IAEA Construction Technologies Workshop Constr ction Workshop, Charlotte NC, August 19-20, 2010
Construction Technologies related to Site Preparation Preparation, Civil and Structural Works
Azhar Khan Manager, EC6 Plant Layout, g , y , Containment Design and Constructability, Atomic Energy of Canada Ltd
UNRESTRICTED / ILLIMIT
Overall Project Schedule
UNRESTRICTED / ILLIMIT
Construction Schedule
UNRESTRICTED / ILLIMIT
Site Preparation
UNRESTRICTED / ILLIMIT
Background to Site Planning and Development
 Phases of site planning and development works:
     Advanced site development p Supply-chain infrastructure Off-site management for module fabrication Module delivery, assembly and outfitting Power island construction
 Open top construction:
 Need at least 1 VHL crane
 M d l i ti and prefabrication: Modularization d f b i ti
 Fully developed site infrastructure to support offloading , assembly and outfitting to exact standards before first nuclear concrete.  Module lay-down areas to be hardstand, fully trafficable and heavy y , y y load capable.  Support facilities required for off site module fabrication and module assembly  Large area needed for storage, prefabrication and pre assembly of storage pre-assembly modules
UNRESTRICTED / ILLIMIT
5
Site Development Schedule
 Site development affects construction schedule:
 If lay-down areas are not available for storage, prefabrication and pre-assembly of modules - site construction schedule will be affected  Excavation of power block to be completed before site development
UNRESTRICTED / ILLIMIT
Pre-requisites for Site development and Plant Construction
 It is recommended that the following be completed prior to commencement of site development and plant construction:
 Subsurface (soils and bedrock) testing and analysis to assess site optimum location  Environmental assessment  Site survey, and site survey control programme established  Transportation study for modules, equipment and personnel  Upgrades and load testing of routes required to handle heavy loads of existing roads, bridges or overpasses and barge offload facilities  Significant cuts and fills necessary to provide a flat and level site free of encumbrances and obstructions  Design for both permanent and temporary construction facilities  Electronic three dimensional (3-D) model for all permanent and temporary sites, structures and components  Site drainage, trenching for utilities  Site development schedule  Excavation plan
UNRESTRICTED / ILLIMIT
7
Pre-requisites for Site development and Plant Construction, contd.
 Temporary services facilities and assembly areas  Site development permits, licensing documentation for site preparation and construction licenses  Procurement of equipment and facilities required for site preparation  Develop quality assurance program  Quality Assurrance procedures  Quality surveillance procedures/check lists  Quality control procedures/check lists
UNRESTRICTED / ILLIMIT
Methods Utilized for Site Infrastructure Implementation and Layout for Site Construction
 All weather construction method:  Construction environment isolated from ambient weather  Buildings have temporary enclosures  Qinshan CANDU  Open top Construction  Methods for construction personnel mobility:  Scaffolding  Mobile scissor lifts, bucket trucks  Access to personal services (tool sheds, toilets, wash water)  Mobile communication systems
UNRESTRICTED / ILLIMIT
Methods Utilized for Site Infrastructure Implementation and Layout for Site Construction, contd.
 Transportation:
 Stick build approach  Modularization approach  Combined approach  Heavy haul path  Need barge unloading facility and heavy haul road(s)  Railroads
 Site mapping and measuring:  Existing conditions including topography  Existing buildings and infrastructure  Existing underground infrastructure  Layout of reference points and markers  Laser and global p g positioning system mapping ( g y pp g (GPS) )
UNRESTRICTED / ILLIMIT
10
Methods Utilized for Site Infrastructure Implementation and Layout for Site Construction, contd.
 Three dimensional modeling:
 It can be developed during early design stages so that the entire plant can be designed using available software  There would be cases where the vendor already has a design with approved two dimensional (2-D) drawings that need to be partially modified to account for country specific requirements.  In such cases, it is recommended that the design drawings are input to the 3-D modelling software to derive the required modifications.  The only disadvantage in using 3-D modelling is that considerable time is needed to develop interference-free plant layout, to work out the BOM to be procured, and to develop working drawings to be used in the field.
