1
Environmental Impact
Assessment (EIA)
Processes and Procedure
                                                     2
Definitions of EIA
• Environmental impact assessment (EIA) is a
  systematic procedure for enabling the possible
  environmental impacts of developments to be
  considered before a decision is made on whether
  the project should be given approval to proceed.
    “a process that assesses the impacts of a planned
    activity on the environment – physical, social and
    economic – providing decision-makers with an
    indication of the likely consequences of the
    development actions”.
                                                        3
• Therefore, as an integral component of the
  planning process, EIA enables “potentially negative
  impacts to be mitigated (and positive impacts to
  be maximized) early in the design stages
 EIA is a tool used to guide decision-making in
   ensuring that environmental as well as technical
   and economic considerations are taken into
   account,
 Project and site specific, thus, leading to it being
   highly contextual,
 A process with cyclical and simultaneously linked
   stages,
                                                    4
• The legal, methodological and procedural
  foundations of EIA were established in 1970 by the
  enactment of the National Environmental Policy Act
  (NEPA) in the USA
• .At the international level, lending banks and
  bilateral aid agencies have EIA procedures that
  apply to borrowing and recipient countries.
• Most developing counties have also embraced and
  are in the process of formalizing EIA through
  legislation.
                                                         5
Objectives of EIA
   To identify negative environmental impacts that
    may be expected to occur due to the
    implementation of a development activity.
   To determine the significance of the impacts.
   To incorporate appropriate mitigation into the
    development action.
   To identify the environmental benefits and cost of
    the development activity or project as well as its
    economic and environmental acceptability to the
    community.
   To identify critical environmental problems which
    require further studies and/or monitoring
                                                          6
Objectives cont--
   To examine and select the optimal alternative from
    the various relevant developmental options available.
   To involve the public in decision-making process
    related to good environmental management and
    stewardship.
   To assist all parties involved in development and
    environmental affairs understand their roles,
    responsibilities and overall relationships with one
    another.
                                                     7
EIA Terminology
Environmental Impact Statement (EIS): This is a
 report/document with the results of an EIA study.
 The report is also sometimes referred to as the
 Environmental Statement (ES) or Impact Statement
 (IS) or Environmental Impact Reports (EIR).
Environmental Inventory (EI): This is a description of
 the environment of an area where a specific
 proposed activity is being considered. Its major
 aim is to evaluate potential impacts of a proposed
 development. Other terms similar in nature include
 Environmental Baseline Study (EBS) or
 Environmental Setting (ES).
                                                     8
• Hazard: a potential to damage/harm to people.
• Residual environmental impact: Potential impact
  remaining after mitigatory measures have been
  adopted into a development activity.
• Environmental audit means the systematic
  documentation and periodic objective evaluation of
  the protection and management of the environment;
• Decommissioning: closure of operations after the
  project’s life span.
                                                           9
The origin of EIA
• Before the First World War, rapid industrialization and
  urbanization in western countries was causing rapid
  loss of natural resources.
• This continued to the period after the Second World
  War giving rise to concerns for pollution, quality of life
  and environmental stress
• In early 60s, there was a global consensus that
  human activities were affecting the environment,
  resources, raw materials and people.
• As a result of this, pressure groups formed with the
  aim of getting a tool that can be used to safeguard
  the environment in any development.
                                                   10
• The USA decided to respond to these issues and
  established a National Environmental Policy Act in
  1970 to consider its goal in terms of environmental
  protection.
• The USA became the first country to enact legislation
  on EIA. This was the first time that EIA became the
  official tool to be used to protect the environment.
• The United Nations Conference on the Environment in
  Stockholm in 1972 and subsequent conventions
  formalized EIA.
• At present, all developed countries have
  environmental laws whereas most of the developing
  countries are still adopting it.
                                                    11
EIA in developing Countries
• Until recently, EIA as a new concept was not readily
  understood and accepted as a tool in developing
  countries.
