RFPII
RFPII
VOLUME – II
                        Regional Office
           National Highways Authority of India
          (Ministry of Road, Transport & Highways)
  Coworking studio, 4th Floor, D-13, Industrial Area near Rajiv
    Nagar under pass at Atal Path Patliputra Patna- 800013
   VOLUME - II
SECTION: VIII
BILL OF QUANTITIES
                                          APPENDIX-I
 The Appendix forms part of Bid. Bidders are required to fill up all the blanks in the form of Bid
 and Appendix thereto)
To
Dear Sir,
        Having examined the site of works and Bid Documents, comprising Instructions to
        Bidders, Scope of works, Conditions of Contract, Technical Specifications, Bill of
        Quantities and schedules for the execution of the above named works, we, the
        undersigned offer to execute and complete such works and remedy any defects
        therein in conformity with the said bid documents for the sum of Rs.
        (Rupees                                                 ) or such other sum as
        may be ascertained in accordance with the said Bid documents.
 2.    We undertake, if our Bid is accepted, to commence the work within five (5) days of
       receipt of the order to commence, and to complete and deliver the sections and
       whole of the works comprised in the Contract within the period stated in the
       bid hereto.
 3.    If our Bid is accepted, we will furnish Performance Security (ies) in the form of a Bank
         Guarantee to be jointly and severally bound on us, in accordance with the Conditions
         of Contract.
 4.     We agree to abide by this Bid for the period of One Hundred & Twenty (120) days
        from the last date fixed for Bid Submission and it shall remain binding upon us and
        may be accepted at any time before the expiry of that period.
 5.    We confirm our agreement to treat the Bid documents and other records connected
       with the works as secret and confidential documents and shall not communicate
       information contained therein to any person other than the person authorised by the
        Employer or use such information in any manner prejudicial to the safety and integrity
        of the works.
6.   Unless and until an agreement is prepared and executed, this Bid, together with your
      written acceptance thereof, shall constitute a binding Contract between us, but
      without prejudice to your right to withdraw such acceptance without assigning any
      reasons thereof.
7.    We understand that you are not bound to accept the lowest or any bid you may
      receive.
Address :
Signature of Witness
Name of witness
Address of witness
9.00 Preamble
9:01 The bill of quantities shall be read in conjunction with the instruction to Bidders Conditions of Contract
Scope of Work and Specifications.
9.02 The quantities given in the Bill of quantities are estimated quantities. The basis of payment will be actual
quantities of work indented and carried out and valued at the rates and prices tendered in the priced Bills of
quantities where applicable and otherwise at such rates and prices as the Engineer may fix within the terms of
Contract.
9.03 The rates and prices tendered in the priced Bit of Quantities shall include all equipment plant tools spares
labour supervision overheads, consumables, materials, erection maintenance, testing of input material delivered,
profit taxes and duties together with all general risk, liabilities and obligations set out and implied in the Contract
and other incidentals to comply with the requirements of technical specifications and scope of work.
904 The rates and prices shall be quoted entirely in Indian Currency.
905    A rate or price shall be entered as a single rate as Tender Premium above/ below on the amount in General
Abstract
906     The whole cost of complying with the provisions of the contract shall be included in the items provided as
the priced Bill of Quantities and where no rates are provided the cost shall be deemed to be distributed among the
rates and prices entered for the related items of work.
9.07 The contractor shall keep the entire carriageway neat and clean throughout the contract period. The
contractor shall maintain guard rails railings, crash barriers, road furniture etc. in good condition by cleaning them
frequently as advised/required using suitable detergents/chemicals.
           o The staff of the contractor shall wear safety jackets shoes helmets etc while on duty and any violation
             will attract a fine of Rs 5,000/- for each incident.
           o Failure to erect safety signage or trying to carry out the works without proper precautions/safety
             measures as required will attract a fine of Rs 5.000/- for each incident.
9.08 The Tendered rate for incident Management shall include all equipment, labour, material, consumable tools
spares and other incidentals to comply with the requirement of the scope of the work and technical specifications.