UNRESTRICTED / ILLIMIT
11
Main Construction Facilities
 Construction management centre:  Use the latest technology to provide direction and control of real time field activities, tracking of equipment, visual and daily debriefing with field personnel  Video conferencing  Real time management of critical path
UNRESTRICTED / ILLIMIT
12
Main Construction Facilities, contd.
 Civil:
 Computerized concrete batch plants:
 Good quality concrete on a continuous basis with no human error
 Concrete/materials testing laboratories  Embedded parts fabrication shop  Reinforcing steel fabrication shop  Shop fabrication mock-up:
 F ll scale or partial scale mock-ups can save on actual work ti Full l ti l l k t l k time
 Structural steel fabrication/assembly shop  Paint shop  Contractor building  Warehouse  Housing for staff g
UNRESTRICTED / ILLIMIT
13
Main Construction Facilities contd.
 Mechanical/Piping:  Pipe fabrication shop  Pickle bath facility  Paint shop  Contractor building  Warehouse  Housing for staff
UNRESTRICTED / ILLIMIT
14
Main Construction Facilities, contd.
 Electrical, Control and Instrumentation:  Electrical cabling shop  Instrument calibration shop  Contractor building  Warehouse  Housing for staff
UNRESTRICTED / ILLIMIT
15
Main Construction Facilities, contd.
 Owner:  Material management centre  Technical and administration building  Lay-down and assembly areas(modules, liner vessels, equipment)  Warehouse  Housing for staff  Transportation depot  VHL crane  Tower c a es and te escop c c a es o e cranes a d telescopic cranes  Construction control room  Construction parking  Security fencing gates and building fencing,
UNRESTRICTED / ILLIMIT
16
Main Construction Facilities, contd.
 Owner contd.:  Temporary power  Fire protection water and service water  Housing for staff  Transportation depot  Cafeteria for workers  First aid station
UNRESTRICTED / ILLIMIT
17
Construction Technologies for Civil and Structural Works
UNRESTRICTED / ILLIMIT
18
Civil and Structural Works
 Civil and structural works comprise the construction (fabrication, manufacture) of buildings, structures and their components and the supply of yard services (drainage, fencing, etc.)  Longest duration on project schedule  Hence important to optimize by using advanced methods that reduce the schedule  Very difficult and very time consuming to correct mistakes  Quality assurance program is critical
UNRESTRICTED / ILLIMIT
19
Civil and Structural Works contd.
 The civil and structural works comprise the following:
 Site clearing, grading and surveying;  Site protection works against flooding, tidal waves, typhoon, tsunami, etc.;  Excavation;  Earth soil/rock removal and disposal;  Site dewatering;  Remedial measures on foundation soil/rock;  Rock and soil slope stabilization;  Building under drainage;  Foundation works;  Building peripheral drainage;  Concrete works abo e foundation; Co c e e o s above ou da o ;  Structural steel fabrication and erection  Yard services  Backfill works  Roads and landscaping  Permanent security construction
UNRESTRICTED / ILLIMIT
20
Excavation
 Requires permits from local jurisdiction prior to start  Requires construction license from regulator prior to start in some countries  Activity of long duration that can last between 6 to 12 months  Sometimes adjacent to operating nuclear power plants  Environment regulations and constraints  It is essential to minimize damage to final foundation material: Protection from blasting near final level  Protection from flood and freezing  It is essential to provide protection to workers  It is essential to provide protection to nearby facilities
UNRESTRICTED / ILLIMIT
21
Excavation Contd.
 Conventional method:  Uses light machinery, blasting and hand excavation machinery excavation.  Advance method:  Precision line blasting;  Chemical foam expansion for breaking rock.
UNRESTRICTED / ILLIMIT
22
Confirmation Of Soundness Of Foundation Materials And Remedial Measures
 Visual examination  Identification of weak areas  Open pit load tests to confirm foundation materials  Conventional remedial measures:  Extra excavation to overcome weak areas;  Thicken and/or enlarged sub-base engineered to reduce differential settlement and tilt of buildings.
 Advanced method:  Consolidation grouting;  Rock anchors;  Bridging of weak areas;  Instrumentation to measure differential settlement and tilt of buildings.
