Estimate for 1Km Length Road
For 3m Road
Sl.No                     Item             No's L(m) B(m) D(m)        Qty    Units   Rate   Amount
1       Soiling Layer                       1 1000      3    0.3      900    Cum     2000   1800000
2       WBM - 40mm                          1 1000      3    0.23     690    Cum     2500   1725000
3       Top coat (12mm)                     1 1000      3             3000   Sqm      200   600000
4       Tack Coat                           1 1000      3             3000   Sqm      30     90000
5       Top coat (6mm)                      1 1000      3             3000   Sqm      150   450000
                                                                                Sub-Total   4665000
6       Labour & Machinery Charge @ 15%                                                     699750
                                      Rate for 1Km Length                                   5364750
                                       Rate for 1m Length                                   5364.75
                                                   For 4m Road
Sl.No                     Item             No's   L(m) B(m) D(m)      Qty    Units   Rate   Amount
1       Soiling Layer                       1     1000    4    0.3    1200   Cum     2000   2400000
2       WBM - 40mm                          1     1000    4    0.23   920    Cum     2500   2300000
3       Top coat (12mm)                     1     1000    4           4000   Sqm      200   800000
4       Tack Coat                           1     1000    4           4000   Sqm      30    120000
5       Top coat (6mm)                      1     1000    4           4000   Sqm      150   600000
                                                                                Sub-Total   6220000
6       Labour & Machinery Charge @ 15%                                                     933000
                                      Rate for 1Km Length                                   7153000
                                       Rate for 1m Length                                    7153
                                      Bitumen Road Estimation (1Km Length and 3m Width)
SI.
            Description              No         L          B               D            Quantity   Rate        Amount
No.
 1               2              3      4       5            6               7              8         9           10
  Soling layer– this bottom layer shall be of two layers using laterite/ BG boulders/
  locally available natural
  rock boulders – each of 150 mm preconsolidated thick – rolled to 115 mm thick -
  consolidated thickness
1
  totalling to 230 mm and each layer shall be blinded with gravel with 1/3 quantity
  of laterite/boulders and
                                 1        1   1000.0      3.00            0.300          900.00
                                                                                         900.00      1615.14   1453626
                                                                                             Cum   1 Cum
  WBM – using 40 mm BG metal - two layers – each of 135 mm preconsolidated
  thick – rolled to 100 mm
  thick - consolidated thickness which includes dry and wet rolling of each layers,
  spreading gravel for blind
  age and consolidation with water, spreading sand to a thickness of 3 mm and top
  rolling. All roads shall be
  provided with 0.60 M wide berm on both sides with 150mm thick well compacted
  laterite/ BG boulders/
  locally available natural rock boulders surface and trapezoidal earthern drains as
4 per the approved drainage
  layout. The area between the solar arrays shall be levelled for carrying panels and
  materials, modules
  washing, easy movement during O & M, etc. The layout and details drawing of all
  roads and culverts (if
  any) shall be submitted to NACOF and got approved, before commencement of
  work.
                                 1        1   1000.00     3.00            0.270          810.00
                                                                                         810.00    2280.03     1846824
                                                                                          Cum      1Cum
      Estimated Value as per
      SOR Telangana 20-21                                                           Sub Total                  3300450
      Additional 10% of Rate
                                                                                                               330045
      Increment (Approx)
      Grand Total                                                                                              3630495
                                                                 Page 2
                                      Bitumen Road Estimation (1Km Length and 4m Width)
SI.
            Description              No         L           B               D            Quantity    Rate       Amount
No.
 1               2              3      4       5            6               7               8         9           10
  Soling layer– this bottom layer shall be of two layers using laterite/ BG boulders/
  locally available natural
  rock boulders– each of 150 mm preconsolidated thick – rolled to 115 mm thick -
  consolidated thickness
1
  totalling to 230 mm and each layer shall be blinded with gravel with 1/3 quantity
  of laterite/boulders
                                 1        1   1000.0       4.00            0.300         1200.00
                                                                                         1200.00      1615.14   1938168
                                                                                             Cum    1 Cum
  WBM – using 40 mm BG metal – one layer of 135 mm pre-consolidated thick –
  rolled to 100 mm thickconsolidated
  thickness which includes dry and wet rolling, spreading gravel for blind age and
2 consolidation
  with water, spreading sand to a thickness of 3 mm and top rolling and
                                 1        1   1000.00      4.00            0.230          920.00
                                                                                          920.00    2280.03     2097628
                                                                                           Cum      1Cum
  Top coat – Top finishing coat shall be of Bituminous Toping using 12 mm
  downgraded metal with
  consolidated thickness of 20mm and seal coat. Outer peripheral road of the solar
3 plant shall also be designed
  and constructed in addition to the internal roads. This road also shall be of single
  lane of 3 M width. This
  peripheral road shall be laid as follows.