9.09 General directions and descriptions of work and materials are not necessarily repeated or summarized in the
Bill of Quantities. Reference to the relevant sections of the bidding document shall be made before entering rates or
prices against each item in the Bill of Quantities.
DESCRIPTION OF WORK:-
ABSTRACT OF COST
            Routine Maintenance and Incident Management of Purnea – Dalkhola Section of NH-27 from Km 410.700 to Km 447.000 in the State of Bihar
                                                         NIT No. 283/RO-PATNA/NHAI/2025-26
   Bill No :
                 Side Slope & Earthen Shoulder Work, & Median Work
       1
                 Side Slope & Shoulder Embankment : Construction of Embankment (Side Slope &
                 Shoulder ) with Material obtained from Borrow pits. Construction of Embankment
        2        with approved material obtained from Borrow pits with approved material obtained                          Cum        224.00
                                                                                                            22,358.18                             5,008,231.20
                 from borrow pits with all lifts and leads, transporting to site, spreading, grading to
                 required slope and compacting to meet requirement of Table 300-2.
                 Construction of Granular shoulders including all leads and lifts complete as per
        4                                                                                                                  Cum      3,100.60
                 drawing and Technical Specifications Clause 407.                                            1,089.90                             3,379,343.94
                 Providing and laying pitching on slopes Laid over prepared filter media including
        5                                                                                                                  Cum      3376.40
                 boulder apron laid dry in front of toe as per drawing and technical specifications.       2,876.48                               9,712,139.80
                 Turfing with Sods : Furnishing and laying of the live sods of perennial turf forming
                 grass on embankment slope, verges or other locations shown on the drawing or as
        6                                                                                                              -   Sqm            150.5
                 directed by the engineer including preparation of ground, fetching of sods and                                                         -
                 watering.
                 Construction of chute drain for proper drainage to the connecting Energy dissipating
                 chamber. The construction shall be as per as per cross-section of chute drain. Cost
        7                                                                                                                  Rm             2378
                 to include RCC drain in M-15, filter material and earth work for settled base of chute.      479.41                              1,140,044.05
                 .
                                              Total Bill No : 1
                                                                                                                                                  19,293,324.76
   Bill No :
                 Drain Work
       2
                 Clearing road side/Median open lined/pucca drains to bring them to original shape,
                 drainage capacity including disposal of sediments, extraneous debris and vegetation
        1                                                                                                                  Rm     13.49
                 growth blocking the free flow from site outside ROW with all leads and lifts complete     12,150.00                               163,903.50
                 in all respects as directed by the Engineer-in- Charge and as per Maintenance
            Standards Clause no. 3.1 (Frequency of cleaning in urban areas will be quarterly
            whereas in rural areas it will be twice in a year i.e. before and after monsoon).
                                         Total Bill No 2
                                                                                                                                          2,729,386.24
Bill No :
            Crash Barrier and Guard Rail
    3
            Repair of damaged single faced W-Beam metal crash barrier made out of members.
            Job includes repair of old damaged members by straightening the members and
                                                                                                                   Per
   1        removing and repairing all the existing dents as well as other defects and neatly                              347
                                                                                                     1,465.00     Metre                    508,355.00
            refixing the repaired members as directed by the Engineer-in- Charge including
            fasteners and fixing etc. complete in all respects.
Credit of using Scrap single faced metal beam crash barrier (W beam & Thrie beam)
            Providing and laying Filter material underneath pitching in slopes complete as per
   2                                                                                                  26.68    Cum   3554.90
            drawing and Technical specification as per MORTH specification clause No.2504.                                           94,855.68
            Toe protection (A toe wall for toe protection can either be in dry rubble masonry in
            case of dry rubble pitching or pitching with stones in wire crates or it can be in PCC
            M15 nominal mix if cement concrete block have been used for pitching . Rates for toe
   3        wall can be adopted from respective clauses depending upon approved design. The           141.30   Rm    12537.80
                                                                                                                                   1,771,591.78
            rate for excavation for foundation, dry rubble masonry and PCC M15 have been
            analysed and given in respective chapters. as per MORTH specification clause
            No.2504.4.)