UNRESTRICTED / ILLIMIT
23
Remedial Measures For Slope stabilization
Objective:  Safety of workers equipment and project assets during the workers, construction phase Conventional methods:  Reducing slope of cuts  Use of anchored steel mesh  Advanced methods  Consolidation Grouting  Grouted rock anchors  Earth reinforcing at e oc g
UNRESTRICTED / ILLIMIT
24
Concrete Types
 Responsibility of site engineering to develop the specified mix designs  Nuclear plants are using more concrete; Hundred of thousands of cubic meters  Functional & performance requirements of buildings are different hence it is economical to specify different mixes  Concrete mixes should be developed and approved at least 6 months before concreting program  Supply of constituent materials (aggregates, sand, water, fly ash, etc) must be confirmed a minimum of 12 months before start of concreting program  Portland cement is normally used  Heavy shielding concrete  Higher performance concretes (45-60 MPa) are being specified recently for containment buildings
UNRESTRICTED / ILLIMIT
25
CONCRETE TYPES contd.
 Conventional Concrete Mixes
 Portland cement  25 to 35 MPa  Heavy shielding concrete
Advanced Concrete Mixes:
 High workability concrete;  High performance concrete: 45 to 60 Mpa;  Fly ash concrete; large volume pours;  Pervious or no fine concrete;  Pre-cast concrete;  Self Consolidating Concrete; Self-Consolidating  Self levelling concrete.
UNRESTRICTED / ILLIMIT
26
Concrete Placement Methods
 Conventional placement method:
 Use of buckets and tower cranes to place concrete
 Advanced Concrete Placement Method:
 Concrete placed with pumps
UNRESTRICTED / ILLIMIT
27
Bonding Between Concrete Pours
 Conventional method:
 Expose aggregates to receive the next pour
 Advanced method:
 Green cutting
UNRESTRICTED / ILLIMIT
28
Reinforcing Steel
 Conventional reinforcing steel method:
 Placing steel bars with lap splices  Bar size 44 mm and above are connected by exothermic welding
 Advanced reinforcing steel methods:
 Using mechanical & cad weld splicing  T-headed shear bars  Use of automatic rebar tie machines  Large prefabricated rebar modules
UNRESTRICTED / ILLIMIT
29
Embedded Parts
 Conventional embedded parts:
 Plate type with manually welded strips or studs for anchoring in concrete  Embedded anchor bolts for equipment and structural steel  Penetrations for piping and conduits pp g
 Advance embedded parts method:  Plate type with studs welded with stud gun  Steel plate reinforced walls: Supports are connected directly to the plate
UNRESTRICTED / ILLIMIT
30
Expansion Anchors
 These are anchors drilled into concrete to support structures, systems and components  Objective:
 Should reduce the use of expansion anchors to only support conduits and p y pp non-seismically qualified systems and non vibrating equipment  Anchors should not cut reinforcing steel
UNRESTRICTED / ILLIMIT
31
Foundation Construction
 Conventional foundation construction methods:  Spread footings, combined footings, mat foundations, pile foundations  In the case of mat foundations, multiple pours are used  Advanced foundation construction methods:  Advances in concrete technology and placement methods have  led to single pours for large mats  Advances in the development of seismic isolations p p permit the  isolation of foundations for structures and equipment and thus  protect them from high seismic events
UNRESTRICTED / ILLIMIT
32
Concrete Construction Above Foundation
 Formwork  Conventional formwork:  Slab formwork consists of wood/metal forms supported by shoring  Wall formwork consists of wood/metal face forms held together with form ties  Forms are stripped after concrete has set and achieved sufficient strength so that it can support its dead load plus a small live load  Advanced types of formworks:  Q-deck or left in shutters  Steel plate reinforced walls (no reinforcing steel in walls)  Steel plate modular floors  Pre-fabricated permanent formwork
UNRESTRICTED / ILLIMIT
33
Walls & Columns
 Conventional Method:
 Place conventional form and pour concrete through trunks up to height of 6 to 7 meters.
 Advanced Construction:
 Steel plate reinforced walls;  Self consolidating concrete;  Self levelling concrete.