• Developers resisted and argued that it was anti
  development because laws and policies supporting
  it dictated that lands developments causing
  negative impacts should be discontinued.
• Thus, EIA was considered just another bureaucratic
  stumbling block in the path of development
• Secondly, it was conceived as a sinister means by
  which industrialized nations intend to keep
  developing countries from breaking the vicious
  cycle of poverty
                                                      12
• Thirdly, the experts in the developing countries were
  foreigners who were viewed as agents of colonization.
• The need for EIAs has become increasingly important
  and is now a statutory requirement in many
  developing countries.
• Historically, the choice of new projects was primarily
  based on one criterion:
economic viability.
Today, a second and a third choice criteria,
  environmental and social impact, have become a
  strong yardstick,
• This led to the development of the triple bottom-line
  approach (economic, environmental and social) to
  project viability
                                                       13
 EIA legal, policy & institutional
 framework
• EIA takes place within the legal and/or policy and
  institutional frameworks established by individual
  countries and international agencies.
• EIA provision and procedure can contribute to
  successful implementation of project if these
  frameworks are adhered to.
                                                 14
EIA in international environmental law
context
• Key Multilateral Environmental Agreements (MEAs)
  have seen review and improvements in EIA legal,
  policy and institutional arrangements.
• These key agreements include the following;
                                                           15
1.Convention on Environmental Impact Assessment
  in a Trans-boundary Context (Espoo, 1991).
• This is the first multi-lateral EIA treaty. It looks at
  EIA in a trans-boundary context and entered into
  force in 1997.
• The Espoo Convention sets out the obligations of
  Parties to assess the environmental impact of
  certain activities at an early stage of planning.
• It also lays down the general obligation of states to
  notify and consult each other on all major projects
  under consideration that are likely to have a
  significant adverse environmental impact across
  borders.
                                                      16
• Apart from stipulating responsibility of signatory
  countries with regards to proposals that have trans-
  boundary impacts,
• it describes the principles, provisions, procedures to
  be followed and list of activities, contents of
  documentation and criteria of significance that
  apply.
                                                         17
2.Rio Declaration (1992)
• Principle 17 of Rio Declaration on Environment and
  Development calls for use of EIA as a national
  decision making instrument to be used in assessing
  whether proposed activities are likely to have
  significant adverse impact on the environment.
• It also emphasized the role of competent national
  authority in the decision making process.
• The other principle (15) of this declaration that is
  relevant to EIA practice is the application of the
  precautionary principle.
                                                     18
Agenda 21, which was also as a result of this
 convention, proposes that governments should;
“Promote the development of appropriate
 methodologies for making integrated energy,
 environment and economic policy decisions for
 sustainable development, inter alia, through
 environmental impact assessment (9.12(b))
Develop, improve and apply environmental impacts
 assessment, to foster sustainable industrial
 development (9.18)
Carry out investment analysis and feasibility studies
 including environmental assessments for
 establishing forest based processing enterprises.
                                                            19
 Introduce appropriate EIA procedures for proposed projects
  likely to have significant impacts upon biological diversity,
  providing for suitable information to be made widely
• Agenda 21 also sets the framework within which countries
  can establish their national environmental laws under the
  following agreements;
a. UN Convention on climate change and Biological Diversity
   (1992) cited EIA as an implementing mechanism of these
   conventions (article 4 and 14 respectively).
b. Doha Ministerial Declaration encourages countries to
   share expertise and experience with members wishing to
   perform environmental reviews at the national level
   (November, 2001).
c. United Nations Conference on the Environment in
   Stockholm 1972.
                                                       20
National legislations
• National legislation may include a statutory
  requirement for an EIA to be done in a prescribed
  manner for specific development activities.
• Most legislation lists projects for which EIA is a
  mandatory requirement.
• The statutory requirement to carry out an EIA for
  specific projects will, for example, require
  registered experts to carry out the study, the
  authority with the help of lead agencies and
  technical committees to review the EIA and
  approve the project.
