14 Annex - A SoW
14 Annex - A SoW
Internal
SoW – Supply and Installation of Solar System
1. INTRODUCTION
Banglalink is one of the leading telecom operators with distributed footprint in Bangladesh. Bringing
continuous changes, Banglalink has established very efficient policies and processes which is one of its
dominating strengths. To keep services available to their customers we are focusing on energy domain.
As part of continuous improvement and from a better sourcing point of view, Banglalink has decided to
conduct a sourcing process for supply and service of renewable energy systems.
MAJOR DELIVERABLE
Solar System for Data Center:
S/N Type of Service Items Unit Job Description
Month wise solar energy rent is based on energy
meter.
Supply and installation of complete solar system (e2e)
1 Solar Energy rent KWH with require survey, complete civil structure,
accessories and solar mounting structure on roof,
ground, and tower structure, and net-metering to
Gazipur, Mymensingh, Cumilla and other Data Center.
Supply and installation of complete solar system (e2e)
Supply and installation of 30KW solar
2 Job with require survey, complete civil structure,
system at site
accessories and solar mounting structure on roof,
ground, and tower structure, and net-metering to
Supply and installation of 50KW solar Gazipur, Mymensingh, Cumilla and other Data Center.
3 Job
system at site If due to space scarcity or other issues, complete
mentioned capacity will not be feasible to install then
Supply and installation of 80KW solar price for the installed system will be adjusted as per
4 Job ratio according to complete system price.
system at site
Page 1 of 17
Internal
SoW – Supply and Installation of Solar System
Supply and installation of GI Pipe dia 4 Supply, transport, and installation of GI Pipe 4-
7 ft
Inch and Thickness 5mm Inch 4mm thickness and MS angle 3-inch 4mm
thickness for any sites of BL
Supply and installation of MS angle 3
8 ft
Inch and Thickness 5mm
Supply of 1x10 RM BYAF DC copper
9 meter
power cable.
Supply of 1x16 RM BYAF DC copper Supply and installation of DC and AC power cable
10 meter
power cable. at Bl network.
Supply of 1x25 RM BYAF DC copper
11 meter
power cable.
Supply of 4x10 rm NYY copper Power
12 meter
cable.
Supply of 4x25 rm NYY copper Power
13 meter
cable.
Supply and installation of Net Metering 3
14 Phase for Different sanctioned loads up Per Site
to 8KW Supply and installation of net meter at BL
Supply and installation of Net Metering 3 network.
15 Phase for Different sanctioned loads Per Site
above 8KW (up to 30KW)
Solar system preventive maintenance at
16 BL network without spare (Panel and Per Site
controller). For rectification purposes
Solar system preventive maintenance at
17 Per Site
BL network without spare (Panel and
Page 2 of 17
Internal
SoW – Supply and Installation of Solar System
Page 3 of 17
Internal
SoW – Supply and Installation of Solar System
Page 4 of 17
Internal
SoW – Supply and Installation of Solar System
Bashundhara Cement, Crown Cement, Holcim, Fresh Cement, Premier Cement, Seven Ringe
Cement, Akij Cement, Confidence Cement. Sand: Sylhet sand or similar sand. Quality stone and
recommended for civil work. Nonbrand/ copy material will not be acceptable.
v. GI Pipe and MS angle: (RAN SL.7-8)
a. Supplier shall supply and installation of GI Pipe 4 Inch and Thickness 5mm and of MS angle 3 Inch
and Thickness 5mm.
b. The supplier shall deliver all necessary accessories welding, paint, nut-bolt, clamp etc.
c. GI Pipe and MS angle brand: Government recommended and approved any Bangladeshi quality
company. Nonbrand/ copy material will not be acceptable.
d. Supplier shall provide the service, supply, transport for any sites of BL network (Including remote
site-Island/Hill track).
vi. Power Cable: (RAN SL.9-13)
a. Supplier supply of following cable: 1X10, 1X16, 1X25 RM BYAF DC copper power cable and 4x10
rm and 4x25 rm NYY cupper Power cable.
b. Supplier shall supply the following branded cable. Cable brands will be BBS, BRB, SQ, Bizli, Partex
or similar brand and origin of DC cable. Nonbrand/ copy material will not be acceptable.
c. Supplier responsible for supply, transportation and install for any sites of BL network (Including
remote site-Island/Hill track).
vii. Net Metering: (RAN SL.14-15)
a. Supplier shall supply and install the net metering of any sites of BL network (Including remote
site (Island/Hill track)).
b. Supplier shall provide the Net meter, necessary accessories (cable, Nut-Bolt, Bracket, Clamp,
Grounding (Aluminum 35 RM), Grounding accessories, Circuit breaker, cable connector etc.)
c. Supplier should follow up, process and approval from power authority. Communication and
necessary document process as per power authority requirement/guideline.
d. Before starting the work, vendor shall visit the site for installation plan and design and submit
to purchase for necessary approval.
