0% found this document useful (0 votes)
14 views31 pages

Personal Safeguarding

The document consists of monthly safety checklists for various zones at Ghani Global Glass Limited, including Control Room, Production Hall, Utilities, Batch Plant, Workshop, Electrical Rooms, and Quality & Packing Hall. Each checklist details safety hazards observed, including the condition of equipment, personal protective equipment (PPE), and compliance with safety protocols. The inspections are conducted by designated SHEQ representatives and include spaces for recording deviations and actions required.

Uploaded by

Shahzad Majeed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
14 views31 pages

Personal Safeguarding

The document consists of monthly safety checklists for various zones at Ghani Global Glass Limited, including Control Room, Production Hall, Utilities, Batch Plant, Workshop, Electrical Rooms, and Quality & Packing Hall. Each checklist details safety hazards observed, including the condition of equipment, personal protective equipment (PPE), and compliance with safety protocols. The inspections are conducted by designated SHEQ representatives and include spaces for recording deviations and actions required.

Uploaded by

Shahzad Majeed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 31

Ghani Global Glass Limited

Monthly Check List of Electrical,Mechanical & Personal Safeguarding Zone-B GGG-SAF-002

Control Room, Furnace & F2


SHEQ Representative: Muhammad Shoaib Date of Inspection:_________________

The following safety hazards were observed by me and are brought to the attention of the designated person
Date of
Sr # Description Y/N Deviation Job Request# Action By Completion Remarks
All items correctly coded as displayed on color
1
code boards
2 All guards in place and secure

3 Fixed ladders in good condition & numbered

4 Gauges in working conditions

5 Red mark on gauges at max.Limit

6 Pressure gauges calibrated

7 Safety valves calibrated

8 Pressure Vessels within testing cycle

9 MSDS of all chemicals available in stores/ gate

10 All portable equipment numbered

11 Electrical cables damaged

12 Any open wire

13 Any broken switches


Distribution board and panel in good
14
condition
15 Valves/switches/levers easy to reach
16 PPEs worn and are in good condition

17 Helmet worn and good condition

18 Eye protection worn

19 High Noise areas demarcated

20 Ear plug worn and in good condition

21 Sign/notices and posters not faded or missing

22 Permit to work system in place


Purity chemicals and appratus in good
23 condition

24 All chemicals containers labelled

25 Any water leakage in cooling towers area

26 Plant procedures

27 Work Intstruction Displayed

28 SOP for plant Avaialable

29 Transformer are in good condition


30 Area Cleaned

31 Any Leakage from Transformer

32 Unnecessary sounds

33
Measuring Instruments Caliberated

34 Measuring instruments displaying quantities

35
Any sparking,loose connection

36
Sensors Working
37 Gloves,Safety Shoes available

38 All Electrical Tools Available


39 Cable Trunches are cleaned

40
Fire Extinguishers available near Panels,
41 Machines,Transformers,Generators.

42 All pumps motor fans are guarded

43 All pumps coupling guarded

44 Safeguard is firmly mounted

45 Safeguard is corrosion free

46 Safeguard damages

47 Safeguard contains grease/oil spots

48 Insects residing inside safeguard

49
Weighing scale calibrated

50
Safety belts worn where required

Signature:_______________
Ghani Global Glass Limited

Monthly Check List of Electrical,Mechanical & Personal Safeguarding Zone -C GGG-SAF-002

All Production Hall


SHEQ Representative: M.Shoaib Date of Inspection:_________________

The following safety hazards were observed by me and are brought to the attention of the designated person
Date of
Sr # Description Y/N Deviation Job Request# Action By Completion Remarks
All items correctly coded as displayed on color
1
code boards
2 All guards in place and secure

3 Fixed ladders in good condition & numbered

4 Gauges in working conditions

5 Red mark on gauges at max.Limit

6 Pressure gauges calibrated

7 Safety valves calibrated

8 Pressure Vessels within testing cycle

9 MSDS of all chemicals available in stores/ gate

10 All portable equipment numbered

11 Electrical cables damaged

12 Any open wire

13 Any broken switches


Distribution board and panel in good
14
condition
15 Valves/switches/levers easy to reach
16 PPEs worn and are in good condition

