Commissioning and Decommissioning of Pipelines, District Isolation Test
Commissioning and Decommissioning of Pipelines, District Isolation Test
Commissioning and Decommissioning of Pipelines, District Isolation Test
APPENDIX 1
to PARTICULAR SPECIFICATIONS
Page 2 of 13
Scope of Work
Part of the works is represented by the replacement of pipes. It is intended to have those pipes in service at the time of the first night flow test. Suggestion for Method Statement for the commissioning of new pipes and the decommissioning of old, not anymore usable, pipes and for District Metered Area Isolation Test are given hereafter. However, the Contractor is requested to prepare and submit own Method Statement as mentioned in the Particular Specifications. The commissioning, the decommissioning of pipes and the Isolation Test have to satisfy the Engineer, and it has to be made sure that no water is lost, safety regulations are kept and the nuisance to the population is kept to a minimum.
2.1
2.2
Completed work
The following works are to be completed before a request to connect new pipes can be made: Pipes are to be laid in appropriate lengths of generally not more than 500 meters. Pipes are to be pressure tested, disinfected and flushed. House connections are to be installed including re-orientation of the water meter, pressure tested, disinfected, flushed, connected to the main and re-tested.
2.3
Connection of pipeline
After coordination with DJB and the Engineer the pipe can be connected into the existing distribution system. The network shall than be used once to feed the house connections through the new piping, on DJBs supply day to the area, to make sure that all plots are served properly.
2.4
Commissioning
Having all works completed, the connections at the pipe and the house connections checked with the consent of DJB, the new system could be commissioned, taken into permanent use.
DELHI WATER SUPPLY AND SEWERAGE PROJECT (DWSSP) WATER DISTRIBUTION AND WASTEWATER COLLECTION IMPROVEMENT
Page 3 of 13
3.1
3.2
Coordination
Coordination has to be made with DJB and the Engineer as to the work procedure. Also the date of expected decommissioning and the exact location of the existing, to be decommissioned pipe are to be fixed. Shop drawings are to be ready approved from the Engineer.
3.3 3.3.1
3.3.2
Details on work to be done The following points will be the normal preparation and procedure for the decommissioning (disconnection) of the replaced pipe: Preparation of skilled labor, tools, fittings, dewatering pump, chlorine water solution (10 ppm), hoses, electric source, grinder, welding machine (where required) etc.. Excavation around the pipe at the pre-determined location of disconnection. It has to be ensured that there is enough working space according to the pipe diameter and the method of disconnection. Marking on the pipe, showing the length of the existing pipe to be cut out. The to be removed piece shall generally be of at least 1.5 meters. Cutting the pipe perpendicular to the pipe centerline, using grinder, metal saw or cutter according to the pipe material. Extreme care is to be taken to avoid any dirt or foreign material entering the existing (and remaining) pipe. Installation of the required fittings to plug the existing (and remaining) pipe. All new parts are completely to be submerged in the chlorine solution (10 ppm) for at least 15 minutes directly before being installed. Installation of thrust block, where required. Repair of any possibly damaged protection layer. Greasing of bolts and washers and installing of the protective coat. After the two weeks period, as described hereafter, all temporary parts are to be removed.
DELHI WATER SUPPLY AND SEWERAGE PROJECT (DWSSP) WATER DISTRIBUTION AND WASTEWATER COLLECTION IMPROVEMENT
Page 4 of 13
3.4 3.4.1
3.4.2
Unknown connection The possibility is given that any replaced pipe has an unknown connection to another pipe inside the District Metered Area, as well as even outside the District Metered Area. It is completely mandatory that such connections are found and eliminated. Not finding such connections would lead to heavy loss of water and would be the first step to bypass the newly installed supply system. There are principally two different cases: Connection from within the District Metered Area This will be the somewhat easier case. At the time of supply to the District Metered Area the water will appear immediately and will stop somewhat delayed to the closing of the inflow point. Connection from outside the District Metered Area This will be the somewhat more difficult case. The water will appear not during the supply cycle for the zone but most probably at the time of supply to one of the adjacent zones.