            Back filling behind abutment, wing wall, return wall complete as per drawing and
   4        technical specifications as per MORTH specification clause No.710.1.4 OF IRC 78 &                  Cum      3,008.40
                                                                                                      550.08                       1,654,853.71
            2200. Sandy material
                                         Total Bill No 6
                                                                                                                                   3,881,672.16
Bill No :
            Toll Plaza Items
    8
            Overhead Signs (Providing and erecting overhead signs with a corrosion resistant
            2mm thick aluminium alloy sheet reflectorised with retro reflective sheeting Type-XI
            with vertical and lateral clearance given in clause 802.2 and 802.3 and installed as
            per clause 802.7 over a designed support system of aluminium alloy or galvanised
            steel trestles and trusses of sections and type as per structural design requirements
            and approved plans & as per IRC: 67). The retro reflective sheeting shall be tested
            for a certificate of having the sheeting tested for coefficient of retro reflection,
            daytime colour and luminance, shrinkage, flexibility, linear removal, adhesion,
            impact resistance, specular gloss and fungus resistance, 3 years outdoor weathering
            and its having passed these tests shall be obtained from International/Goverment
            Laboratory/Institute by the manufacturer of the sheeting and in case the certificate
   1        is obtained from international condition, it should also be obtained from indian
            condition within 3 years of launching of product by the manufacture in
            abroad.Alternatively, a certificate conforming to ASTM specification (D4956-09) on
            artificial accelerated weathering requirements from a reputed laboratory in India
            can be accepted provisionally.In such a situation, the Employer/Client, if so desires
            could seek for a performance guarantee which would released after receipt a
            certificate meeting the requirement of three years outdoor weathering of the
            sheeting as per IRC 67:2022 & proof of the same report shall be uploaded while
            quoting tendor. 10 years warranty shall be provided for retro reflective sheeting
            Type-XI as per Clause 6.9 of IRC 67:2022. At the end of warranty period, the sheeting
            shall retain atleast 80% of its retro reflectance. When totally wet, the sheeting shall
            show not less than 90% of the value of the desired retro reflectance.
            Overhead Sign Board attached with canopy truss, Size 60m X 1.83m Providing and
            erecting retro- reflectorised sign on toll plaza canopy as per IRC :67-2022 made of
   2                                                                                                  109.8    Sqm   14140.00
            Type XI sheet vide clause 801.3, fixed over aluminum sheeting, 2 mm thick or                                           1,552,572.00
            aluminum composite material sheet overall thickness of 4 mm
            Solar Blinker: Providing Solar Blinker with Pole including installation and running
   4                                                                                                   10      Nos   16885.5
            charges at authorised Median Cuts and Intersection as per the approval of Engineer.                                     168,855.00
            Dismantling of Structures (Dismantling of existing structures like culverts, bridges,
            retaining walls and other structure comprising of masonry, cement concrete, wood
            work, steel work, including T&P and scaffolding wherever necessary, sorting the
            dismantled material, disposal of unserviceable material and stacking the serviceable
   1                                                                                                  211.2    Cum   1189.80
            material with all lifts and lead of 1000 metres)as per MoRTH specification clause No.                                   251,285.76
            202.
            By Mechanical Means for items No. 2.04( b) & ( c)
            Prestressed / Reinforced cement concrete grade M-20 & above
            Providing structural steel for super- structure complete as per drawing and
   5                                                                                                5.02     MT     131,732.10
            technical specifications                                                                                              661,861.75
                                        Total Bill No : 8
                                                                                                                                 5,070,008.18
            Junction Improvement
            A.( LHS Ch.