17 Helmet worn and good condition

18 Eye protection worn

19 High Noise areas demarcated

20 Ear plug worn and in good condition

21 Sign/notices and posters not faded or missing

22 Permit to work system in place


Purity chemicals and appratus in good
23 condition

24 All chemicals containers labelled

25 Any water leakage in cooling towers area

26 Plant procedures

27 Work Intstruction Displayed

28 SOP for plant Avaialable

29 Transformer are in good condition


30 Area Cleaned

31 Any Leakage from Transformer

32 Unnecessary sounds

33
Measuring Instruments Caliberated

34 Measuring instruments displaying quantities

35
Any sparking,loose connection

36
Sensors Working

37 Gloves,Safety Shoes available


38 All Electrical Tools Available
39 Cable Trunches are cleaned

40
Fire Extinguishers available near Panels,
41 Machines,Transformers,Generators.

42 All pumps motor fans are guarded

43 All pumps coupling guarded

44 Safeguard is firmly mounted

45 Safeguard is corrosion free

46 Safeguard damages

47 Safeguard contains grease/oil spots

48 Insects residing inside safeguard

49 Weighing scale calibrated

50
Safety belts worn where required

Signature:_______________
Ghani Global Glass Limited

Monthly Check List of Electrical,Mechanical & Personal Safeguarding Zone -E GGG-SAF-002

Utilities & LPG


SHEQ Representative: Saleem Babar Date of Inspection:_________________

The following safety hazards were observed by me and are brought to the attention of the designated person
Date of
Sr # Description Y/N Deviation Job Request# Action By Completion Remarks
All items correctly coded as displayed on color
1
code boards
2 All guards in place and secure

3 Fixed ladders in good condition & numbered

4 Gauges in working conditions

5 Red mark on gauges at max.Limit

6 Pressure gauges calibrated

7 Safety valves calibrated

8 Pressure Vessels within testing cycle

9 MSDS of all chemicals available in stores/ gate

10 All portable equipment numbered

11 Electrical cables damaged

12 Any open wire

13 Any broken switches


Distribution board and panel in good
14
condition
15 Valves/switches/levers easy to reach

16 PPEs worn and are in good condition


17 Helmet worn and good condition

18 Eye protection worn

19 High Noise areas demarcated

20 Ear plug worn and in good condition

21 Sign/notices and posters not faded or missing

22 Permit to work system in place


Purity chemicals and appratus in good
23 condition

24 All chemicals containers labelled

25 Any water leakage in cooling towers area

26 Plant procedures

27 Work Intstruction Displayed

28 SOP for plant Avaialable

29 Transformer are in good condition


30 Area Cleaned

31 Any Leakage from Transformer

32 Unnecessary sounds

33
Measuring Instruments Caliberated

34 Measuring instruments displaying quantities

35
Any sparking,loose connection

36
Sensors Working

37 Gloves,Safety Shoes available

38 All Electrical Tools Available


39 Cable Trunches are cleaned
40
Fire Extinguishers available near Panels,
41 Machines,Transformers,Generators.

42 All pumps motor fans are guarded

43 All pumps coupling guarded

44 Safeguard is firmly mounted

45 Safeguard is corrosion free

46 Safeguard damages

47 Safeguard contains grease/oil spots

48 Insects residing inside safeguard

49 Weighing scale calibrated

50
Safety belts worn where required

Signature:_______________
Ghani Global Glass Limited

Monthly Check List of Electrical,Mechanical & Personal Safeguarding Zone -F GGG-SAF-002

Batch Plant & Sand Processig Plant


SHEQ Representative: Zulfiqar ali Date of Inspection:_________________

The following safety hazards were observed by me and are brought to the attention of the designated person
Date of
Sr # Description Y/N Deviation Job Request# Action By Remarks
Completion
All items correctly coded as displayed on color
1
code boards
2 All guards in place and secure

3 Fixed ladders in good condition & numbered

4 Gauges in working conditions

5 Red mark on gauges at max.Limit

6 Pressure gauges calibrated

7 Safety valves calibrated

8 Pressure Vessels within testing cycle

9 MSDS of all chemicals available in stores/ gate

10 All portable equipment numbered

11 Electrical cables damaged

12 Any open wire

13 Any broken switches


Distribution board and panel in good
14
condition
15 Valves/switches/levers easy to reach

