MATERIAL TRACEABILITY PROCEDURE
1. SCOPE
This procedure applies to identification and traceability of material and constructed work under the
responsibility of WACOM and its Subcontractors at the stages of supply, and installation.
2. PURPOSE
To ensure that:
All installed work can be identified and traced to the applicable drawing,
inspection report, specification or other document,
All traceability marks and certificates received are maintained throughout the
construction process,
Contractor/Company traceability requirements are met,
3. REFERENCES
ISO 9001:2015 - Quality management systems
Material Control Procedure
Control of Non-Conforming Product
4. DEFINITIONS
Material Certificate A certificate that provides the capability to identify the chemical analysis and
mechanical properties of materials throughout manufacturing, construction and plant
operation
Normal Traceability The ability to trace received permanent material to its manufacturer’s certificate
Total or Full The ability to trace any installed permanent material back to its source material and
Traceability: the respective material certificate
Certification The authoritative act of documenting compliance with requirements. The requirements
can be related to personnel, processes, products, organizations and services
Company TotalEnergies
Contractor Wacom Group
5. RESPONSIBILITIES
The Material Engineer is the overall responsible for ensuring that traceability and certification
requirements are adequately addressed and specified in the respective purchase orders for WACOM
supplied permanent material.
The Material Controller(s) is responsible for ensuring that identification and certificates are preserved
during the material receiving, storage and supply stage.
The Construction Superintendent(s) in conjunction with the discipline QC Inspector(s) are responsible for
ensuring that identification and traceability are maintained during the construction process.
All project personnel involved with material/equipment acquisition, processing and installation should be
familiar and implement the requirements of this procedure.
6. PROCEDURE
6.1 WACOM supplied Material Procurement
6.1.1. The Material Controller/ Engineer in conjunction with the QC Manager shall review and define
requirements for identification, traceability and certification of material/equipment to be procured
by WACOM. These requirements shall be clearly defined in the purchase order data.
6.1.2. Where applicable, purchase order and subcontract data shall include instructions to vendors and
subcontractors to confirm material identification during production and delivery and specifically in
the case of alloy steels through Positive Material Identification (PMI) as per applicable
procedure.
6.2 Receipt and Storage of Materials
6.2.1. On receipt, materials/equipment shall be checked to ensure that appropriate identification and
material certificates are included with the consignment and this information shall be recorded on
the Material Receiving Reports.
6.2.2. For materials with full traceability or any other special requirements, or if required by the
applicable Inspection and Test Plan, QC inspectors will follow the material checks and carry out
inspection including checks of identification marks and traceability.
6.2.3. Items or bundles of items that are individually tagged and identified shall be stored in the
warehouse such as to ensure easy recognition; Material Controller(s) and Storekeeper(s) shall
ensure that identification marks and tags do not get erased or detached.
6.3 Issue of Permanent Materials
6.3.1 All permanent materials supplied for the project shall fulfill the requirements
specified by the contract specifications. Issue of permanent materials and
definition of WACOM.s personnel involved and their activities/ interrelations.
6.3.2 The control of non conforming materials is defined in procedure. Personnel
whose activities are defined there in shall refer to paragraph 6.4 to 6.8 for
certification and traceability requirements.
6.3.3 During construction/installation and until mechanical completion, all personnel
involved shall refer to paragraphs 6.4 to 6.8 for the definition of the traceability
requirements during processing materials including installation.
6.4 Traceability of Civil Materials
6.4.1. Traceability and approval of civil materials shall be in accordance with
specifications and QC documentation.
6.4.2. Cement shall be checked as acceptable (manufacturer’s certificate) prior to
loading into the silo, only conformant cement shall be used.
6.4.3. Aggregates are received into a 'Bulk' storage area and sample tests taken. If
these are within specification they are then moved to the 'Feed' storage or Batch
Plant.
6.4.4. All water shall be tested before initial use both at source and storage supply.
Testing thereafter shall be in accordance with specifications. Mix water shall
conform to requirements in “Ready-Mixed Portland Cement Concrete”.
6.4.5. Additives are received with a manufacturers certificate of analysis. If stored for a
period exceeding the “use by” date specified by the manufacturer then they are
tested prior to use.
6.4.6. Reinforcement (Rebar): all rebar is supplied with a manufacturer’s mill certificate.
Coated rebar is supplied with a certificate from the coating manufacturer. Both
sets of certificates shall be checked against the tags on the bundle of bar during
receiving inspection.
