0% found this document useful (0 votes)
63 views2 pages

Carmona

The document outlines the electrical inspection project for a warehouse with attic located in Kapitolyo, owned by Mr. & Mrs. Lema, with a total cost of PHP 33,040. It includes detailed costs for general requirements and site works, along with payment terms and conditions. The project is expected to take 20 working days to complete.

Uploaded by

Trending Juan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
63 views2 pages

Carmona

The document outlines the electrical inspection project for a warehouse with attic located in Kapitolyo, owned by Mr. & Mrs. Lema, with a total cost of PHP 33,040. It includes detailed costs for general requirements and site works, along with payment terms and conditions. The project is expected to take 20 working days to complete.

Uploaded by

Trending Juan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

PROJECT : WAREHOUSE WITH ATIC

LOCATION : KAPITOLYO
OWNER : MR, & MRS Lema
ARCHITECT : ALDENO REALTY DEVELOPMENT
SUBJECT : ELECTRICAL INSPECTION
DATE : 31-Jan-24

Materials Labor
Item Description Qty Unit Total Amount
Total Cost Total Cost
I. GENERAL REQUIREMENTS
1.01 Mobilization 1.00 lot - 5,000.00 5,000.00
1.02 Permits
a. Electrical compliance certificate with sign and seal of Electrical Engineer 1.00 lot - 14,000.00 14,000.00
SUB- TOTAL 19,000.00
II. SITE WORKS
2.01 Electrical test - -
a. Insulation resistance test (IR) 1.00 lot 5,000.00 5,000.00
b. Continuity test 1.00 lot 3,000.00 3,000.00
c. Electrical inspection 1.00 lot 2,500.00 2,500.00
SUB- TOTAL 10,500.00
DIRECT COST PHP 29,500.00
PROJECT SUMMARY
ITEM DESCRIPTION REMARKS
I. GENERAL REQUIREMENTS 19,000.00
II. SITE WORKS 10,500.00
DIRECT COST 29,500.00
CONTINGENCY
MARK-UP/PROFIT
12% VAT 3,540.00
GRAND TOTAL 33,040.00
TERMS AND CONDITIONS:
• The quotation is based on mentioned details, any revisions or addition on the approved layout will be charged.
• Request for refunds after signing of the agreement is subject to cancellation fee (10% of total contract price.)
• All materials obtained from the demolition will go to Aldeno.
• Duration of work 20 working days

PAYMENT TERMS:
• Fifty percent (50%) down payment upon signing the conforme.
• Fifty percent (50%) upon completion of project.
• All check payments payable to Arch. June Kathleen Mordeno
BDO Account:
June Kathleen Mordeno
007510090951

Prepared by: Checked By:

Diane Buela Richard Aldea


Estimator Operations Manager

Approved By:

Kathleen Mordeno
President