-Nov-18 Slippage to Date, +/- : -11.670% %
Revised Contract Duration 243 C.D. Contract time Elapsed : 217.000 c.d.
Revised Expiry Date : 6-May-19 Percent Time Elapse 89.300% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.914 0.018 0.932 53,896.75 1,061.424 54,958.176 0.109% 0.109%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.130 11,460.130 3,687,182.23 - 3,687,182.226 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 4,799.360 969,374.73 - 969,374.733 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.000 39,216.000 685,495.68 - 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 9,600.000 9,600.000 7,643,328.00 - 7,643,328.000 15.168% 18.754%
311 PCCP 24,524.95 cu.m 1,214.79 29,792,664.01 59.12% 19,498.650 352.500 19,851.150 23,686,765.03 428,213.475 24,114,978.509 47.855% 54.678%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% - - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% - - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - - - 0.000% 1.140%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.190 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE) 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.914 0.018 0.932 169,357.30 3,335.264 172,692.563 0.343% 0.343%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 0.858% 80.482% 80.482% 92.153%
. SLIPPAGE, +/- -11.670%
40,124,108.79 432,610.16 40,556,719.75
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 36
Period Covered JANUARY 17-23, 2019
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities
such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 88.185% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 51.104% %
Contract Started : 16-May-18 Actual Accomplishment to date : 55.808% %
Contract Duration : 205 DAYS Slippage Previous +/- : -30.386% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -32.378% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 157.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 91.813% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount
Quantity Previous This Period To Date Previous This Period To date DATE TO DATE
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.884 0.041 0.925 52,127.71 2,417.688 54,545.400 0.108% 0.108%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.670%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE) 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.13 11,460.13 3,687,181.90 - 3,687,181.904 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 85.400 23,292.85 - 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,800.00 4,800.00 969,504.00 - 969,504.000 1.924% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.00 39,216.00 685,495.68 - 685,495.680 1.360% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 11,800.00 50.000 11,850.00 9,394,924.00 39,809.000 9,434,733.000 18.723% 18.754%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 6,231.25 1910.000 8,141.25 7,569,660.19 2,320,248.900 9,889,909.088 19.626% 48.710%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.00 40.000 174,401.60 - 174,401.600 0.346% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 0.000 - - - 0.000% 1.765%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 560.190 560.190 2,283,261.62 - 2,283,261.615 4.531% 4.531%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% 0.000 - - - 0.000% 0.381%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% 0.000 - - - 0.000% 0.032%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% 0.000 - - - 0.000% 0.327%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% 0.000 - - - 0.000% 0.375%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.890 0.041 0.931 164,910.28 7,596.990 172,507.271 0.342% 0.342%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 51.104% 4.703% 55.808% 55.808% 88.185%
. SLIPPAGE, +/- -32.378%
25,752,512.83 2,370,072.578 28,122,585.406
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"
Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 30
Period Covered DECEMBER 06-12, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 52.823% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 40.810% %
Contract Started : 16-May-18 Actual Accomplishment to date : 44.209% %
