0% found this document useful (0 votes)
25 views1 page

PMP Formula Pocket Guide

The PMP® Formula Pocket Guide provides essential formulas and concepts for project management, including earned value calculations, probability assessments, and depreciation methods. It also outlines key acronyms and definitions relevant to project management practices. This guide serves as a quick reference for studying and applying project management principles effectively.

Uploaded by

oleg.filtsov
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views1 page

PMP Formula Pocket Guide

The PMP® Formula Pocket Guide provides essential formulas and concepts for project management, including earned value calculations, probability assessments, and depreciation methods. It also outlines key acronyms and definitions relevant to project management practices. This guide serves as a quick reference for studying and applying project management principles effectively.

Uploaded by

oleg.filtsov
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PMP® Formula Pocket Guide

Print it - Fold it - Study wherever you go.

Earned Value Mathematical Basics


CV = EV - AC Average (Mean) = Sum of all members divided by the number of items.
CPI = EV / AC Median = Arrange values from lowest value to highest. Pick the middle
SV = EV - PV one. If there is an even number of values, calculate the mean of the
SPI = EV / PV two middle values.
EAC ‘typical’ = BAC / CPI Mode = Find the value in a data set that occurs most often.
EAC ‘fundamentally flawed’ = AC + ETC
EAC ‘atypical’ = AC + BAC - EV Values
EAC ‘over budget + deadline’ = AC + ((BAC - EV) / (CPI * SPI)) 1 sigma = 68.26%
ETC = EAC - AC 2 sigma = 95.46%
ETC ‘atypical’ = BAC - EV 3 sigma = 99.73%
ETC ‘typical’ = (BAC - EV) / CPI Six sigma = 99.99%
ETC ‘flawed’ = new estimate Control Limits = +/- Three sigma from mean.
Percent Complete = EV / BAC * 100 Control Specifications = Defined by customer; looser than the control
VAC = BAC - EAC limits.
EV = % complete * BAC Rough Order of Magnitude estimate = -50% to +50% (PMBOK®)
TCPI ‘based on BAC’ = (BAC – EV) / (BAC – AC) Preliminary estimate = -15% to + 50%
TCPI ‘based on EAC’ = (BAC – EV) / (EAC – AC) Budget estimate = -10% to +25%
Definitive estimate = -5% to +10%
PERT Final estimate = 0%
PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6 Float on the critical path = 0 days
PERT σ = (Pessimistic - Optimistic) / 6 Pareto Diagram = 80/20
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2 Time a PM spends communicating = 90%
PERT Deviation all activities = √sum((Pessimistic - Optimistic) / 6)^2 Crashing a project = Crash least expensive tasks on critical path.
JIT inventory = 0% (or very close to 0%.)
Communications Minus 100 = (100) or -100
Communication Channels = n * (n-1) / 2

Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target
Cost

Probability Acronyms
EMV = Probability * Impact in currency AC Actual Cost
BAC Budget at Completion
Network Diagram BCR Benefit Cost Ratio
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1 CBR Cost Benefit Ratio
Total Float = LS - ES or Total Float = LF – EF CPI Cost Performance Index
Free Float = ES of Following - ES of Present - DUR of Present CV Cost Variance
EF = ES + duration - 1 DUR Duration
ES = EF of predecessor + 1 EAC Estimate at Completion
LF = LS of successor - 1 EF Early Finish
LS = LF - duration + 1 EMV Expected Monetary Value
ES Early Start
Project Selection ETC Estimate to Complete
PV = FV / (1+r)^n EV Earned Value
FV = PV * (1+r)^n FV Future Value
NPV = Formula not required. Select biggest number. IRR Internal Rate of Return
ROI = Formula not required. Select biggest number. JIT Just-in-Time
IRR = Formula not required. Select biggest number. LF Late Finish
Payback Period = Add up the projected cash inflow minus expenses LS Late Start
until you reach the initial investment. NPV Net Present Value
BCR = Benefit / Cost PERT Program Evaluation and Review Technique
CBR = Cost / Benefit PTA Point of Total Assumption
Opportunity Cost = The value of the project not chosen. PV Planned Value
PV Present Value
Depreciation ROI Return on Investment
Straight-line Depreciation: SPI Schedule Performance Index
Depr. Expense = Asset Cost (– Scrap Value) / Useful Life SV Schedule Variance
Depr. Rate = 100% / Useful Life TCPI To-Complete Performance Index
Double Declining Balance Method: VAC Variance at Completion
Depr. Rate = 2 * (100% / Useful Life) σ Sigma / Standard Deviation
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year ^ “To the power of” (2^3 = 2*2*2 = 8)
Book Value = Book Value at beginning of year - Depreciation Expense
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc.
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)

Visit www.pm-prepcast.com for more Exam Resources For disclaimer see PMP® Formula Study Guide
th
Copyright © 2009 by OSP International LLC. All rights reserved. Version 2.1 - Use with PMBOK® Guide 4 Edition

You might also like