Itp Pipe Supports

This document outlines KBR's inspection test plan for pipe supports. It lists 9 inspection activities with different required levels of inspection for levels 1 through 4. The inspection activities include documentation review, manufacturing inspection, final assembly, load testing, surface coatings inspection, final visual and dimensional inspection, marking/tagging/shipping inspection, and nameplate review. The document notes that inspection is not required for standard pipe supports without springs or insulation, and purchase order requirements take precedence over the document.

Uploaded by

kaml
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
263 views4 pages

Itp Pipe Supports

This document outlines KBR's inspection test plan for pipe supports. It lists 9 inspection activities with different required levels of inspection for levels 1 through 4. The inspection activities include documentation review, manufacturing inspection, final assembly, load testing, surface coatings inspection, final visual and dimensional inspection, marking/tagging/shipping inspection, and nameplate review. The document notes that inspection is not required for standard pipe supports without springs or insulation, and purchase order requirements take precedence over the document.

Uploaded by

kaml
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 4

KBR

INSPECTION TEST PLAN FOR PIPE SUPPORTS


NO.

INSPECTION ACTIVITY
Level 1 Level 2 Level 3
Selected Level of Inspection >

PRE-INSPECTION MEETING

DOCUMENTATION REVIEW
Vendor Quality Plan (To be submitted prior to Pre-Inspection Meeting)
Manufacturing Schedule
List of Major Sub-Orders
Material Substitution Requests
Material Test Reports
Welding Procedures (WPS's & PQR's)
Welder Performance Qualifications
Manufacturer's Data Report

R
R
R
R
R
R
R
R

R
R
R
R
R
R
R
R

W
SW
SW
SW
SW
SW
SW
SW

SW
SW
SW
SW
SW
SW
SW
SW

MANUFACTURING INSPECTION (In Process)


Material Traceability
Insulation Blocks
Springs
Rods & Threads
Counter Weights
Holes
Bolting
Monitor Production Welding

FINAL ASSEMBLY

W/R

SW/R

LOAD TESTING

W/R

SW/R

SURFACE COATINGS
Galvanizing
Neoprene
Painting
Others

W
W
W

SW
SW
SW

FINAL VISUAL & DIMENSIONAL INSPECTION

MARKING, TAGGING & SHIPPING INSPECTION


Preservation, Marking, Tagging
Shipping Preparation & Protection

W
W

W
W

NAMEPLATE REVIEW

Note:

H = Hold Point
W = Witness Point
SW = Spot Witness
R = Review
N/A = Not Applicable

KBR
INSPECTION TEST PLAN FOR PIPE SUPPORTS
NO.
10

INSPECTION ACTIVITY
Level 1 Level 2 Level 3
Selected Level of Inspection >
COMMENTS
Inspection is not required for the following:
Pipe supports of manufacturer's standard design without springs or insulation
material.
If a discrepancy exists between this document and the applicable purchase
order, the information listed on the purchase order shall take precedent.

Note:

H = Hold Point
W = Witness Point
SW = Spot Witness
R = Review
N/A = Not Applicable

KBR
INSPECTION TEST PLAN FOR PIPE SUPPORTS
Level 4

N/A

R
R
R
R
R
R
R
R

R
N/A
N/A
N/A
N/A
N/A
N/A
N/A
R
R

SW
SW
SW

W
W
W

Note:

H = Hold Point
W = Witness Point
SW = Spot Witness
R = Review
N/A = Not Applicable

KBR
INSPECTION TEST PLAN FOR PIPE SUPPORTS
Level 4

Note:

H = Hold Point
W = Witness Point
SW = Spot Witness
R = Review
N/A = Not Applicable