DELHI WATER SUPPLY AND SEWERAGE PROJECT (DWSSP) WATER DISTRIBUTION AND WASTEWATER COLLECTION IMPROVEMENT
Page 5 of 13
3.4.3
Procedures If water should appear at the unplugged ends of the replaced pipe, the Contractor will contact DJB without delay. DJB will provide information about the latest changes in valve settings and pump operations. With this information the source of the supplied water will be encircled, pointing to a possible unknown connection to the decommissioned pipe. The Contractor will immediately, without any further written instruction, start searching for the unknown pipe. Step one (internal connection) Valves in the immediate vicinity of the decommissioned pipe shall be closed. In case that the water flow stops the connection has to be somewhere close. Opening the different valves and assessing the flow of water will pinpoint search. Such opening of valves should be directed in such form as to avoid supply by the loop system. With the water flow from one single direction it will be easier to locate the connection. If this form does not bring the required result the water might come from outside the district. Step two (external connection) If it becomes evident that the water comes through a connection from outside the district, it will be necessary to examine jointly with DJB what changes in pump- or valve settings has been done recently. With such information it should be decided about the measurements to be undertaken. The task will be to isolate in ever-bigger circles the area where the water appears until the source is found. Because this might be a tedious and sometimes even impossible task another measurement shall be taken. Step three Start digging out the decommissioned pipe from both ends until the unknown connection is found. The found pipe has to be followed until at least the border of the district, in order to isolate the district properly.
4.1
4.2
Completed work
The following works are to be completed before a request to connect new pipes can be made: Pipes are to be laid in their full length. Pipes are to be pressure tested, disinfected and flushed.
DELHI WATER SUPPLY AND SEWERAGE PROJECT (DWSSP) WATER DISTRIBUTION AND WASTEWATER COLLECTION IMPROVEMENT
Page 6 of 13
4.3
Connection of pipeline
After coordination with DJB and the Engineer the pipe can be connected into the existing distribution system. The valves at both ends will be kept closed.
4.4
Commissioning
Having all works completed, the connections at the pipe checked with the consent of DJB, the new system could be commissioned, taken into permanent use.
Disconnection Arrangements
Fittings for disconnections/connections will be according to contract drawing Standard Details as shown below:
5.1
5.2
DELHI WATER SUPPLY AND SEWERAGE PROJECT (DWSSP) WATER DISTRIBUTION AND WASTEWATER COLLECTION IMPROVEMENT
Page 7 of 13
5.3
5.4
h- PE pipes (63) 1- End caps 63mm 2- Or, push fit / threaded adaptors. Threaded connectors with plugs.
DELHI WATER SUPPLY AND SEWERAGE PROJECT (DWSSP) WATER DISTRIBUTION AND WASTEWATER COLLECTION IMPROVEMENT
Page 8 of 13
Note: Existing Pipes left open are cancelled (not in service); Closed pipes are still in operation.
6.1
6.2
Inflow point
The new system foresees that each District Metered Area has its own inflow point. This inflow point may be a water meter alone or a pressure reducing valve in combination with a water meter.
6.3
DELHI WATER SUPPLY AND SEWERAGE PROJECT (DWSSP) WATER DISTRIBUTION AND WASTEWATER COLLECTION IMPROVEMENT
Page 9 of 13
valves, installed for the purpose of isolation, can be removed and the relevant pipes closed with end-caps. But it will also mean that the designated area will be served by only using the new feeding point. It has to be kept in mind that such action is only possible where there is no temporary supply needed to adjacent areas. Such areas might be other District Metered Areas or single houses not yet included in any District Metered Area. Those pipes shall stay with the temporary valves until the foreseen final solution is executed. 6.4
6.5 1 2 3 4
DELHI WATER SUPPLY AND SEWERAGE PROJECT (DWSSP) WATER DISTRIBUTION AND WASTEWATER COLLECTION IMPROVEMENT
Page 10 of 13
5 6
Conclusions; Further actions before re-test if required. NOTE: All above reported flow and pressure values shall contain the date and the time of reading (recording) as well as the ID Number of the source device from where the information was born.