16 PPEs worn and are in good condition

17 Helmet worn and good condition


18 Eye protection worn

19 High Noise areas demarcated

20 Ear plug worn and in good condition

21 Sign/notices and posters not faded or missing

22 Permit to work system in place


Purity chemicals and appratus in good
23
condition
24 All chemicals containers labelled

25 Any water leakage in cooling towers area

26 Plant procedures

27 Work Intstruction Displayed

28 SOP for plant Avaialable

29 Transformer are in good condition

30 Area Cleaned

31 Any Leakage from Transformer

32 Unnecessary sounds

33 Measuring Instruments Caliberated

34 Measuring instruments displaying quantities

35 Any sparking,loose connection

36 Sensors Working

37 Gloves,Safety Shoes available

38 All Electrical Tools Available

39 Cable Trunches are cleaned

40 Fire Extinguishers available near Panels,

41 Machines,Transformers,Generators.
42 All pumps motor fans are guarded

43 All pumps coupling guarded

44 Safeguard is firmly mounted

45 Safeguard is corrosion free

46 Safeguard damages

47 Safeguard contains grease/oil spots

48 Insects residing inside safeguard

49 Weighing scale calibrated

50
Safety belts worn where required

Signature:_______________
Ghani Global Glass Limited

Monthly Check List of Electrical,Mechanical & Personal Safeguarding Zone -H GGG-SAF-002

WorkShop
SHEQ Representative: Nauman Ahmad Date of Inspection:_________________

The following safety hazards were observed by me and are brought to the attention of the designated person
Date of
Sr # Description Y/N Deviation Job Request# Action By Remarks
Completion
All items correctly coded as displayed on color
1
code boards
2 All guards in place and secure

3 Fixed ladders in good condition & numbered

4 Gauges in working conditions

5 Red mark on gauges at max.Limit

6 Pressure gauges calibrated

7 Safety valves calibrated

8 Pressure Vessels within testing cycle

9 MSDS of all chemicals available in stores/ gate

10 All portable equipment numbered

11 Electrical cables damaged

12 Any open wire

13 Any broken switches


Distribution board and panel in good
14
condition
15 Valves/switches/levers easy to reach

16 PPEs worn and are in good condition

17 Helmet worn and good condition


18 Eye protection worn

19 High Noise areas demarcated

20 Ear plug worn and in good condition

21 Sign/notices and posters not faded or missing

22 Permit to work system in place


Purity chemicals and appratus in good
23
condition
24 All chemicals containers labelled

25 Any water leakage in cooling towers area

26 Plant procedures

27 Work Intstruction Displayed

28 SOP for plant Avaialable

29 Transformer are in good condition

30 Area Cleaned

31 Any Leakage from Transformer

32 Unnecessary sounds

33 Measuring Instruments Caliberated

34 Measuring instruments displaying quantities

35 Any sparking,loose connection

36 Sensors Working

37 Gloves,Safety Shoes available

38 All Electrical Tools Available

39 Cable Trunches are cleaned

40 Fire Extinguishers available near Panels,

41 Machines,Transformers,Generators.
42 All pumps motor fans are guarded

43 All pumps coupling guarded

44 Safeguard is firmly mounted

45 Safeguard is corrosion free

46 Safeguard damages

47 Safeguard contains grease/oil spots

48 Insects residing inside safeguard

49 Weighing scale calibrated

50
Safety belts worn where required

Signature:_______________
Ghani Global Glass Limited

Monthly Check List of Electrical,Mechanical & Personal Safeguarding Zone -I GGG-SAF-002

Electrical rooms, Generators


SHEQ Representative: Imran Arshad Date of Inspection:_________________

The following safety hazards were observed by me and are brought to the attention of the designated person
Date of
Sr # Description Y/N Deviation Job Request# Action By Completion Remarks
All items correctly coded as displayed on color
1
code boards
2 All guards in place and secure

3 Fixed ladders in good condition & numbered

4 Gauges in working conditions

5 Red mark on gauges at max.Limit

6 Pressure gauges calibrated

7 Safety valves calibrated

8 Pressure Vessels within testing cycle

9 MSDS of all chemicals available in stores/ gate

10 All portable equipment numbered

11 Electrical cables damaged

12 Any open wire

13 Any broken switches


Distribution board and panel in good
14
condition
15 Valves/switches/levers easy to reach