UNRESTRICTED / ILLIMIT
34
Slab, floors and roofs
 Conventional Method:
 Use conventional concrete mixes conventional reinforcing steel with mixes, lap splicing, conventional formwork
Advanced Method:
 Use Q Deck or left in shutters in slabs not supporting seismically Q-Deck qualified systems  Modular floors  Steel reinforcement concrete composite structures and Deck Plate construction  Self compacting concrete  Pre-fabricated permanent formwork p
UNRESTRICTED / ILLIMIT
35
Structural Steel Fabrication
 Braced frames consisting of columns, beams and bracing, and equipment supporting steel systems  Conventional method
 Cutting and welding of structural steel based on two-dimensional fabrication drawings and using manual measurements  Use of clip angles  Maximize welding in shop
 Advanced method
 Automated fabricating shop  Use of 3D and precision control maintained by lasers  Use of end plate connections
UNRESTRICTED / ILLIMIT
36
Structural Steel Erection
 Conventional method:
 Use of temporary bracing to align and temporarily support the braced frame structures  Use of conventional high strength steel bolts using torque method such as turn of nut and calibrated wrenches  Maximize bolting and minimize welding at site
 Advanced method:  Facilitates modularization and parallel works  Use of buckling restrained braces (BRBs)  Use of twist off bolts
UNRESTRICTED / ILLIMIT
37
Water Proofing
 Required for underground structures, basements, large water transporting system, liquid retaining concrete tanks, etc.  Conventional method:
 Use of rubber water-stops  Use of external painted waterproofing on structures below ground  Use of sump pump installation
 Advanced method:
 Use of superior waterproofing material with advance spraying system  Use of fast setting epoxy injection material
UNRESTRICTED / ILLIMIT
38
Backfilling
Used for areas between open cut and buildings; Used in pipe trenches Used in landscaping Conventional method:  Common backfill in open area  Granular backfill adjacent to building and covering piping in trenches
 Advanced method: C Cement / sand backfill mixture i used t d b kfill i t is d
UNRESTRICTED / ILLIMIT
39
Yard Services
Storm water drainage system Sewage system Plant system, piping and cables Plant roads Conventional method:
 Backfilled trenches
 Advanced method  Tunnels
UNRESTRICTED / ILLIMIT
40
Construction Technologies for Nuclear Power Plant Buildings
UNRESTRICTED / ILLIMIT
41
CONTAINMENT BUILDING
Foundation base slab + steel liner Containment vessel or steel lined concrete Containment wall + dome Shield wall (in double containments) Internal structures
UNRESTRICTED / ILLIMIT
42
FOUNDATION BASE SLAB + LINER
 Large reinforced concrete mat foundations (greater than 5000 m3)  Waterproofing membrane under foundation  Conventional Method:
 Multiple pours, placed to minimize shrinkage C Conventional concrete d i mix ti l t design i
 Advanced Methods:
 Single pour due to improved concrete technology / concrete mixes with low shrinkage cement reduced cement content increased use cement, content, of plasticizer admixtures, etc.  Significant increase in concrete pump use  Increased reliability of batch plants
UNRESTRICTED / ILLIMIT
43
BASE SLAB
UNRESTRICTED / ILLIMIT
44
Example of RB Base Slab Rebar Mat
UNRESTRICTED / ILLIMIT
45
CONTAINMENT WALL
 Conventional Method:
 Use pre-assembled gang wall forms & construct in multiple repetitive pre assembled concrete lifts between 6 to 7 meters  Concrete placement using trunks to pour concrete; not greater than 1 meter fall  Use vibrators for achieving homogeneity  Carpenter crews are employed for erecting forms  Large scaffolding to set up
 Advanced Method:
 Slip-forming:
 Continuous placing of concrete at p p p g pre-planned rates  Hydraulic lift with jacks moving short section of formwork
UNRESTRICTED / ILLIMIT
46
Climbing Formwork
 Climbing formwork is a self supporting formwork system.  Standard steel forms supported from frame  After wall is poured, form is released and rolled back from face  Jacks lift or climb the whole frame up one level  Prefab rebar installed  Formwork panels are closed and next p concrete wall is poured  Standard cycle times
UNRESTRICTED / ILLIMIT
47
CONTAINMENT WALL SLIP-FORMING contd.