                                                        21
• Other national legal requirements that govern the
  use and protection of resources like water,
  fisheries, forests, wildlife, public health etc must
  be identified and complied with during an EIA.
                                                      22
Institutional framework
• EIA institutional systems vary from country-to-
  country and reflecting different types of governance.
• In some countries, either the Ministry of Environment
  or a designated authority or Planning Agency
  administers EIA.
• Environmental issues also involve many disciplines
  and many government bodies with general
  environmental and resource management laws
• Data will therefore have to be collected and collated
  from a wide range of technical ministries, other
  government authorities and parastatals where
  applicable.
                                                    23
EIA guiding principles
• International Association for Impact Assessment
  (IAIA, 1999) and others have developed guiding
  principles for EIA/IA and these include;
24
                                                     25
• Participative: The process should provide appropriate
  opportunities to inform and involve the interested
  and affected publics and incorporate their input in
  decision-making.
• Transparency: Assessment process, outcomes &
  decisions should be open and accessible.
• Certainty: The process and timing of the assessment
  should be agreed in advanced and followed by all
  participants.
• Accountability: The decision-makers and project
  proponents are responsible to all parties for their
  action and decisions under the assessment process.
• Integrated - the process should address the
  interrelationships of social, economic and
  biophysical aspects
                                                             26
• Credibility: Assessment is undertaken with
  professionalism and objectivity.
• Cost-effectiveness: The assessment process and its
  outcomes will ensure environmental protection at the
  least cost to the society.
• Practical - the process should result practical outputs,
  which can be implemented by proponent.
• Relevant - the process should focus information that
  is relevant for development planning and decision-
  making.
• Focused - the process should concentrate on
  significant environmental effects and key issues that
  need to be taken into account in making decisions.
• Interdisciplinary - the process should ensure that the
  appropriate techniques and experts in the relevant
  disciplines are employed, including use of traditional
  knowledge as relevant.
                                                          27
Legislative provisions for EIA in
Zimbabwe
   Established under Section XI of Environmental
    Management Act – and section 2 have listed or
    prescribed projects –
   Under Sec 98 the developer has to submit a
    prospectus to the DG
    A prospectus is some form of a project initial EIA
    or brief upon which the DG can make a decision
    regarding EIA
                                                     28
Section 99 on Contents of an EIA
Statement
An environmental impact assessment report on a
  project shall:
a. give a detailed description of the project and the
    activities to be undertaken in implementing it;
    and
b. state the reasons for selecting the proposed site
    of the project; and
c. give a detailed description of the likely impact the
    project may have on the environment or any
    segment thereof, covering the direct, indirect,
    cumulative, short-term and long-term effects of
    the project; and
                                                          29
d. specify the measures proposed for eliminating,
   reducing or mitigating any anticipated adverse effects
   the project may have on the environment, identifying
   ways of monitoring and managing the environmental
   effects of the project; and
An environmental impact assessment report on a project
   shall:
e. indicate whether the environment of any other country
   is likely to be affected by the project and any
   measures to be taken to minimise any damage to that
   environment;
f. where applicable, indicate how the developer
   proposes to integrate biological diversity in the project;
g. describe concisely the methodology used by the
   developer to compile the environmental impact
   assessment report.
                                                     30
Legislative provisions for EIA statement
review process
Sec 100 of EMA stipulates that:
1) Within sixty days after receiving an environmental
   impact assessment report, the Director-General
   shall:
consider the report and reach a decision on it in
 terms of this section; and
cause the developer to be notified of his decision;
and, if he fails to do so, the project shall be deemed
 to have been approved.