16 PPEs worn and are in good condition

17 Helmet worn and good condition


18 Eye protection worn

19 High Noise areas demarcated

20 Ear plug worn and in good condition

21 Sign/notices and posters not faded or missing

22 Permit to work system in place

23 All chemicals containers labelled

24 Any water leakage in cooling towers area

25 Plant procedures

26 Work Intstruction Displayed

27 SOP for plant Avaialable

28 Transformer are in good condition

29 Area Cleaned

30 Any Leakage from Transformer

31 Unnecessary sounds

32 Measuring Instruments Caliberated

33 Measuring instruments displaying quantities

34 Any sparking,loose connection

35 Sensors Working

36 Gloves,Safety Shoes available

37 All Electrical Tools Available

38 Cable Trunches are cleaned

39 Fire Extinguishers available near Panels,

40 Machines,Transformers,Generators.

41 All pumps motor fans are guarded


42 All pumps coupling guarded

43 Safeguard is firmly mounted

44 Safeguard is corrosion free

45 Safeguard damages

46 Safeguard contains grease/oil spots

47 Insects residing inside safeguard

48 Weighing scale calibrated

49
Safety belts worn where required

Signature:_______________
Ghani Global Glass Limited

Monthly Check List of Electrical,Mechanical & Personal Safeguarding Zone -K GGG-SAF-002

Ampoule Quality & Packing Hall


SHEQ Representative: Zulfiqar Ali Date of Inspection:_________________

The following safety hazards were observed by me and are brought to the attention of the designated person
Date of
Sr # Description Y/N Deviation Job Request# Action By Completion Remarks
All items correctly coded as displayed on color
1
code boards
2 All guards in place and secure

3 Fixed ladders in good condition & numbered

4 Gauges in working conditions

5 Red mark on gauges at max.Limit

6 Pressure gauges calibrated

7 Safety valves calibrated

8 Pressure Vessels within testing cycle

9 MSDS of all chemicals available in stores/ gate

10 All portable equipment numbered

11 Electrical cables damaged

12 Any open wire

13 Any broken switches


Distribution board and panel in good
14
condition
15 Valves/switches/levers easy to reach

16 PPEs worn and are in good condition

17 Helmet worn and good condition


18 Eye protection worn

19 High Noise areas demarcated

20 Ear plug worn and in good condition

21 Sign/notices and posters not faded or missing

22 Permit to work system in place

23 All chemicals containers labelled

24 Any water leakage in cooling towers area

25 Plant procedures

26 Work Intstruction Displayed

27 SOP for plant Avaialable

28 Transformer are in good condition

29 Area Cleaned

30 Any Leakage from Transformer

31 Unnecessary sounds

32 Measuring Instruments Caliberated

33 Measuring instruments displaying quantities

34 Any sparking,loose connection

35 Sensors Working

36 Gloves,Safety Shoes available

37 All Electrical Tools Available

38 Cable Trunches are cleaned

39 Fire Extinguishers available near Panels,

40 Machines,Transformers,Generators.

41 All pumps motor fans are guarded


42 All pumps coupling guarded

43 Safeguard is firmly mounted

44 Safeguard is corrosion free

45 Safeguard damages

46 Safeguard contains grease/oil spots

47 Insects residing inside safeguard

48 Weighing scale calibrated

49
Safety belts worn where required

Signature:_______________
Ghani Global Glass Limited

Monthly Check List of Electrical,Mechanical & Personal Safeguarding Zone -L GGG-SAF-002

OCMI Ampoule Hall


SHEQ Representative: Ansar Iqbal Date of Inspection:_________________

The following safety hazards were observed by me and are brought to the attention of the designated person
Date of
Sr # Description Y/N Deviation Job Request# Action By Completion Remarks
All items correctly coded as displayed on color
1
code boards
2 All guards in place and secure

3 Fixed ladders in good condition & numbered

4 Gauges in working conditions

5 Red mark on gauges at max.Limit

6 Pressure gauges calibrated

7 Safety valves calibrated

8 Pressure Vessels within testing cycle

9 MSDS of all chemicals available in stores/ gate

10 All portable equipment numbered

11 Electrical cables damaged

12 Any open wire

13 Any broken switches


Distribution board and panel in good
14
condition
15 Valves/switches/levers easy to reach