            435.300,434.800,435.500,437.000,437.500,437.850,442.400,443.000,443.600,
Bill No :
            446.000,446.900)
   09
            B. (RHS Ch.
            431.600,431.250,432.600,433.200,434.200,434.800,435.000,435.300,
            440.500,443.500,446.800)
            Construction of Embankment          with Material obtained from Borrow pits :
            Construction of Embankment with approved material obtained from Borrow pits
   1        with approved material obtained from borrow pits with all lifts and leads,                       Cum    224
                                                                                                  2,277.00                       510,048.00
            transporting to site, spreading, grading to required slope and compacting to meet
            requirement of Table 300-2.
            Construction of Subgrade and Earthen Shoulders : Construction of sub-grade and
            earthen shoulders with approved material obtained from Borrow pits with approved
   2        material obtained from borrow pits with all lifts and leads, transporting to site,               Cum    227.5
                                                                                                  2,277.00                       518,017.50
            spreading, grading to required slope and compacting to meet requirement of Table
            300-2.
            Granular Sub-Base with Graded Material : Construction of granular sub-base by
            providing close graded material, spreading in uniform layers with motor grader on
   3        prepared surface, mixing by mix in place method with front end loader at OMC, and                Cum   3100.6
                                                                                                  910.80                         2,824,026.48
            compacting with vibratory roller to achieve the desired density, complete as per
            clause 401.
            Providing, laying, spreading and compacting graded stone aggregate to wet mix
            macadam specification including premixing the Material with water at OMC in
   4        mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform                Cum    3365.9
                                                                                                     1,138.50                    3,832,077.15
            layers with grader in sub- base / base course on well prepared surface and
            compacting with vibratory roller to achieve the desired density.
            Providing and laying dense graded bituminous macadam with higher typer HMP
            using crushed aggregates of specified grading, premixed with bituminous binder @
            4.0 per cent by weight of total mix and filler, transporting the hot mix to work site,
   5        laying with a hydrostatic paver finisher with sensor control to the required grade,                 Cum   11958.6
                                                                                                     546.48                      6,535,135.73
            level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to
            achieve the desired compaction as per MoRTH specification clause No. 505 complete
            in all respects.
            Providing and applying primer coat with SS1 bitumen emulsion on prepared surface
   6        of granular Base including clearing of road surface and spraying primer at the rate of              Sqm    47.10
                                                                                                     9,108.00                    428,986.80
            0.70 kg/sqm using mechanical means.
            Tack Coat on Bituminous surfaces:Providing and applying tack coat with bitumen
   7        emulsion using emulsion pressure distributor at the rate of 0.20 kg per sqm on the                  Sqm    14.10
                                                                                                     9,108.00                    128,422.80
            prepared bituminous surface cleaned with mechanical broom.
            Providing and laying bituminous concrete with higher capacity batch type hot mix
            plant using crushed aggregates of specified grading, premixed with bituminous
            binder @5.2 percent of mix and filler, transporting the hot mix to work site, laying
   8        with a hydrostatic paver finisher with sensor control to the required grade, level and              Cum   14354.30
                                                                                                     364.32                      5,229,558.58
            alignment , rolling with smooth wheeled, vibratory and tandem rollers to achieve the
            desired compaction as per MORT&H specification clause no. 507 complete in all
            respects.VG 30
                                        Total Bill No : 10
                                                                                                                                 20,006,273.03
Bill No :
            Signages
   10
    Providing and fixing of retro-reflectorised cautionary, mandatory and informatory
    sign as per clause 801 of MoRTH Specifications for Roads & Bridge Works and IRC:
    67 (2022) made of class -C Micro Prismatic Grade Sheeting of Type XI retro
    reflective sheeting. The retro - reflective sheeting shall have manufacturer logo,
    watermark and lot number on the sheet.