DELHI WATER SUPPLY AND SEWERAGE PROJECT (DWSSP) WATER DISTRIBUTION AND WASTEWATER COLLECTION IMPROVEMENT
Page 11 of 13
6.6
Handover / Commissioning Steps DMA / District Taking Over and Documentation Steps - Guide
Step 1 Sectional Taking-over Of Network in a not yet Isolated District or DMA Who From N1) Approved As-built drawings showing new, disconnected and still to be disconnected mains and all temporary isolation valves, PMPs, PRVs, Meters - Hard copy (1 copy) ENGINEER N2) Approved As-built drawings showing new, disconnected and still to be disconnected mains and all temporary isolation valves, PMPs, PRVs, Meters - Soft GIS copy on labelled CD with contents list(1 copy) 3) FORM N1 - Sectional Physical Transfer of Network within a not yet isolated District or DMA & associated documents (From DJB To MC) Sectional Taking-over of a Completed / Isolated District or all Districts in a DMA Step 2 and Transfer to MC 1) Approved As-built drawings showing new, disconnected and still to be disconnected mains, PMPs, PRVs, Meters etc -Hard copy (1 copy) 2) Approved As-built drawings showing new, disconnected and still to be disconnected mains, PMPs, PRVs, Meters etc -Soft copy on labelled CD with contents list(1 copy) 3) "Set Up" Description and simple schematic describing how water gets the district, how the meter and PRVs are set up. 4) The District Schematic as per the sample SOP 5) FORM N2 - Sectional Physical Transfer of an Isolated District or all Districts in a DMA & associated documents (From DJB To MC) Step 3 Start of Trial Tests - Test Plan Submittal For The DMA 1) DMA Test Plan -as per ENGINEER proforma, updated between tests to reflect conditions for subsequent tests 2) Reporting after each test with data analysis and recommendations and next test plan update 4) FORM N3 - Notification of Start of DMA Testing & Plan Submittal Step 4 Confirmation that the Engineer Recommends Commissioning of Completed DMA (all work completed except additional Rehabilitation) 1) Verified Draft As-built drawings showing new & disconnected mains all PMPs, PRVs, Meters, boundaries etc -Hard copy (1 copy) 2) Verified Draft DMA SOP/Manual as per the sample already agreed -Hard Copy (1 copy)
ENGINEER
ENGINEER
ENGINEER ENGINEER
3) A DMA Pre- Commissioning Report based on the last test showing balance of flow meters, reservoir level, pressures at all PMPs, before and after PRVs, head loss assessment in the secondary main, drop test of individual districts. Comparison of flows and pressures with the design data. Data to be at max 8 hr intervals ENGINEER 4) FORM N4 Confirmation that the Engineer Recommends Commissioning of Completed DMA- Draft Documents Step 5 At the End of Completed DMA Commissioning 1) Report showing that levels of no water complaints are low over 2 rationing periods NGWA to comment on Draft commissioning documents and the pre- commissioning reports - within 14 days of receiving Form N4 and associated documents. Notification of Completed Distribution Zone (when all original CIP works are Step 6 completed in the DMA) 1) Final As-built drawings showing new & disconnected mains all PMPs, PRVs, Meters, boundaries etc -Hard copy (1 copy) ENGINEER
MC MC
ENGINEER
DELHI WATER SUPPLY AND SEWERAGE PROJECT (DWSSP) WATER DISTRIBUTION AND WASTEWATER COLLECTION IMPROVEMENT
Page 12 of 13
2) Final As-built drawings showing new & disconnected mains all PMPs, PRVs, Meters, boundaries etc - Soft copy on labelled CD with contents list (1 copy) 3) Final DMA SOP/Manual as per the sample already agreed -Hard Copy (1 copy) 4) Final DMA SOP/Manual as per the sample already agreed -Soft Copy (1 copy) 5) FORM N5 - Notification of Completed and Tested DMA & associated documents transfer
Upon Completion of the Additional Rehabilitation works in all Districts in an already Step 7 commissioned DMA 1) Final As-built drawings showing all additional pipes and fittings installed since the issue of the Final As built drawings associated with Form N5 -Hard copy (1 copy) ENGINEER 2) Final As-built drawings showing all additional pipes and fittings installed since the issue of the Final As built drawings associated with Form N5 -Soft Copy (1 copy) ENGINEER 3) FORM N6 - Notification of Completion of the Additional Rehabilitation works in all Districts in an already commissioned DMA Step 8 Taking- Over Certificate For the Whole of The Works Documentation Transfer to MC Relating to the whole works 1) Handover Committee Report for all works (if not already submitted) ENGINEER 2) Taking-over BOQ covering the whole of the works ENGINEER 3) FORM N7 - Taking- Over Certificate For the Whole of The Works Documentation Transfer to MC Step 9 Defects Liability Certificate For the Whole of The Works ENGINEER to develop a Defects Liability Management Procedure ENGINEER
