PROJECT : WAREHOUSE WITH ATIC
LOCATION : KAPITOLYO
OWNER : MR, & MRS Lema
ARCHITECT : ALDENO REALTY DEVELOPMENT
SUBJECT : ELECTRICAL INSPECTION
DATE : 31-Jan-24
Materials Labor
Item Description Qty Unit Total Amount
Total Cost Total Cost
I. GENERAL REQUIREMENTS
1.01 Mobilization 1.00 lot - 5,000.00 5,000.00
1.02 Permits
a. Electrical compliance certificate with sign and seal of Electrical Engineer 1.00 lot - 14,000.00 14,000.00
SUB- TOTAL 19,000.00
II. SITE WORKS
2.01 Electrical test - -
a. Insulation resistance test (IR) 1.00 lot 5,000.00 5,000.00
b. Continuity test 1.00 lot 3,000.00 3,000.00
c. Electrical inspection 1.00 lot 2,500.00 2,500.00
SUB- TOTAL 10,500.00
DIRECT COST PHP 29,500.00
PROJECT SUMMARY
ITEM DESCRIPTION REMARKS
I. GENERAL REQUIREMENTS 19,000.00
II. SITE WORKS 10,500.00
DIRECT COST 29,500.00
CONTINGENCY
MARK-UP/PROFIT
12% VAT 3,540.00
GRAND TOTAL 33,040.00
TERMS AND CONDITIONS:
• The quotation is based on mentioned details, any revisions or addition on the approved layout will be charged.
• Request for refunds after signing of the agreement is subject to cancellation fee (10% of total contract price.)
• All materials obtained from the demolition will go to Aldeno.
• Duration of work 20 working days
PAYMENT TERMS:
• Fifty percent (50%) down payment upon signing the conforme.
• Fifty percent (50%) upon completion of project.
• All check payments payable to Arch. June Kathleen Mordeno
BDO Account:
June Kathleen Mordeno
007510090951
Prepared by: Checked By:
Diane Buela Richard Aldea
Estimator Operations Manager
Approved By:
Kathleen Mordeno
President