    A QR (Bar) code shall also be placed on the urbackside of the sign board with an
    indelible ink. For signs above 600mm size, retro reflective sheet shall be fixed over 2
    mm thick aluminium sheeting vide or 4mm thick Aluminium composite material
    sheet vide clause 801 of MoRTH Specifications for Roads & Brige Works. For signs
    above 600mm sizes, sign shall be fixed over back support frame of minimum 35 x
    35x 3 mm angle Frame. For signs above 600mm size, Signs shall be supported on Gl
    circular pipe 80 NB, 3.2 mm thickness confirming to IS 1239. Retro-Reflective sheet
    shall be fixed on Substrate with Pressure Sensitive Adhesive. The Substrate shall be
    firmly riveted on Angle Frame @ 200mm spacing with Aluminium Pop rivets using
    Pneumatic Guns. The Angle frame shall be firmly fixed with high strength bolts,
    washers nuts conforming to IS1364 and IS 1367 on Sign Support Pole. Sign Supports
    shall be firmly fixed to the ground by means of properly designed foundation with M
    25 grade cement concrete 45 cm x 45 cm x 60, 60 cm below ground level as per
    approved drawling. All Components of signs and supports including Angle Frame,
    Bolts, Nuts, Washers, etc. other than the reflective portion shall be galvanized by hot
    dip process (Zinc coated, 0.55 kg/sqm; minimum single spot) unless otherwise
    specified. All galvanizing shall be done after fabrication. Alternate white and yellow
1   bands measuring 50 mm long retro-reflective sheeting shall be pasted around Gi
    posts which help in ensuring the visibility/Presence of poles during night time even
    if the sign boards are stolen or totally vandalized. Minimum four bands of such retro-
    reflective sheeting shall be pasted
    starting from a height of 0.5 m above the finish road level. The messages (legends,
    letters, numerals, etc.) and borders as per clause 6.8 of IRC 67 shall be digitally
    printed. Finished Signs shall have an Ultra Violet (UV) protective clear overlay
    applied to the entire face of the signs supplied by reflective sheet manufacturer. The
    agency shall submit 10 years warranty for satisfactory field performance for type XI
    retro reflective sheeting from the retro-reflective sheet manufacturer confirming to
    clause 6.7 & 6.9 of IRC 67. Agency shall submit a certified copy of test reports from
    an Government laboratory/ Institute conforming to clause 6.7 & 6.9 of IRC 67
    including 3 years accelerated outdoor weathering for the retro reflective sheeting.
    The Agency shall submit the sign convertor (manufacturer) name with details of
    essential equipment available with convertor in his fabrication shop such as digital.
    printer, cutter, plotter, laminator, Galvanizing plant, etc. The Agency shall submit
    road sign
    installation drawing in Kmz file for approval before installation and after installation
    submit geo-tagging of all road signs with its installation photos and date of
    installation and other details as mentioned in IRC 67 annexure Vil, complete in all
    respects. The sign supports and its foundation details are indicative. These may be
    increased
    like in coastal areas. This is applicable to all road signs and direction boards.
