ENVIRONMENTAL IMPACT
ASSESSMENT
    Dr. Anupam Singhal
What is EIA?
 an important procedure for ensuring that
  the likely effects of new development on
  the environment are fully understood and
  taken into account before the development
  is allowed to go ahead
        (DETR and National Assembly for Wales, 1999)
      What is the purpose of EIA ?
  To encourage productive and enjoyable
 harmony between man and his environment;
    to promote efforts which will prevent or
   eliminate damage to the environment and
biosphere and stimulate the health and welfare
  of man; to enrich the understanding of the
   ecological systems and natural resources
          important to the Nation....
(National Environmental Policy Act of 1969, (NEPA)
Section 2, as enacted by the Congress of the United
States of America
    What is the purpose of EIA ?
      To LOOK before you LEAP!
 EIA is now a required process in more than
  100 nations.
 The International Association for Impact
  Assessment (IAIA) is a global network with
  2,700 members from more than 80 countries.
What is it really?
Environmental Impact Assessment is a process,
  set down as a repeatable series of steps to be
  taken, to allow the environmental consequences
  of a proposed development to be assessed.
The environmental consequences have to be
  those INCREMENTAL effects which are due to
  the proposed development, and not those which
  are due to the passage of time or other
  developments not included in the proposal.
Origins and history of EIA
 1960s witnessed the emergence of
  environmentalism (e.g. publication of
  Silent Spring by Rachel Carson in 1962)
 First formal system of EIA established in
  the     US    following   the   National
  Environmental Policy Act (NEPA) of
  1969
Origins and history of EIA
 NEPA sought to ensure that environmental
  concerns were considered in the decision-
  making of Federal Government agencies
 Section 102(2)(c) required agencies to prepare a
  detailed statement on the environmental
  impact of proposals for legislation and other
  major Federal actions significantly affecting the
  quality of the human environment
Origins and history of EIA
 The statement  referred to as an
  Environmental Impact Statement (EIS) -
  should include details on
    any adverse environmental effects
     which cannot be avoided should the
     proposal be implemented
    alternatives to the proposed action
Origins and history of EIA
 Since 1969 a host of other countries have
  adopted EIA legislation
 In 1977 the European Commission began
  drafting a directive on EIA and finally published a
  proposal in 1980
 Directive 85/337/EEC on the assessment of the
  effects of certain public and private projects on
  the environment  the EIA Directive was
  adopted in July 1985 and Member States had
  until 3 July 1988 to implement its requirements
    KEY ELEMENTS OF EIA
1. EIA must be undertaken EARLY in the
   development of proposed projects, plans,
   and programs, and must be completed
   BEFORE a decision to proceed is made.
2. EIA must be an OBJECTIVE, IMPARTIAL
   analytical process, not a way of promoting
   or selling a proposal to decision-
   makersit must use accepted scientific
   principles and methods.
  KEY ELEMENTS OF EIA
3. EIA must analyze all REASONABLY
   FORESEEABLE environmental impacts or
   effects of a proposed action effects may
   be short-term, long-term, direct, or indirect.
4. The process of EIA must be OPEN  to
   government officials at all levels, to
   potential stakeholders (those with direct
   interests in the proposed action), and to the
   PUBLIC.
     KEY ELEMENTS OF EIA
5.   There must be an early, public SCOPING stage in
     EIA to consider ALTERNATIVES and to help focus
     subsequent analysis on the MORE SIGNIFICANT
     potential impacts  rather than studying all possible
     environmental effectsthe GOAL is to reach a
     decision.
6.   Government officials responsible for implementing
     EIA must ENCOURAGE (not just tolerate) PUBLIC
     PARTICIPATION in the process from the scoping
     stage forward.
     KEY ELEMENTS OF EIA
7.   In all EIA processes, effective MITIGATION
     MEASURES must be identified and includedto
     avoid, minimize, or reduce the adverse effects of
     all potentially significant impacts.
8.   EIA reports must include an ENVIRONMENTAL
     MANAGEMENT SYSTEM (EMS) or Action Plan to
     MONITOR the implementation phase of the project,
     plan, or program and provide for CORRECTIVE
     actionssuch action plans must have assured
     FUNDING and be legally enforceable.
The EIA Directive
 The EIA Directive requires projects likely
  to have significant effects on the
  environment by virtue of their nature, size
  or location to undergo an environmental
  assessment before the competent
  authority in question grants consent
The EIA Directive
 The EIA Directive was amended in 1997
  (Directive 97/11/EC). Following signature
  of the Aarhus Convention on 25 June
  1998, Directive 2003/35/EC was adopted
  which amends amongst others the EIA
  Directive and brings it into line with the
  public participation requirements of the
  Aarhus Convention
The EIA Directive
 The EIA Directive defines a project as
   the execution of construction works or of
    other installations or schemes,
   other interventions in the natural
    surroundings and landscape including
    those involving the extraction of mineral
    resources
The EIA Directive
 The EIA should identify, describe and assess
  the direct and indirect effects of a project on
  the following factors:
     human beings, fauna and flora
     soil, water, air, climate and the landscape
     material assets and cultural heritage
     the interaction between the above factors
 EIA should therefore have a strong social
  dimension
                  FINAL
                  REPORT
                                   EXISTING ENVIRONMENTAL
                                   STATUS WITHOUT PROJECT
 DECISION ON
 FEASIBILITY OF
 PROJECT
REMEDIAL               PREDICTION OF IMPACT ON
MEASURES               ENVIRONMENT DUE TO PROPOSED
                       PROJECT
ENVIRONMENTAL IMPACT ASSESSMENT
 Screening       (does the project     Impact assessment
          require EIA?)                  (interpreting the impacts)
 Scoping      (what issues and       Mitigation      (what can be done to
impacts should the EIA address?)         alleviate negative impacts?)