viii.Supply of solar panel:
a. Supplier shall deliver the solar panel to any sites of BL network (Including remote site-Island/Hill
track).
b. Solar panel capacity, efficiency, brand, type, size etc. will be as per given technical specification.
c. Supplier shall be solely responsible for all the mobilization, labor, and resources etc.
d. The supplier shall be responsible for any damage broken during the mobilization.
ix. Solar system Preventive and Emergency maintenance: (RAN SL.16-19)
a. Supplier shall be providing the service and maintenance for any sites of BL network. Service
charge will be deferent for normal sites and remote sites (Island/Hill track).
b. Supplier shall be responsible for transport, labor, standard tools usages etc. during the service
and maintenance.
c. Preventive Service and maintenance scope comprise of cleaning and checking of solar panel,
controller, inverter, Solar panel frame, and check the cable and all over connection, panel frame
and structure, functionality of controller, inverter, and net-meter setting and data etc.
d. Supplier shall collect the data (Minimum 90 days) from controller, inverter, and net meter.
e. Supplier Shall provide the pictures (after and before), PAT, 90 days data and complete report to
Purchaser.
f. During the servicing and maintenance if required any accessories, supplier shall provide the nut-
bolt, clamp, cable tie, electrical tape, bitumen tape, cable luge, painting, brass, jute, 4/6 rm DC
Page 5 of 17
Internal
SoW – Supply and Installation of Solar System
cable for panel-to-panel connection etc. Supplier shall use the stranded tools during the service
and maintenance.
g. Emergency Service and Maintenance as requirement of Purchaser, supplier shall provide service
to to any solar site of BL network. Purchase will issue ticket through Mail/SMS/WhatsApp for
emergency service to Supplier. Supplier will attend at site maintaining SLA and find out the root
cause, create and share report to Purchaser and provide required solution maintaining SLA and
provide necessary support for rectification with require major spares provided by Purchaser and
minor spare parts will be provided by supplier.
h. Major parts are solar panel (Per site 200 to 1500-watt solar panel will be (solar panel size and
quantity depend on existing solar panel size and quantity), controller, inverter, cable, junction
box, Mate (data collect gateway), and Minor parts are cable, CKT and accessories .
x. Supply of solar controller mate and junction box:
a. Supplier shall provide the solar controller mate and junction box for any sites of BL network
(Including remote site-Island/Hill track).
b. Supper shall provide the standard quality of junction box and maintain the Wire leads connecting
the panel to the string and bypass diodes are located inside the junction box. Protection Degree:
IP65 or IP68.
c. Supper shall provide the standard quality of solar controller mate and international certification
(CE, RoHs, SGS, ISO9001).
d. User easily will collect the data from mate (Store Last minimum 90 days data (Hourly and
Monthly Energy, Max, and Min voltage (Solar Array and Battery), Max and Min Current (Solar
Array and Battery) etc. Pote: RJ45, USB. Data is easy to collect by pen drive, laptop.
e. During the installation if required any accessories, supplier shall provide the nut-bolt, clamp,
cable tie, electrical tape, bitumen tape, cable luge, 4/6 rm DC etc.
Vendor Feedback:
Page 6 of 17
Internal
SoW – Supply and Installation of Solar System
6. TECHNICAL SPECIFICATION
6.1 SOLAR PANEL SPECIFICATION
Item Subcategory Requirement Mandatory Vendor Feedback
Panel Capacity ≥550 Wp Yes
Panel Type Monocrystalline Yes
Mono-facial
Panel Type
/Bi-facial
Design Life ≥20 year Yes
Module Efficiency >21% Yes
STC: Irradiance 1000 W/m2, Module temperature 25℃, AM=1.5
Maximum Power
≥550 W Yes
(Pmax)
Power Tolerance 0 to +5W Yes
Optimum
Operating Voltage ~45V
(Vmp)
Optimum
Operating Current ~13A
SOLAR PANEL
(Imp)
Open Circuit
~50V
Voltage (Voc)
Short Circuit
~14A
Current (Isc)
NMOT: Irradiance 800 W/m2, Module temperature 20℃, AM=1.5
Maximum Power
>410 W
(Pmax)
Optimum
Operating Voltage ~41V
(Vmp)
Optimum
Operating Current ~11A
(Imp)
Open Circuit
~47V
Voltage (Voc)
Short Circuit
~11A
Current (Isc)
Operating
0℃ to 75℃
Temperature
Weight ~35 kg
Dimensions
2200 ×1100 ×35 mm
(L×W×H) Approx.