                                 1        1   1000.00      4.00                          4000.00
                                                                                         4000.00    173.00      692000
                                                                                          sqmt      1 SQM
      Estimated Value as per
      SOR Telangana 20-21                                                            Sub Total                  4727796
      Additional 10% of Rate
                                                                                                                472780
      Increment (Approx)
      Grand Total                                                                                               5200575
                                                                  Page 3
                                       Bitumen Road Estimation (1Km Length and 4m Width)
SI.
           Description                No         L          B               D            Quantity     Rate       Amount
No.
 1              2                3     4        5            6              7               8          9           10
  Excavation in soil with hydraulic excavator of 0.9 cum
  bucket capacity including cutting and loading in tippers,
  trimming bottom and side slopes, in accordance with
  requirements of lines, grades and cross-sections, and
1
  transporting to the embankment location with all lifts and
  lead upto 1000 m as per Technical Specification Clause
  302.3 MORD / 301 MORTH
                                  1        1   1000.0      4.00            0.600         2400.00
                                                                                         2400.00        103.76   249024
                                                                                             Cum     1 Cum
2 Compacting with roller 80 to 100 kn /hr
                       Qty as of Item No.1                                                 2400.00
                                                                                         2400.00        138.00   331200
                                                                                             Cum     1 Cum
  Providing, laying, spreading and compacting graded stone aggregate to wet mix
  macadam specification including premixing the material with water at OMC in
  mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in
  uniform layers in sub-base/base course on a
  well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN /
4 Vibratory Roller 80-100 kN weight to achieve the desired density including
  lighting,barricading and maintenance of diversion, etc as per Tables 400.11 &
  400.12 and Technical Specification Clause 406
  MORD / MORTH.
                                  1        1   1000.00     4.00            0.230          920.00
                                                                                          920.00      2173.96    2000043
                                                                                           Cum       1Cum
  Providing and applying primer coat with bitumen emulsion
  (SS-1) on prepared surface of granular base including
  cleaning of road surface and spraying primer at the rate of
5 0.70-1.0 kg/sqm using mechanical means as per Technical
  Specification Clause 502 MORD (for use on Wet mix
  macadam & WBM)
                                  1        1   1000.00     4.00                          4000.00
                                                                                         4000.00      52.11      208440
                                                                                          sqmt       1 SQM
  Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion
  distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared dry and hungry
6 bituminous surface cleaned with Hydraulic broom as per Technical Specification
  Clause 503 MORD.
                                  1        1   1000.00     4.00                          4000.00
                                                                                         4000.00      16.80      67200
                                                                                          sqmt       1 SQM
  Providing and laying dense graded bituminous macadam with 100-120 TPH batch
  type HMP producing an average output of 75 tonnes per hour using crushed
  aggregates of specified grading, premixed with bituminous binder @ 4.5 % by
  weight of total mix and filler, transporting the hot mix to work site, laying with a
  hydrostatic paver finisher with
  sensor control to the required grade, level and alignment,rolling with smooth
7 wheeled, vibratory and tandem rollers to achieve the desired compaction as per
  MoRTH specification clause No. 507 complete in all respects.
                                  1        1   1000.00     4.00            0.050          200.00
                                                                  Page 4
                                                                                           200.00     9309.97    1861994
                                                                                            Cum        1Cum
  Providing and applying tack coat with bitumen emulsion using emulsion pressure
  distributor at the rate of 0.20 kg per sqm on the prepared bituminous/granular
8 surface cleaned with mechanical broom as per Tech. specification No 503 MORTH
                                  1      1   1000.00        4.00                           4000.00
                                                                                           4000.00     12.19     48760
                                                                                            sqmt      1 SQM
  Providing and laying bituminous concrete with 100-120 TPH batch type hot mix
  plant producing an average output of 75 tonnes per hour using crushed aggregates
  of specified grading, premixed with bituminous binder @ 5.4 per cent of mix and
  filler, transporting the hot mix to work site,laying with a hydrostatic paver finisher
  with sensor control to the required grade, level and alignment, rolling with smooth
9 wheeled, vibratory and tandem rollers to achieve the desired compaction as per
  MORTH specification clause No. 509 complete in all respects
                                  1      1   1000.00        4.00            0.030          120.00
                                                                                           120.00    10594.916   1271390
                                                                                            Cum        1Cum
   Estimated Value as per
   SOR Telangana 20-21                                                                 Sub Total                 6038051
   Additional 10% of Rate
                                                                                                                 603805
   Increment (Approx)
   Grand Total                                                                                                   6641856
                                                                   Page 5