                                                    31
(2) Upon considering an environmental impact
    assessment report, the DG may do any of the
    following:
approve the project to which the EIA report relates;
require the developer to conduct a further EIA of
 the whole or part of the project;
require the developer to supply such further
 information or do such other thing as the DG
 considers necessary or desirable
                                                    32
3) In considering whether or not to approve a project
   to which an EIA report relates, the DG:
shall take into account any likely impact of the
 project on the environment and the actual impact of
 any existing similar project on the environment;
shall have regard to the extent to which the project
 complies with the National Plan and any applicable
 local authority environmental management plan;
may consult any authority, organisation, community,
 agency or person which or who, in his opinion, has an
 interest in the project – Public participation
                                                       33
4) On approval of a project, the DG shall issue to
   the developer a certificate:
identifying the project;
stating the name and address of the developer
 and, where the developer is a company, the
 company’s registered office;
stating the date of issue of the certificate and the
 date of its expiry;
setting out any conditions fixed by the DG in
 terms of subsection (4); and
setting out such other matters as may be
 prescribed.
                                                     34
• A statement on the impact that a development
  activity or proposal may have on the environment
  may turn out to be merely a document for
  obtaining a permit to implement the proposal
• As such the process of review (which also
  involves the public) can minimise this shortfall
• The review process also provides checks and
  balances on the genuineness of the involvement
  of key stakeholders and the need to achieve
  development that is sustainable.
                                                              35
The general objectives from reviewing EIA
• To objectively evaluate the EIA report in relation to the
  terms of reference of the study and the quality of the
  findings obtained.
• To assess the views of all stakeholders on the findings.
• To enable decision-makers to arrive at final decisions on
  how to proceed with implementing the proposal.
• To ensure strong commitment to the implementation of
  recommendations
                                                        36
Issues addressed in the review
 include;
• Compliance with the ToR with which the study
  was instituted to investigate the:
Impacts in their various forms and
Provide mitigatory measures
• Plausibility of methods used in gathering and
  analysing data.
• Clarity in presentation of report (report structure
  and layout).
                                                    37
Final EIA Statement
• After review, the draft EIS is finalised to become a
  manual for managing the environmental aspects of
  the development activity.
• Usually, an Agreement/Letter of acceptance
  between the development proponent and the EIA
  authority is signed and bound together with the final
  EIS.
• This agreement shows acceptance of the findings
  and, more important, recommendations for the EIS
  by the proponent, and a commitment to
  implementation.
• Without such a commitment, the EIS may simply be
  shelved and its recommendations ignored.
                                                         38
In terms of Section 101:
1) A certificate issued by the DG in terms of Sec 100
   shall be valid for two years from the date of its
   issue:
 Provided that, for good cause shown, the Director-General
  may extend the validity of a certificate for not more than
  one year for a project that has been commenced within
  the stipulated period but not yet completed.
2) The DG shall not extend the validity of a
   certificate on a project that has not been
   commenced within the stipulated period when the
   validity of the certificate expires.
                                                       39
Section 102
Establishes the Register of Certificates
1) The Director-General shall maintain a register of
   certificates issued in terms of section one hundred, in
   which he shall record, in relation to each certificate:
the project in respect of which the certificate was
 issued; and
the developer to whom the certificate was issued; and
the certificate’s dates of issue and expiry; and
any conditions subject to which the certificate was
 issued;
any amendment, suspension or cancellation of the
 certificate; and
such other particulars as may be prescribed.
                                                   40
2) The register kept in terms of subsection (1) shall
   be open to inspection by members of the public at
   all reasonable times at the Director-General’s
   office, on payment of the prescribed fee, if any.