UNRESTRICTED / ILLIMIT
48
CONTAINMENT WALL SLIP-FORMING contd.
UNRESTRICTED / ILLIMIT
49
CONTAINMENT WALL SLIP-FORMING contd.
UNRESTRICTED / ILLIMIT
50
CONTAINMENT WALL SLIP-FORMING contd.
UNRESTRICTED / ILLIMIT
51
CONTAINMENT WALL contd.
 Advanced Method contd.:
 Jump forming:  This method is being used to construct practically all steel lined containment walls  Wall is formed in stages with the form lifted hydraulically or jumped g y y j p up to the next stage after concrete has reached sufficient strength  Use of prefabricated rebar modules
UNRESTRICTED / ILLIMIT
52
Jump Forming
UNRESTRICTED / ILLIMIT
53
Jump Forming in Parallel with Liner Construction and Installation
UNRESTRICTED / ILLIMIT
54
Jump Forming and Prefab Rebar Mat
UNRESTRICTED / ILLIMIT
55
Completion of Jump Forming
UNRESTRICTED / ILLIMIT
56
CONTAINMENT DOME
 Conventional Method:
 Support formwork:
 Uses a space truss system and shoring supports from the base slab  Advanced Method:
 Use a permanent steel plate dome formwork, lifted into place with a VHL crane  Jump form the dome  Use of prefabricated rebar modules
UNRESTRICTED / ILLIMIT
57
CONTAINMENT DOME contd.
UNRESTRICTED / ILLIMIT
58
INTERNAL STRUCTURES
 Conventional Method:
 Use preassembled gang wall forms or hand set forms and construct the wall in multiple repetitive lifts  Construction is up to underside of slabs, construct slab and then proceed with columns and walls up to next slab  Conventional concrete mixes are used  Scaffolding is supported from the base slab and subsequently from the next slab
Advanced Methods:
 Use Q-deck or left in shutters supported by steel beams, for slabs not supporting seismically qualified systems  Self consolidating concrete  Self levelling concrete  Proposed methods are to use modular floors and modules with mechanical and electrical systems. These activities are performed off site and q y p subsequently, the modules are transported to site and installed with a VHL crane
UNRESTRICTED / ILLIMIT
59
TURBINE BUILDING
Significant activities are:
 Excavation (significant at coastal sites with large tidal variations)  Dewatering system  Base Slab  Turbine generator Pedestal  Structural Steel  Building Crane (200 tons or greater);
UNRESTRICTED / ILLIMIT
60
TURBINE BUILDING
Conventional Method:
 Base slab is constructed in multiple pours;  For concrete structures use preassembled gang wall forms and construct the wall in multiple repetitive lifts;  Turbine generator p g pedestal is concreted similar to other concrete structures;  Structural steel is erected with conventional method of erecting braced frames, stabilizing with temporary or permanent braces  Roof trusses are installed on columns after being preassembled on ground;  Building Crane is lifted in to place with a heavy lift transportation crane. crane
UNRESTRICTED / ILLIMIT
61
TURBINE BUILDING contd.
Advanced Method:
 Base slabs  single pour or larger pours  Concrete structures  left in shutters, pumped concrete  Turbine pedestal  seismic isolators and self consolidating concrete, p p pumped concrete  Structural Steel  modularized and installed with heavy lift crane, use of buckling restraint braces, twist off bolts  Turbine building crane  installed with VHL crane
UNRESTRICTED / ILLIMIT
62
Turbine Building Excavation
UNRESTRICTED / ILLIMIT
63
TURBINE BUILDING CONSTRUCTION
UNRESTRICTED / ILLIMIT
64
Turbine Building Construction
UNRESTRICTED / ILLIMIT
65
Turbine Building Base Mat
UNRESTRICTED / ILLIMIT
66
TURBINE BUILDING CONSTRUCTION
UNRESTRICTED / ILLIMIT
67
Prefabricated Rebar Mat
UNRESTRICTED / ILLIMIT
68
Wall Rebar Mat
UNRESTRICTED / ILLIMIT
69
UNRESTRICTED / ILLIMIT
70