Page 7 of 17
Internal
SoW – Supply and Installation of Solar System
Nominal Battery
48V Yes
Voltages
Maximum Output
80A (4KW) and 60A (3KW) Yes
Current
Solar Maximum Array 48VDC systems: 4000W and
Yes
STC Nameplate 3000W
PV Open Circuit
Vendor to specify
Voltage (VOC)
Standby Power
Less than 5W
Consumption
Input voltage 70V to 420V
Operating Voltage -42V to -58V
Power Conversion
Min 97%, 48VDC system Yes
Efficiency
Status Display LED
Page 8 of 17
Internal
SoW – Supply and Installation of Solar System
Page 9 of 17
Internal
SoW – Supply and Installation of Solar System
Page 10 of 17
Internal
SoW – Supply and Installation of Solar System
Page 11 of 17
Internal
SoW – Supply and Installation of Solar System
Output Side
Rated Output Power (kW) 3 KW 4 KW 6 KW 6 KW 8 KW
4000 8800
Max Apparent Power (VA) 3000 VA
VA 6000 VA 66000 VA VA
Rated Grid Frequency (Hz) 50/60 Hz
Operating Phase 1/N/PE 3/N/PE
Rated AC Grid Output
230V (180-280V)
Current (A) 230/400Vac
Max. AC Output Current
(A) 13.6 A 19 A 27 A 9.5 A 13.5 A
Page 12 of 17
Internal
SoW – Supply and Installation of Solar System
Page 13 of 17
Internal
SoW – Supply and Installation of Solar System
8. DELIVERY
Supplier will deliver the complete solar system to BL within a maximum of Eighty (80) calendar days
from the day of PO issuance.
Vendor Feedback:
9. WARRANTY
Items Years
a. Solar controller- Five (05) years (Min.).
b. Inverter- Five (05) years (Min.).
c. Solar panel- Eight (08) years.
All Items d. All civil structure with GI Pipe and MS angles etc.- Eight (08) years
e. All AC, DC and Grounding cable- Five (5) years.
f. Accessories- painting, Grounding, Circuit breaker, SPD, Distribution box,
MDB, Energy meter- Two (2) years.
The Warranty period will start from the date of PAT Acceptance of Solar system on site.
Supplier will collect damaged/fault items from Banglalink site and after rectification is done, will
re-installation at site.
During the warranty period the supplier will replace/repair damaged items as per the following
SLA.
Replaced or repaired item warranty will be same from date of PAT acceptance.
Warranty is not applicable for stolen case, physical damage and burn case (Banglalink).
Though solar panel will be broken or damaged by hailstorm, supplier shall replace it under
warranty clause.
Vendor needs to ensure sufficient facilities and minimum 3% spares for warranty.
For only DG+Solar site, supplier will provide warranty support within 72hrs.
Vendor Feedback:
OBI will be conducted by both parties (BL and Suppliers) within Two (2) working days after
delivering the product to Warehouse/Site.
If any partially/full DEFECTS in terms of quality or quantity found during OBI, vendor is liable to
replace the faulty products or BL will claim the financial adjustment or impose penalty as per
clause.
Before OBI supplier shall provide order document, LC document, shipment document, product
certification, company profile, and manufacturer company POC information (Company name,
Page 14 of 17
Internal
SoW – Supply and Installation of Solar System
Email address, Phone number, website information etc.). Supplier shall provide all information
before shipment and shipment document with ship tracking-number after shipment (within 3
days from the shipment confirmation date). Note that, no need to provide any type of supplier
material price information to purchaser.
If the supplier fails to provide the following information, and provides non-band/ copy product,
low quality, not matching with SoW etc. Purchaser has right the cancel the PO and impose the
penalty as per clause.
Vendor Feedback:
11.ACCEPTANCE:
The requirements related to Acceptance are set out in each case description. However typically Purchaser
will issue a Acceptance on site after successful achievement of the below activities: -
Supplier will ensure preventive maintenance service of solar system with three (03) month interval for
two (02) years from date of acceptance for every site. All require spares, services and transportation for
PMS will be free of cost during two (02) years and supplier will be responsible to ensure PMS on due time.
Total PMS quantity will be seven (07), three (03) in 1st year and four (04) in 2nd year.
Vendor Feedback:
Page 15 of 17
Internal
SoW – Supply and Installation of Solar System
For ensuring the performance and seriousness from vendors Liquidity Damage is fixed. It is designed
based on severity, criticality, and intension of the jobs. However, BDCL expects all partners will follow
the compliance policy, CoC and SLA to avoid LD.
Page 16 of 17
Internal
SoW – Supply and Installation of Solar System
- All LD amounts will be adjusted from current Invoice or Pending Invoice or Upcoming Invoice or
Security deposit.
- Maximum LD amount will be 20% of the total invoice (Supply).
Vendor Feedback:
14.PO CANCELLATION:
Banglalink has reserved the right to cancel PO, if vendor will not maintain the below SLA,
Failed to maintain PO delivery lead time.
Any false information providing or misleading.
Deviation in supplied item’s specification with agreed specification.
Failed to maintain BL standard work.
Vendor Feedback:
Phone;
E-mail (PR –mail box);
Fax;
Social Media
Page 17 of 17