                                                            41
Transfer of certificate under Sec 103
• A developer to whom a certificate has been issued
  shall not assign, cede or otherwise transfer the
  certificate to any other person without the prior
  approval of the DG:
• Provided that if a developer to whom a certificate has been
  issued dies or, in the case of a company, is placed in
  liquidation, the certificate shall be deemed to have been
  transferred to the executor of the developer’s estate or the
  developer’s liquidator, as the case may be, and the DG’s
  approval shall not be required for any such transfer
                                                        42
Amendment of certificates Section 104
1) If, while a project is being implemented, the DG is
   satisfied, on the basis of new evidence or any
   report by the developer, that the project is likely to
   be a source of pollution or otherwise to pose a
   threat to the environment, the DG may:
cancel the certificate and order the preparation of a
 new EIA report; or
amend the certificate or any conditions subject to
 which it was issued; or
give such directions as considered necessary to
 prevent or minimise the pollution or threat to the
 environment, including;
                                                    43
a. the methods of execution and planning of the
   project;
b. works or actions required to eliminate, reduce or
   mitigate the adverse effects of the project on the
   environment;
c. research and monitoring programmes related to
   the project;
d. periodic reports on the environmental impact of
   the project.
                                                      44
2) The DG may also suspend or cancel any
   certificate if he is satisfied that the developer:
a. obtained the certificate on the basis of fraud or
   negligent misrepresentation or any false or
   misleading statement; or
b. has failed to comply with any condition imposed
   on the issue of the certificate; or
c. has contravened other relevant sections
                                                      45
Section 105
• Demands that developer informs DG if project not
  implemented or changed
• Every developer to whom a certificate has been issued
  shall inform the DG without delay:
if it becomes apparent that he will not be able to
  implement the project before the certificate’s period of
  validity expires; or
if there is any change in the project which is likely
  materially to alter the project’s effect on the
  environment; or
if it appears that the project may have an effect on the
  environment that differs materially, in kind or degree,
  from the effect outlined in the environmental impact
  assessment report prepared for the project
                                                    46
Section 106 0n Environmental Audits
1) DG, in consultation with such authorities as he
   considers appropriate, shall carry out or cause to
   be carried out periodic environmental audits of
   any projects, including projects whose
   implementation started before the fixed date, for
   the purpose of ensuring that the their
   implementation complies with the requirements
   of this Act.
2) For the purposes of subsection (1), a developer
   shall keep such records and submit such reports
   to the DG as specified.
                                                    47
Section 107
Under Sec 107 developers are called upon to be
 good environmental stewards
1) Every developer shall take all reasonable
   measures to prevent or, if prevention is not
   practicable, to mitigate any undesirable effect on
   the environment that may arise from the
   implementation of his project.
2) A developer shall report to the DG without delay
   any measures taken in terms of subsection (1),
   unless the measures have already been described
   in an EIA report or reported in terms of section
   105 considered earlier.
                                                       48
Section 108
Demands that EIA reports be inspected – during
  implementation
• An EIA report shall be open for public inspection at
  all reasonable times at the DG’s office, on the
  payment of a prescribed fee, if any:
• Provided that no person shall use any information
  contained therein for personal benefit except for
  purposes of civil proceedings brought under this
  Act or under any other law in a matter relating to
  the protection and management of the
  environment
                                                      49
Monitoring Environmental Impacts
• Monitoring is also required to assess whether the
  predicted impacts materialise, and what their
  severity could be.
• The feedback from monitoring allows for
  modifications in the activity and/ or appropriate
  mitigation.
• Monitoring should be properly focused to:
Check for the occurrence of the most important
  predicted environmental impacts
                                                50
Check whether the mitigation measures are
 effective; and
Provide early warning about unexpected
 environmental impacts.
It is, thus, vital to have an efficient decision-
 making mechanism to implement corrective steps.
                                                         51
Preparation of terms of reference (TOR)
• ToR sets out what is expected of a practitioner or a
  consultant when carrying out an EIA.
• Usually drafted during the scoping phase
• ToR are set of specific guidelines applicable to a
  single development project at a particular site.
• ToR include important environmental variables which
  need detailed study, the degree of detail, the scope of
  the study, budgeting, etc.
• There are no universal formats for terms of reference,
  which will be suitable for every study. However, there
  are general rules, which should be observed when
  preparing ToR for the EIA.
                                                   52
Suggested format of TOR
1. Introduction - Identification of the project to be
   assessed and explanation of the executing
   arrangements for conducting the Environmental
   Impact Assessment.