ENGINEER
Note 1: Steps 1, 2, 7 may not occur for all districts, e.g. some contractors will not have sectional handovers or addition rehabilitation Note 2: Above mentioned Forms will be available with the Engineer, or on Contractors suggestion, new ones will be produced in coordination with the Engineer to better suit the specific conditions if considered necessary.
DELHI WATER SUPPLY AND SEWERAGE PROJECT (DWSSP) WATER DISTRIBUTION AND WASTEWATER COLLECTION IMPROVEMENT
TABLE OF CONTENTS 1 2 Scope of Work.................................................................................................................... 2 Method Statement for: Commissioning of replacement pipes ........................................... 2 2.1 General ....................................................................................................................... 2 2.2 Completed work ......................................................................................................... 2 2.3 Connection of pipeline ............................................................................................... 2 2.4 Commissioning........................................................................................................... 2 Method Statement for: Decommissioning of replaced pipes............................................. 3 3.1 General ....................................................................................................................... 3 3.2 Coordination ............................................................................................................... 3 3.3 Suggested Decommissioning procedure..................................................................... 3 3.3.1 General ............................................................................................................... 3 3.3.2 Details on work to be done ................................................................................. 3 3.4 Observations on and treatment of decommissioned pipe ........................................... 4 3.4.1 General ............................................................................................................... 4 3.4.2 Unknown connection.......................................................................................... 4 3.4.3 Procedures .......................................................................................................... 5 Method Statement for: Commissioning of reinforcement pipes ........................................ 5 4.1 General ....................................................................................................................... 5 4.2 Completed work ......................................................................................................... 5 4.3 Connection of pipeline ............................................................................................... 6 4.4 Commissioning........................................................................................................... 6 Disconnection Arrangements ............................................................................................. 6 5.1 For DI pipes 80mm.................................................................................................. 6 5.2 For Steel pipes DN 80mm ....................................................................................... 6 5.3 For other material DN 80mm .................................................................................. 7 5.4 For pipes of DN 75mm............................................................................................ 7 Method Statement for: Commissioning of District Areas ................................................. 8 6.1 General ....................................................................................................................... 8 6.2 Inflow point ................................................................................................................ 8 6.3 Commissioning of new border ................................................................................... 8 6.4 Commissioning of District Metered Area .................................................................. 9 6.5 Commissioning / Test Reporting................................................................................ 9 6.6 Handover / Commissioning Steps ............................................................................ 11
DELHI WATER SUPPLY AND SEWERAGE PROJECT (DWSSP) WATER DISTRIBUTION AND WASTEWATER COLLECTION IMPROVEMENT