    90 cm equilateral triangle                                                                 10.00   Each   8141.00
                                                                                                                         81,410.00
    90 cm circular                                                                             10.00   Each   9967.00
                                                                                                                         99,670.00
    90 cm x 75 cm rectangular                                                                  10.00   Each   10176.00
                                                                                                                         101,760.00
    80 cm x 60 cm rectangular                                                                  10.00   Each   8811.00
                                                                                                                         88,110.00
    Direction and Place Identification Signs upto 0.9 sqm Size Board.(Providing and
    erecting direction and place identification retro-reflectorised sign as per IRC:67
    made of high intensity grade sheeting vide clause 801.3, fixed over aluminium
    sheeting, 2 mm thick or Aluminium composite material sheet with overall thickness
    of 4 mm with area not exceeding 0.9 sqm fixed over back support frame of min 35 x
    35 x 3 mm Angle mounted on a mild steel circular pipe 65 NB, firmly fixed to the
    ground by means of properly designed foundation with M25 grade cement concrete
    45 x 45 x 60 cm, 60 cm below ground level as per approved drawing).The retro
    reflective sheeting shall be tested for a certificate of having the sheeting tested for
    coefficient of retro reflection, daytime colour and luminance, shrinkage, flexibility,
    linear removal, adhesion, impact resistance, specular gloss and fungus resistance, 3
    years outdoor weathering and its having passed these tests shall be obtained from
    International/Goverment Laboratory/Institute by the manufacturer of the sheeting
2   and in case the certificate is obtained from international condition, it should also be     9.00    Sqm   14811.80
                                                                                                                         133,306.20
    obtained from indian condition within 3 years of launching of product by the
    manufacture in abroad.Alternatively, a certificate conforming to ASTM specification
    (D4956-09) on artificial accelerated weathering requirements from a reputed
    laboratory in India can be accepted provisionally.In such a situation, the
    Employer/Client, if so desires could seek for a performance guarantee which would
    released after receipt a certificate meeting the requirement of three years outdoor
    weathering of the sheeting as per IRC 67:2022 & proof of the same report shall be
    uploaded while quoting tendor. 7 years warranty shall be provided for retro
    reflection sheeting Type-IV & 10 years warranty shall be provided for retro
    reflective sheeting Type-XI as per Clause 6.9 of IRC 67:2022. At the end of warranty
    period, the sheeting shall retain atleast 80% of its retro reflectance. When totally
    wet, the sheeting shall show not less than 90% of the value of the desired retro
    reflectance.
    Direction and Place Identification Signs with size more than 0.9 sqm size
    Board.(Providing and erecting direction and place identification retro- reflectorised
    sign as per IRC :67 made of high intensity grade sheeting vide clause 801.3, fixed
    over aluminium sheeting, 2 mm thick or Aluminium composite material sheet with
    overall thickness of 4 mm with area exceeding 0.9 sqm fixed over back support
    frame of min 40 x 40 x 5 mm Angle mounted on two nos. of mild steel circular pipe
    65 NB, 3.2mm thickness and 4.5m meter total height firmly fixed to the ground by
    means of properly designed foundation with M 25 grade cement concrete 45 cm x 45
    cm x 60 cm, 60 cm below ground level as per approved drawing).The retro reflective
    sheeting shall be tested for a certificate of having the sheeting tested for coefficient
    of retro reflection, daytime colour and luminance, shrinkage, flexibility, linear
    removal, adhesion, impact resistance, specular gloss and fungus resistance, 3 years
    outdoor weathering and its having passed these tests shall be obtained from
    International/Goverment Laboratory/Institute by the manufacturer of the sheeting
3                                                                                              124.00   Sqm   15533.40
    and in case the certificate is obtained from international condition, it should also be                              1,926,141.60
    obtained from indian condition within 3 years of launching of product by the
    manufacture in abroad.Alternatively, a certificate conforming to ASTM specification
    (D4956-09) on artificial accelerated weathering requirements from a reputed
    laboratory in India can be accepted provisionally.In such a situation, the
    Employer/Client, if so desires could seek for a performance guarantee which would
    released after receipt a certificate meeting the requirement of three years outdoor
    weathering of the sheeting as per IRC 67:2022 & proof of the same report shall be
    uploaded while quoting tendor. 7 years warranty shall be provided for retro
    reflection sheeting Type-IV & 10 years warranty shall be provided for retro
    reflective sheeting Type-XI as per Clause 6.9 of IRC 67:2022. At the end of warranty
    period, the sheeting shall retain atleast 80% of its retro reflectance. When totally
    wet, the sheeting shall show not less than 90% of the value of the desired retro
    reflectance. `
            Road Delineators (Supplying and installation of MS delineators (Road way
            indicators, hazard markers, object markers), 80-100 cm high above ground level,
            painted black and white in 15 cm wide strips, fitted with 80 x 100 mm rectangular or
            75 mm dia circular reflectorised panels at the top, buried or pressed into the ground
            and conforming to IRC-79 and the drawings. MS Delineator made of Mild steel with
            pure polyester powder coating with the minimum thickness of powder coating of
            not less than 40 micron for protection against corrosion. The surface should be
            concealed so that there should not be any exposed surface without powder coating.