2. Background Information - A description of the
   major components of the proposed project, the
   implementing agents, and a brief history of the
   project and its current status.
3. Study Area - Specification of the boundaries of
   the study area for assessment as well as any
   adjacent or remote areas, which should be
   considered with respect to the project.
                                                      53
4. Scope of Work - Standard environmental impact
    assessment techniques will be used including site
    reconnaissance, literature review, desktop research,
    field work, data analysis and interviews with
    appropriate personnel, in order to satisfy the Terms
    of Reference
• The following tasks will be performed:
Task 1: Description of the Proposed Project:
• A full description of the project and its existing
  setting, using maps as appropriate.
• This is to include general layout, size, location,
  physical characteristics, biological environment and
  socio-cultural setting.
Task 2: Description of the Environment.
• Assemble, evaluate and present data on the relevant
  characteristics of the study area.
• Information will include the following:
                                                       54
Terrestrial Environment
Physical environment: geology, topography, soils
 Natural drainage features: surface drainage, flood
 risk
Air quality: particulates and noise levels
Biological environment: forest/vegetation cover,
 existing wildlife (flora and fauna), rare or endangered
 species, sensitive habitats, species of commercial
 importance, migratory path of birds, nuisance
 species, pests and vectors
Socio-cultural environment: land use, traffic patterns,
 proposed developments, public health issues,
 demographics, employment and solid waste
 management.
                                                           55
Task 3: Legislative and Regulatory Considerations.
• A description will be given of the pertinent regulations,
  standards and regulatory bodies governing environmental
  quality, health and safety, protection of endangered species,
  parks and protected areas, and land use control.
Task 4: Determination of Potential Impacts of the Proposed
  Project.
• Impacts will be determined as significant positive or
  negative, direct or indirect, short-term or long-term,
  unavoidable or irreversible.
• Cumulative of the proposed development will also be
  highlighted.
• Special emphasis will be placed on:
 Land use management
 Terrestrial ecology
Visual Resource
 Energy Transmission
 Air quality o Noise
                                                      56
Task 5: Mitigation and Management of Negative
  Impacts.
• Recommendations will be made for feasible and
  cost-effective measures to prevent or reduce
  significant negative impacts to acceptable levels.
Task 6: Recommendations for the development of
  an Emergency Response Management Plan.
• Recommendations will be made for the
  development of an Emergency Response Plan to
  ensure that procedures are in place to handle any
  emergency.
                                                    57
Task 7: Recommendations for the development of a
  Monitoring Plan.
• Recommendations will be made for the
  development of a Monitoring Plan to ensure
  implementation of the mitigation measures and
  long-term minimization of negative environmental
  impacts.
Task 8: Assist in Inter-Agency Coordination and Public
 Participation. As, required by Law to assist in the
 public participation/review process through
 meetings with relevant governmental agencies, in
 obtaining the views of civil society and participating
 in a public consultation if required
                                                         58
5. Report - the Environmental Impact Assessment report
   will be concise and limited to the significant
   environmental issues.
• The main text will focus on findings, conclusions and
   recommended actions, supported by summaries of the
   data collected and citations for any references used in
   interpreting those data.
• The report will be organized according to, but not
   necessarily be limited by, the outline below:
     Executive Summary
     Description of the Proposed Project
     Policy, Legal and Administrative Framework
     Description of the Environment
     Significant Environmental Impacts and Proposed
      Mitigation Measures o
     Analysis of Alternative
     Recommendations for Monitoring Plan
     List of References
     Photographs, Maps and Plans as appropriate
                                                    59
 EIA study/compilation plan/proposal
• Printing or reproduction of the full EIA report:
  provision of the budget for the reproduction of the
  EIA report as well as the number of copies required
  should be indicated; and
• Study team: expertise and specialists needed for
  the proposed project study team should be
  described.