Baseline studies (establish           EIS preparation/review
   the environmental baseline)           (document the EIA findings)
 Alternatives        (consider the     Public consultation
      different approaches)          (consult general public and NGOs)
Impact prediction        (forecast   Monitoring (monitor impacts
   the environmental impacts)                   of project)
Screening
 Is an EIA needed?
 Many projects may have no significant
  environmental effects
 A screening mechanism seeks to identify those
  projects with potentially significant adverse
  environmental effects
 The principal approaches to screening:
     the use of thresholds
     Size of the project
     Sensitivity of the environment
     case-by-case examination against criteria
Scoping
 The scope of an EIA is the key issues and
  impacts that should be included in the
  Environmental Assessment
 Scoping is the process of deciding which
  of a projects possible alternatives and
  impacts should be addressed in the EIA
 An EIA should focus only on the
  significant issues and impacts
Scoping
 Scoping is carried out in discussions
  between the developer, the competent
  authority, relevant agencies and, ideally,
  the public
 Effective     scoping     enables     limited
  resources to be allocated to best effect
  (i.e. through investigation of only the most
  significant impacts)
Baseline studies
 Following the scoping phase, it is essential to
  assemble all the relevant information on the
  current status of the environment
 The baseline study should anticipate the future
  state of the environment assuming the project is
  not undertaken - the no action alternative
 This provides the baseline against which future
  impacts can be assessed
Baseline studies
 Baseline studies should be undertaken for
  each alternative site so that the relative
  severity of the impacts for each alternative
  can be assessed
 New field work may be necessary (e.g.
  ecological survey) if relevant data is not
  already available
Impact assessment
 Impact assessment involves evaluating the
  significance of the impacts identified
 Significance can be determined through
  professional judgement, reference to regulations
  etc.
 Potential for bias in determining what is
  significant
 The conclusions of the impact assessment can
  ultimately be used by decision-makers when
  determining the fate of the project application
Mitigation
 Negative impacts on the environment identified
  during the EIA can be alleviated through
  mitigation measures
 The mitigation hierarchy: Avoid - Reduce -
  Remedy - Compensate - Enhance
 Impacts remaining after mitigation are known as
  residual impacts
 The legislation obstructs the proper process
  of design development
EIS preparation / review
 The Environmental Impact Statement
  (EIS) is a formal document which includes
  information on the development and
  information relating to screening, scoping,
  baseline studies, alternatives etc.
 Common requirement to include a non-
  technical summary
EIS preparation / review
 Once complete, the EIS is submitted to the
  competent authority (along with the
  planning application)
 The EIS is often reviewed (either formally
  or informally)
 The review enables the competent
  authority to decide whether the EIA is
  adequate, accurate and unbiased
Public consultation
 The EIA Directive provides for public
  consultation on the application for
  development and the EIS
Post-project monitoring
 Monitoring should determine:
   the accuracy of the original predictions
   the degree of deviation from the predictions
   the possible reasons for any deviations
   the extent to which mitigation measures have
    achieved their objectives
         What is in an ES?
 Non Technical Summary
 Description of the proposals
 Assessment of Baseline conditions
 Assessment of no development conditions
 Assessment of conditions with
  development
 Mitigation proposals
          What is in an ES?
All conditions assessed for
 Construction phase
 Operation phase
 Termination phase
CONTENT OF EIA ANALYSIS
Physical components:
   Land
   Air
   Water
   Energy
CONTENT OF EIA ANALYSIS
Bio-Cultural components:
   Nature
   Culture
   People
   Access
EIA Impact Analysis Summary Table
    PHASE:        Construction Operation Termination
    __________________________________________________
    Physical:
   Land
   Air
   Water
   Energy
    __________________________________________________
    Bio-Cultural:
   Nature
   Culture
   People
   Access
        Construction Phase
 Temporary
 Higher levels of impact usually deemed
  acceptable
 Difficult to predict
 VERY difficult to enforce conditions
 Usually well influenced by effective
  consultation
            Operation Phase
 Long Term
 Much less room for compromise on standards
 Relatively simpler to predict
 Less difficult to enforce conditions, as the
  conditions are on the project owner
 Usually less influenced by effective consultation
  at scheme level, more at detailed level
              Operation Phase
 Can be several phases
 Project itself may be developed in stages
 Sometimes need to look at
     Commissioning
     Opening
     Operation after period
     Operation once landscaping mature
     Operation at design capacity
     Operation at ultimate capacity
           Consents Process
 ES generally accompanies an application for
  permission to proceed
 May be at Local, Regional, or National level
 Local and regional levels usually can refer
  upwards
 Application will be at outline or detailed stage;
  increasingly difficult to get approval on outline
  applications