            Alternatively,these metal guide poles can be concealed with thermoplastic body. The
            posts shall have fan ellipsoidal or circular design with the height of the pole shall be
            800 to 900 mm above the ground with about 200 to 300 mm base which can be
            anchored onto ground. Mild steel Guide poles shall conform to Type XI sheeting
            specifications as per IRC:67 and ASTM D4956 which would ensure to obtain clear
   4        visibility of the road alignment during night time. The retro reflective sheeting shall    72.00    Each     794.60
                                                                                                                                      57,211.20
            be tested for a certificate of having the sheeting tested for coefficient of retro
            reflection, daytime colour and luminance, shrinkage, flexibility, linear removal,
            adhesion, impact resistance, specular gloss and fungus resistance, 3 years outdoor
            weathering and its having passed these tests shall be obtained from
            International/Goverment Laboratory/Institute by the manufacturer of the sheeting
            and in case the certificate is obtained from international condition, it should also be
            obtained from indian condition within 3 years of launching of product by the
            manufacture in abroad.Alternatively, a certificate conforming to ASTM specification
            (D4956-09) on artificial accelerated weathering requirements from a reputed
            laboratory in India can be accepted provisionally.In such a situation, the
            Employer/Client, if so desires could seek for a performance guarantee which would
            released after receipt a certificate meeting the requirement of three years outdoor
            weathering of the sheeting as per IRC 67:2022
            Solar traffic blinkers for highways typically feature 5mm LEDs, with specifications
            including a flashing frequency of 30-35 per minute, a visibility range of 500 meters,
   5        and a duty cycle of 66.67%. They often utilize a 12V, 12 Ah LiFePo4 battery and a 30-      41.00    Each    16885.50
                                                                                                                                      692,305.50
            watt solar panel. The blinkers are designed for 24/7 operation, offering autonomy of
            up to 48 hours, and have an IP65 rating for weather resistance.
                                        Total Bill No : 10
                                                                                                                                      3,179,914.50
Bill No :   Routine Maintenance ,Crane & Patrolling Vehicle for accident and Traffic
   11       Management System
            Removal of all types of broken down vehicles which have met with accidents from
            the carriageway and towing the same to proper locations i.e. nearest police station
            or some suitable location by using 20 MT or of more capacity pick and carry crane,
            as per the requirement of incident management as per the clause 6.4 of Scope of
            work as per Clause 6.8 "Performance Standard" of scope of work. The crane shall be
                                                                                                                 Per
   1        equipped with precise vehicle tracking system (VTS) (of reputed ISO 9001 company)            6              200000
                                                                                                                Month                  1,200,000.00
            based on Global positioning system (GPS) and GSM / GPRMS technology.The system
            shall include micro, live real time tracking web based software through which use of
            GIS map and transit, stoppage idle, over speed reports of vehicle shall be obtained.
            Specifications shall be as per MoRTH SOP for IMS dt 09.02.2021. Crane should
            adhere to the minimum specifications as described in IRC SP 84-2019.
            Providing, running and maintaing route patrol vehicle as per clause 6.4 of scope of
            work and as per clause 6.8 "Performance Standard' of scope of work. It also include
            removal of dead animals lying on highways and burying them at proper safe location
                                                                                                                 Per
   2        out of ROW. it will be incidental to this work.Payment will be made as defined in            6              250000
                                                                                                                Month                  1,500,000.00
            clause 6.8 of scope of work. Specifications shall be as per MoRTH SOP for IMS dt
            09.02.2021. Patrol vehicle should adhere to the minimum specifications as described
            in NHAI Policy Circular no.: 12.19 dated 20.03.2018.
NAME OF
 FIRM
Percentage
 below on
Estimated
Cost put to
  Tender
Percentage
 above on
Estimated
Cost put to
  Tender
 At par of
estimated
cost put to
 Tender