16 PPEs worn and are in good condition

17 Helmet worn and good condition


18 Eye protection worn

19 High Noise areas demarcated

20 Ear plug worn and in good condition

21 Sign/notices and posters not faded or missing

22 Permit to work system in place

23 All chemicals containers labelled

24 Any water leakage in cooling towers area

25 Plant procedures

26 Work Intstruction Displayed

27 SOP for plant Avaialable

28 Transformer are in good condition

29 Area Cleaned

30 Any Leakage from Transformer

31 Unnecessary sounds

32 Measuring Instruments Caliberated

33 Measuring instruments displaying quantities

34 Any sparking,loose connection

35 Sensors Working

36 Gloves,Safety Shoes available

37 All Electrical Tools Available

38 Cable Trunches are cleaned

39 Fire Extinguishers available near Panels,

40 Machines,Transformers,Generators.

41 All pumps motor fans are guarded


42 All pumps coupling guarded

43 Safeguard is firmly mounted

44 Safeguard is corrosion free

45 Safeguard damages

46 Safeguard contains grease/oil spots

47 Insects residing inside safeguard

48 Weighing scale calibrated

49
Safety belts worn where required

Signature:_______________
Ghani Global Glass Limited

Monthly Check List of Electrical,Mechanical & Personal Safeguarding Zone -M GGG-SAF-002

Chinese Ampoule Hall


SHEQ Representative: Furqan Aslam Date of Inspection:_________________

The following safety hazards were observed by me and are brought to the attention of the designated person
Date of
Sr # Description Y/N Deviation Job Request# Action By Completion Remarks
All items correctly coded as displayed on color
1
code boards
2 All guards in place and secure

3 Fixed ladders in good condition & numbered

4 Gauges in working conditions

5 Red mark on gauges at max.Limit

6 Pressure gauges calibrated

7 Safety valves calibrated

8 Pressure Vessels within testing cycle

9 MSDS of all chemicals available in stores/ gate

10 All portable equipment numbered

11 Electrical cables damaged

12 Any open wire

13 Any broken switches


Distribution board and panel in good
14
condition
15 Valves/switches/levers easy to reach

16 PPEs worn and are in good condition

17 Helmet worn and good condition


18 Eye protection worn

19 High Noise areas demarcated

20 Ear plug worn and in good condition

21 Sign/notices and posters not faded or missing

22 Permit to work system in place

23 All chemicals containers labelled

24 Any water leakage in cooling towers area

25 Plant procedures

26 Work Intstruction Displayed

27 SOP for plant Avaialable

28 Transformer are in good condition

29 Area Cleaned

30 Any Leakage from Transformer

31 Unnecessary sounds

32 Measuring Instruments Caliberated

33 Measuring instruments displaying quantities

34 Any sparking,loose connection

35 Sensors Working

36 Gloves,Safety Shoes available

37 All Electrical Tools Available

38 Cable Trunches are cleaned

39 Fire Extinguishers available near Panels,

40 Machines,Transformers,Generators.

41 All pumps motor fans are guarded


42 All pumps coupling guarded

43 Safeguard is firmly mounted

44 Safeguard is corrosion free

45 Safeguard damages

46 Safeguard contains grease/oil spots

47 Insects residing inside safeguard

48 Weighing scale calibrated

49
Safety belts worn where required

Signature:_______________
Monthly Check List for Kitchen GGG-SAF-004
SHEQ Representative:Nasir Hameed Date of Inspection:_________________

The following safety hazards were observed by me and are brought to the attention of the designated person
Date of
Sr # Description Y/N Deviation Job Request# Action By Remarks
Completion
1 General house keeping.