6.5 Inspection, Measuring and Test Equipment Calibration
Equipment calibration traceability requirements are defined in Wacom calibration procedure
6.6 Certification and Traceability Requirements of Material
The following material traceability system will be used for the Project job site. For all
bulk material, certification and traceability requirements shall be in accordance with
contractual requirements.
6.7 Material requiring Normal Traceability.
Receiving inspection (Warehouse Inspection) of material
a) Upon receival of materials the Material Controller or his designee shall verify receipt of the QC
Data Book, type of Material Certificate and color code as applicable.
b) Color coding shall be along the longitudinal axis not on the circumference. Color coding system
for material is defined in the CONTRACTOR’s specification: “Identification of Material”.
Fabrication and installation traceability of material
a) After issuing the materials to the Construction team, the Construction team shall be responsible
for the material control. QC Inspectors and Supervisor shall check/monitor the team's quality
control activities (incl. traceability control). Materials shall be checked against the material
isometric drawings and materials lists.
b) Color coding in accordance with the specification shall be maintained during all stages of
fabrication. When cutting material, the cut material shall be identified by color coding or marking
6.8 Material requiring Full Traceability.
6.8.1 Receiving inspection (Warehouse Inspection) of material
Upon receival of material requiring full traceability, the responsible QC Inspector
shall:
review and compile separately the material certificate as appropriate
Register the following data (for material components) into a material certificate /Heat No.
Control Log (preferably a computerized data base) to permit tracing the material certificate
from a Heat No. originally marked on each material component upon receipt:
Purchase order No. (if applicable)
Material Certificate No.
Material identification number/grade.
Manufacturer's name.
Heat number
Size/schedule.
File No. (QC Data Book).
Where practical, material requiring full traceability shall be stored in geographically
separated areas at the open stores yard.
6.8.2 Fabrication and installation traceability of material
a) Before requesting the issuance of material, the Material Supervisor shall check material grade
on the isometric drawing. Material issuer shall also check the material to be issued using the
information available on the “Material Request sheet”, MRS.
b) After issuing the materials to the Construction team, they shall be responsible
for the material control. QC Inspectors and the responsible Material Supervisor
shall check/monitor the Construction Group's activities related to traceability
control). Materials shall be checked against the material isometric drawings and
materials lists.
c) Fabrication areas for carbon steel, low temperature carbon steel, low alloy steel and stainless
steel, shall be separated to ensure that there is no mixing or misusing of materials and welding
materials.
d) During fabrication the following steps shall be followed:
· When cutting pipes, the Material Supervisor or his designee shall
ensure that the cut pipes can be identified by material identification
No. (Heat No.).
· After fit-up and before welding, the Material Supervisor or his
designee shall check the Heat No. on material components against
the marked copy of the “Material Request sheet”, MRS.
· After checking the Heat No., the Material Supervisor or his designee
shall mark the Heat No. on the isometric drawing and on the material
identification sheet.
· The Heat No. for each block set item such as vent connection, drain
connection, pressure instrument connection, etc., shall also be
marked on the isometric drawing and on the material identification
sheet.
· The Heat No marked on each material component shall be recorded
on each isometric drawing and on the material identification sheet.
The materials should be segregated with every isometric drawing for
its fabrication.
· Material test packs/traceability details are to be handed over to the
CONTRACTOR/COMPANY with the final hand over documentation.
e) After pre-fabrication, and before blast/painting and/or PWHT is carried out:
The QC Inspectors shall check color code, and material identification No. (Heat No.) on
material, and on the isometric drawing.
6.9 Positive Material Identification (PMI)
6.9.1 PMI shall be carried out where required, and in accordance with client spec.
6.10 Welding
Welding records including identification and traceability shall be maintained by QC department
using the welding module of the WACOM DOC. system.
Certification and traceability of welding consumables shall be in accordance with client spec's
6.11 Certification and Traceability Requirements for Structural Steel
Receiving inspection (warehouse inspection) of structural steel:
· On the arrival of structural materials, the QC Inspector shall check for
shipping damage, quantity, size, material certificates release notes and
markings against the packing list. Material certificate requirements shall be
in accordance with contract requirements.
· At the same time, QC Inspector shall check for the availability of QC Data
Book.
6.12 Equipment, Tagged Items, Instruments Traceability Requirements
On the arrival of materials, the Material Controller shall check for shipping damage, quantity,
size, and marking against the packing list.
At the same time, the QC Inspector shall check for the availability of QC Data Book.