Contract Duration : 205 DAYS Slippage Previous +/- : -4.977% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -8.614% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 133.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 77.778% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.638 0.638 0.041 0.041 0.679 0.679 67.900% 67.900% 0.638 0.041 0.679 37,621.58 2,417.688 40,039.272 0.079% 0.079%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,450.000 10.129 11,460.129 11,460.129 100.000% 100.000% 11,450.00 10.129 11,460.13 3,683,923.00 3,258.904 3,687,181.904 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 80.000 5.400 85.400 85.400 100.000% 100.000% 80.000 5.400 85.400 21,820.00 1,472.850 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 4,400.000 300.000 4,799.360 4,700.000 100.000% 97.930% 4,400.00 300.000 4,700.00 888,712.00 60,594.000 949,306.000 1.884% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.001 38,500.000 300.000 39,216.001 38,800.000 100.000% 98.939% 38,500.00 300.000 38,800.00 672,980.00 5,244.000 678,224.000 1.346% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 10,302.332 11,350.000 1,567.746 200.000 11,870.078 11,550.000 100.000% 97.303% 11,350.00 200.000 11,550.00 9,036,643.00 159,236.000 9,195,879.000 18.249% 18.754%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 6,043.927 3,265.000 1,820.000 487.500 7,863.927 3,752.500 32.065% 15.301% 3,265.00 487.500 3,752.50 3,966,289.35 592,210.125 4,558,499.475 9.046% 18.957%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 104.300 - 104.300 - 100.000% 0.000% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 2.400 - 2.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 15.000 15.000 40.000 30.000 100.000% 75.000% 15.00 15.000 30.000 65,400.60 65,400.600 130,801.200 0.260% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% - - 133.817 133.817 - 46.667% 0.000% 0.000 - - - 0.000% 0.824%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 168.057 325.000 200.000 168.057 525.000 30.000% 93.718% 325.000 200.000 525.000 1,324,657.75 815,174.000 2,139,831.750 4.246% 1.359%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.644 0.644 0.041 0.041 0.685 0.685 68.500% 68.500% 0.644 0.041 0.685 119,328.34 7,596.990 126,925.328 0.252% 0.252%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 - 3.000 - 100.000% 0.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 40.810% 3.399% 44.209% 44.209% 52.823%
. SLIPPAGE, +/- -8.614%
20,565,128.62 1,712,605.158 22,277,733.777
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 31
Period Covered DECEMBER 13-19, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 58.980% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 41.986% %
Contract Started : 16-May-18 Actual Accomplishment to date : 45.357% %
Contract Duration : 205 DAYS Slippage Previous +/- : -4.977% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -13.623% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 140.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 81.871% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.679 0.638 0.041 0.041 0.720 0.679 72.000% 67.900% 0.638 0.041 0.679 37,621.58 2,417.688 40,039.272 0.079% 0.084%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,450.000 10.129 11,460.129 11,460.129 100.000% 100.000% 11,450.00 10.129 11,460.13 3,683,923.00 3,258.904 3,687,181.904 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 80.000 5.400 85.400 85.400 100.000% 100.000% 80.000 5.400 85.400 21,820.00 1,472.850 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 4,400.000 300.000 4,799.360 4,700.000 100.000% 97.930% 4,400.00 300.000 4,700.00 888,712.00 60,594.000 949,306.000 1.884% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.001 38,500.000 300.000 39,216.001 38,800.000 100.000% 98.939% 38,500.00 300.000 38,800.00 672,980.00 5,244.000 678,224.000 1.346% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 11,870.078 11,350.000 200.000 11,870.078 11,550.000 100.000% 97.303% 11,350.00 200.000 11,550.00 9,036,643.00 159,236.000 9,195,879.000 18.249% 18.754%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 7,863.927 3,752.500 1,820.000 270.000 9,683.927 4,022.500 39.486% 16.402% 3,752.50 476.250 4,228.75 4,558,499.48 578,543.738 5,137,043.213 10.194% 23.345%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 104.300 - 104.300 - 100.000% 0.000% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 2.400 - 2.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 15.000 15.000 40.000 30.000 100.000% 75.000% 15.00 15.000 30.000 65,400.60 65,400.600 130,801.200 0.260% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 133.817 - 133.817 267.634 - 93.334% 0.000% 0.000 - - - 0.000% 1.648%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 168.057 325.000 114.372 200.000 282.429 525.000 50.417% 93.718% 325.000 200.000 525.000 1,324,657.75 815,174.000 2,139,831.750 4.246% 2.284%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.685 0.644 0.041 0.041 0.726 0.685 72.600% 68.500% 0.644 0.041 0.685 119,328.34 7,596.990 126,925.328 0.252% 0.267%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 - 3.000 - 100.000% 0.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 41.986% 3.371% 45.357% 45.357% 58.980%
. SLIPPAGE, +/- -13.623%
21,157,338.74 1,698,938.770 22,856,277.515
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date
Annex 36 Form No.
Republic of the Philippines
PHILIPPINE RURAL DEVELOPMENT PROJECT (PRDP)
Province of Ilocos Norte, Region 1
Contractor: Badoc Builders
Proj. Location: Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte 32
Period Covered DECEMBER 20-26, 2018
WEEKLY PROGRESS REPORT