2 Kitchen Staff Uniform is clean

3 Disposable Gloves for handling and serving food ?

4 Hat for covering head is available?

5 Health Condition of kitchen Staff? Remarks

6 Floor is clean.

7 Wall are painted.

8 All window pans are clean.

9 Doors are lockable and painted.

10 Wash basin is cleaned and no leakages.

11 All water taps are functional.

12 Waste bins are emptied.

13 Kitchen is dust free zone.

14 Exhaust fan is functional.

15 Sufficient ventilation is available.

16 Insects are not present in kitchen premises.

17 All utensils are stored properly in racks.

18 Is there any falling hazard?

19 Refrigerator/Freezer and oven are functional.

20 No any smell from Refrigerator/Freezer and oven.

21 Kitchen staff is well dressed.

22 All kitchen employees are medical fit.

23 Any gas leakages?

24 Drain is into sanitation system.


Signature:_____________________
Ghani Global Glass Limited

Monthly Check List of Fire Extinguishers GGG-SAF-003


SHEQ Representative : M.Shoaib Date of Inspection:_________________

The following safety hazards were observed by me and are brought to the attention of the designated person
Date of
Description Y/N Deviation Job Request# Action By Remarks
Sr # Completion
Fire Protection & Prevention Numbered Seal Pressure Signage Valve Paint
1 Fire extinguisher FE-01
2 Fire extinguisher FE-02
3 Fire extinguisher FE-03
4 Fire extinguisher FE-04
5 Fire extinguisher FE-05
6 Fire extinguisher FE-06
7 Fire extinguisher FE-07
8 Fire extinguisher FE-08
9 Fire extinguisher FE-09
10 Fire extinguisher FE-10
11 Fire extinguisher FE-11
12 Fire extinguisher FE-12
13 Fire extinguisher FE-13
14 Fire extinguisher FE-14
15 Fire extinguisher FE-15
16 Fire extinguisher FE-16
17 Fire extinguisher FE-17
18 Fire extinguisher FE-18
19 Fire extinguisher FE-19
20 Fire extinguisher FE-20
21 Fire extinguisher FE-21
22 Fire extinguisher FE-22
23 Fire extinguisher FE-23
24 Fire extinguisher FE-24
25 Fire extinguisher FE-25
26 Fire extinguisher FE-26
27 Fire extinguisher FE-27
28 Fire extinguisher FE-28
29 Fire extinguisher FE-29
30 Fire extinguisher FE-30
31 Fire extinguisher FE-31
32 Fire extinguisher FE-32
33 Fire extinguisher FE-33
34 Fire extinguisher FE-34
35 Fire extinguisher FE-35
36 Fire extinguisher FE-36
37 Fire extinguisher FE-37
38 Fire extinguisher FE-38
39 Fire extinguisher FE-39
40 Fire extinguisher FE-40
41 Fire extinguisher FE-41
42 Fire extinguisher FE-42
43 Fire extinguisher FE-43
44 Fire extinguisher FE-44
45 Fire extinguisher FE-45
46 Fire extinguisher FE-46
47 Fire extinguisher FE-47
48 Fire extinguisher FE-48
49 Fire extinguisher FE-49
50 Fire extinguisher FE-50
51 Fire extinguisher FE-51
Signature:_______________
Ghani Global Glass Limited

Monthly Check List of Fire Protection & Prevention GGG-SAF-003


SHEQ Representative : M.Farasat Saleem Date of Inspection:_________________

The following safety hazards were observed by me and are brought to the attention of the designated person
Date of
Description Y/N Deviation Job Request# Action By Remarks
Sr # Completion
Fire Protection & Prevention Numbered Seal Pressure Signage Valve Paint
1 Fire extinguisher FE-01
2 Fire extinguisher FE-02
3 Fire extinguisher FE-03
4 Fire extinguisher FE-04
5 Fire extinguisher FE-05
6 Fire extinguisher FE-06
7 Fire extinguisher FE-07
8 Fire extinguisher FE-08
9 Fire extinguisher FE-09
10 Fire extinguisher FE-10
11 Fire extinguisher FE-11
12 Fire extinguisher FE-12
13 Fire extinguisher FE-13
14 Fire extinguisher FE-14
15 Fire extinguisher FE-15
16 Fire extinguisher FE-16
17 Fire extinguisher FE-17
18 Fire extinguisher FE-18
19 Fire extinguisher FE-19
20 Fire extinguisher FE-20
21 Fire Buckets filled
22 Fire Hydrants # 1 working
23 Fire Hydrants # 2working
24 Fire Hydrants # 3 working
25 Fire Hydrants # 4 working
26 Safety committees working
27 Holder moving properly
28 Natural Gas leaking
29 Smoke Detector.
30 Smoking Area Define.