PMP® Formula Pocket Guide
Print it - Fold it - Study wherever you go.
Earned Value                                                                 Mathematical Basics
CV = EV - AC                                                                 Average (Mean) = Sum of all members divided by the number of items.
CPI = EV / AC                                                                Median = Arrange values from lowest value to highest. Pick the middle
SV = EV - PV                                                                 one. If there is an even number of values, calculate the mean of the
SPI = EV / PV                                                                two middle values.
EAC ‘typical’ = BAC / CPI                                                    Mode = Find the value in a data set that occurs most often.
EAC ‘fundamentally flawed’ = AC + ETC
EAC ‘atypical’ = AC + BAC - EV                                               Values
EAC ‘over budget + deadline’ = AC + ((BAC - EV) / (CPI * SPI))               1 sigma = 68.26%
ETC = EAC - AC                                                               2 sigma = 95.46%
ETC ‘atypical’ = BAC - EV                                                    3 sigma = 99.73%
ETC ‘typical’ = (BAC - EV) / CPI                                             Six sigma = 99.99%
ETC ‘flawed’ = new estimate                                                  Control Limits = +/- Three sigma from mean.
Percent Complete = EV / BAC * 100                                            Control Specifications = Defined by customer; looser than the control
VAC = BAC - EAC                                                              limits.
EV = % complete * BAC                                                        Rough Order of Magnitude estimate = -50% to +50% (PMBOK®)
TCPI ‘based on BAC’ = (BAC – EV) / (BAC – AC)                                Preliminary estimate = -15% to + 50%
TCPI ‘based on EAC’ = (BAC – EV) / (EAC – AC)                                Budget estimate = -10% to +25%
                                                                             Definitive estimate = -5% to +10%
PERT                                                                         Final estimate = 0%
PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6                    Float on the critical path = 0 days
PERT σ = (Pessimistic - Optimistic) / 6                                      Pareto Diagram = 80/20
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2                  Time a PM spends communicating = 90%
PERT Deviation all activities = √sum((Pessimistic - Optimistic) / 6)^2       Crashing a project = Crash least expensive tasks on critical path.
                                                                             JIT inventory = 0% (or very close to 0%.)
Communications                                                               Minus 100 = (100) or -100
Communication Channels = n * (n-1) / 2
Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target
Cost
Probability                                                                  Acronyms
EMV = Probability * Impact in currency                                       AC      Actual Cost
                                                                             BAC     Budget at Completion
Network Diagram                                                              BCR     Benefit Cost Ratio
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1           CBR     Cost Benefit Ratio
Total Float = LS - ES or Total Float = LF – EF                               CPI     Cost Performance Index
Free Float = ES of Following - ES of Present - DUR of Present                CV      Cost Variance
EF = ES + duration - 1                                                       DUR     Duration
ES = EF of predecessor + 1                                                   EAC     Estimate at Completion
LF = LS of successor - 1                                                     EF      Early Finish
LS = LF - duration + 1                                                       EMV     Expected Monetary Value
                                                                             ES      Early Start
Project Selection                                                            ETC     Estimate to Complete
PV = FV / (1+r)^n                                                            EV      Earned Value
FV = PV * (1+r)^n                                                            FV      Future Value
NPV = Formula not required. Select biggest number.                           IRR     Internal Rate of Return
ROI = Formula not required. Select biggest number.                           JIT     Just-in-Time
IRR = Formula not required. Select biggest number.                           LF      Late Finish
Payback Period = Add up the projected cash inflow minus expenses             LS      Late Start
until you reach the initial investment.                                      NPV     Net Present Value
BCR = Benefit / Cost                                                         PERT    Program Evaluation and Review Technique
CBR = Cost / Benefit                                                         PTA     Point of Total Assumption
Opportunity Cost = The value of the project not chosen.                      PV      Planned Value
                                                                             PV      Present Value
Depreciation                                                                 ROI     Return on Investment
Straight-line Depreciation:                                                  SPI     Schedule Performance Index
Depr. Expense = Asset Cost (– Scrap Value) / Useful Life                     SV      Schedule Variance
Depr. Rate = 100% / Useful Life                                              TCPI    To-Complete Performance Index
Double Declining Balance Method:                                             VAC     Variance at Completion
Depr. Rate = 2 * (100% / Useful Life)                                        σ       Sigma / Standard Deviation
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year          ^       “To the power of” (2^3 = 2*2*2 = 8)
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)
Visit www.pm-prepcast.com for more Exam Resources                                      For disclaimer see PMP® Formula Study Guide
                                                                                                                          th
Copyright © 2009 by OSP International LLC. All rights reserved.                      Version 2.1 - Use with PMBOK® Guide 4 Edition