PROJECT DESCRIPTION :

The project Rehabilitation of Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan Farm to Market Road is located at Bgy Tapao Tigue-Poblacion 2-Sta Cruz-Lang Ayan, Currimao, Ilocos Norte will include the complete construction of vital facilities such as road network, side, drainage system, perimeter fence.

PROJECT DATA PROJECT STATUS

Contract Amount 50,391,994.74 Scheduled Accomplishment to Date : 67.666% %


Revised Contract Amount 50,391,995.74 Previous Accomplishment : 42.636% %
Contract Started : 16-May-18 Actual Accomplishment to date : 46.008% %
Contract Duration : 205 DAYS Slippage Previous +/- : -4.977% %
Contract Expiration : 6-Dec-18 Slippage to Date, +/- : -21.658% %
Revised Contract Duration 265 DAYS Contract time Elapsed : 147.000 c.d.
Revised Expiry Date : 4-Feb-19 Percent Time Elapse 85.965% %

PROJECT UPDATE
Rel. Wt. ACCOMPLISHMENT ACCOMPLISHMENT (QTY) AMOUNT
Original % ACTUAL TO % SCHEDULED
PART DESCRIPTION Unit Unit Cost Contract Amount DATE TO DATE
Quantity Previous Target Previous Actual Target Actual Target to Date Actual to Date %Target to Date %Actual to Date Previous This Period To Date Previous This Period To date
(%)
SPL 1-1 FIELD OFFICE AND LABORATORY FOR THE ENGINEER 1.00 l.s 58,968.00 58,968.00 0.12% 0.720 0.638 0.041 0.041 0.761 0.679 76.100% 67.900% 0.638 0.041 0.679 37,621.58 2,417.688 40,039.272 0.079% 0.089%
SPL-1 MOBILIZATION AND DEMOBILIZATION 1.00 l.s 410,976.30 410,976.30 0.82% 0.500 0.500 0.500 0.500 50.000% 50.000% 0.500 0.500 205,488.15 - 205,488.150 0.408% 0.408%
100 CLEARING AND GRUBBING 2.45 ha 167,391.43 410,109.00 0.81% 2.450 2.450 - 2.450 2.450 100.000% 100.000% 2.450 2.450 410,109.00 - 410,109.004 0.814% 0.814%
101(1) REMOVAL OF STRUCTURES AND OBSTRUCTIONS(FENCE 1.00 l.s 53,524.80 53,524.80 0.11% 1.000 1.000 - 1.000 1.000 100.000% 100.000% 1.000 1.000 53,524.80 - 53,524.800 0.106% 0.106%
101(3) REMOVAL OF EXISTING CONCRETE PAVEMENT 109.20 sq.m. 501.22 54,733.22 0.11% 109.200 109.200 - 109.200 109.200 100.000% 100.000% 109.200 109.200 54,733.22 - 54,733.224 0.109% 0.109%
102(2) SURPLUS COMMON EXCAVATION 11,460.13 cu.m 321.74 3,687,182.23 7.32% 11,460.129 11,450.000 10.129 11,460.129 11,460.129 100.000% 100.000% 11,450.00 10.129 11,460.13 3,683,923.00 3,258.904 3,687,181.904 7.317% 7.317%
103 STRUCTURE EXCAVATION 85.40 cu.m 272.75 23,292.85 0.05% 85.400 80.000 5.400 85.400 85.400 100.000% 100.000% 80.000 5.400 85.400 21,820.00 1,472.850 23,292.850 0.046% 0.046%
104 EMBANKMENT 4,799.36 cu.m 201.98 969,374.73 1.92% 4,799.360 4,400.000 300.000 4,799.360 4,700.000 100.000% 97.930% 4,400.00 300.000 4,700.00 888,712.00 60,594.000 949,306.000 1.884% 1.924%
