CHECK LIST
20 READY BUILT FACTORIES& 12 SUPPORT CLIENT MODON
Project Name
UNITS- WAAD AL SHAMAL
PMC CONSOLIDATED CONSULTANT GROUP (CCG)
Contractor SAUDI ZAAS CONSTRUCTION COMPANY
WAS1-05-004-SZC-TS9-1-QUM-
Related ITP
EARTH WORK ( EXCAVATION & ITP-0001_01
Checklist Title:
BACKFILLING/COMPACTION) WAS1-05-004-SZC-TS9-1-QUM-
Related MST
MST-0002_00
READY BUILT FACTORIES AND SUPPORT
Related FIR
Works Location: UNITS
Status - Acceptable
SN Description of checking to be carried out Remarks
Yes No NA
Approved Shop Drawings,Material Submittals,Method Statement obtained
1 from Employer/Engineer.
Materials to be use are Approved by Employer/Engineer as per
2
Requirements and / or MIR.
3 Approved Mock-Up and Trial Area ,IF Required by Employer/Engineer
4 Has the site survey conducted for the designated area
5 Are the undergroud utilities identified and protected
6 Has the excavation Permit issued prior to the start of the activity.
7 Is the excavation done as per the levels approved.
8 Is the excavation done as per the coordinates mentioned in the Drawings.
9 Has the debris and rubbish material carted away.
10 Are safety measures and precautions implemented.
Backfilling / Compaction
12 Is the backfilling area cleaned properly.
13 Is the Compaction done properly Layer by layer - 200 mm thick.
15 fill shall be compacted at least 95% MDD
16 Is the compaction test taken.
17 compaction test shall be taken 1 point each 50m2 area
Remarks:
For Contractor For Supervision Consultant (PMC)
Name Aleem Akhtar
Designation QA/QC Engineer
Signature
Date