105 SUBGRADE PREPARATION 39,216.00 sq.m. 17.48 685,495.68 1.36% 39,216.001 38,500.000 300.000 39,216.001 38,800.000 100.000% 98.939% 38,500.00 300.000 38,800.00 672,980.00 5,244.000 678,224.000 1.346% 1.360%
200 AGGREGATE SUBBASE COARSE 11,870.08 cu.m 796.18 9,450,720.29 18.75% 11,870.078 11,350.000 200.000 11,870.078 11,550.000 100.000% 97.303% 11,350.00 200.000 11,550.00 9,036,643.00 159,236.000 9,195,879.000 18.249% 18.754%
311 PCCP 24,524.95 sq.m. 1,214.79 29,792,664.01 59.12% 10,802.657 4,022.500 2,043.746 476.250 12,846.403 4,498.750 52.381% 18.344% 4,022.50 476.250 4,498.75 4,886,492.78 578,543.738 5,465,036.513 10.845% 30.969%
404 REINFORCING STEEL 104.30 kgs. 154.67 16,132.08 0.03% 104.300 - 104.300 - 100.000% 0.000% 0.000 - - - 0.000% 0.032%
405 STRUCTURAL CONCRETE 2.40 cu.m 18,456.56 44,295.74 0.09% 2.400 - 2.400 - 100.000% 0.000% 0.000 - - - 0.000% 0.088%
500(1)C PIPE CULVERTS & STORM DRAINS, 910 MM DIA. 40.00 l.m. 4,360.04 174,401.60 0.35% 40.000 15.000 15.000 40.000 30.000 100.000% 75.000% 15.00 15.000 30.000 65,400.60 65,400.600 130,801.200 0.260% 0.346%
505 GROUTED RIPRAP 286.75 cu.m 3,102.21 889,558.72 1.77% 267.634 - 19.117 286.751 - 100.000% 0.000% 0.000 - - - 0.000% 1.765%
506 STONE MASONRY 560.19 cu.m 4,075.87 2,283,261.62 4.53% 282.429 325.000 114.372 200.000 396.801 525.000 70.833% 93.718% 325.000 200.000 525.000 1,324,657.75 815,174.000 2,139,831.750 4.246% 3.209%
605(2) DIRECTIONAL SIGN(TRIANGLE 600MM) 42.00 each 9,143.67 384,034.14 0.76% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
605(3) INFORMATIVE SIGN(457MMX1219MMX3MM-SCHOOL ZONE 2.00 each 16,345.51 32,691.02 0.06% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
612 PAVEMENT MARKINGS(THERMOPLASTIC WHITE) 245.25 sq.m. 1,342.71 329,299.63 0.65% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
620 CHEVRON DIRECTIONAL SIGN(450MM X 600MM) 48.00 each 9,001.85 432,088.80 0.86% - - - - 0.000% 0.000% 0.000 - - - 0.000% 0.000%
SPL-2 CONSTRUCTION SAFETY AND HEALTH 1.00 l.s 185,292.45 185,292.45 0.37% 0.726 0.644 0.041 0.041 0.767 0.685 76.700% 68.500% 0.644 0.041 0.685 119,328.34 7,596.990 126,925.328 0.252% 0.282%
SPL-4 BILLBOARD 3.00 each 7,965.94 23,897.82 0.05% 3.000 - 3.000 - 100.000% 0.000% 3.000 3.000 23,897.82 - 23,897.820 0.047% 0.047%
TOTAL CONTRACT AMOUNT 50,391,994.74 100.00% 42.636% 3.371% 46.008% 46.008% 67.666%
. SLIPPAGE, +/- -21.658%
21,485,332.04 1,698,938.770 23,184,270.815
PROGRESS PHOTOS

Photos shall reflect the accomplishment indicated in the figures of accomplishment " this period"

Captions:

ISSUES / PROBLEMS ENCOUNTERED:


*Electrical Post/ Solar Post

Reported by: Certified by:

Signature Signature
Name JOHN CARLO L. MADDELA Name JAY-MARK M. PONCE DUDEO C. GALEON
Title MPMIU Resident Engineer Title MPMIU Engineer MPMIU Head
Date Date