• The need of foreign expertise, if necessary, should
  be indicated.
                                                        60
Time constraints
 EIA report: the time required for the EIA report to
  be completed, eg., within 3-12 months;
 EIA study proposal: the deadline for the EIA
  proposal to be submitted should be stated.
Budget
 Consultants to tender their budget
Other relevant information
                                                     61
General contents of TOR
The ToR should commence with a brief description
 of the program or project. This should include a plan
 of the area that will be affected either indirectly or
 directly.
The study should ensure that the consultants or
 practitioners focus on the major issues and the most
 serious likely impacts identified during scoping e.g.
 air emission, waste water discharge etc.
The opportunities for enhancing any positive benefits
 from the project should also be highlighted. This
 component of ToR is usually submitted to designated
 authority for scrutiny and approval.
                                                        62
The ToR should contain explicit references to which
 safeguard policies may be relevant and which legal
 requirements should be applied.
The ToR should give an indication of the team
 considered necessary for the study and a team
 leader identified.
Depending on the scope of the study this may be
 multi- disciplinary. However, as the team should not
 be rigidly imposed on the consultant.
If international experts are doing the EIA, it is
 important to make provision for local capacity
 building in the ToR.
Apart from enabling in-country expertise to be built
 up, this will promote more involvement and
 understanding of the issues raised by the study.
                                                         63
As most EIA studies are of relatively short duration,
 this is probably best achieved through the
 attachment of project proponent to the consultants
 during the study or an insistence on the use of local
 staff personnel for some of the tasks.
The expected date of commencement and time
 limit should be given and consultants program of
 work must be within the given time limit.
The budget limit should be given in the ToR. The
 type of experts, and whether foreign or local, and
 the duration of their inputs will usually be the
 deciding cost factors although a large field survey
 or measurement program with laboratory analysis
 could significantly increase costs.
                                                    64
Any assistance to be provided by the Client to reduce
 costs should be clearly stated in the ToR.
Consultant payments proposal should be made and
 tied to specific milestones e.g. the consultant will be
 paid 20% of their fee upon receipt of draft report by
 client etc.
Reporting requirements should be clearly stated and
 should comply with local or international reporting
 guidelines.
The format of EIS must be clear and the number of
 copies in soft and hard must be stated.
ToR should make provision for the consultants to
 improve the terms of reference in order to improve the
 quality of EIA.
                                                   65
ENVIRONMENTAL IMPACT
ASSESSMENT (EIA) PROCESS
• The first phase of an environmental assessment
  is called an Initial Environmental Examination
  (IEE) and the second is Environmental Impact
  Studies (EIS) or simply detailed EIA.
                                                            66
Initial Environmental Examination (IEE)
• IEE is carried out to determine whether potentially
  adverse environmental effects are significant or
  whether mitigation measures can be adopted to
  reduce or eliminate these adverse effects.
• The IEE contains a brief statement of key
  environmental issues, based on readily available
  information, and is used in the early (pre-feasibility)
  phase of project planning.
• The IEE also suggests whether in-depth studies are
  needed.
67
                                                   68
Environmental Impact Assessment (EIA)
            Screening (EIA or No EIA needed)
             Scoping (+ public participation)
              Impact analysis, mitigation &
                  management plan
           Draft Environmental Impact Report
          Report review (regulatory body and the
                          public)
            Decision (accept, reject or amend)
           Final Environmental Impact Report
          Implementation and decommissioning
                                                     69
Screening phase
• EIA process kicks off with project screening.
• Screening is done to determine whether or not a
  proposal should be subject to EIA and, if so, at what
  level of detail.
• Guidelines for whether or not an EIA is required are
  country specific depending on the laws or norms in
  operation.
• Legislation often specifies the criteria for screening
  and full EIA.
• Development banks also screen projects presented
  for financing to decide whether an EIA is required
  using their set criteria.
                                                      70
• The output of the screening process is often a
  document called an Initial Environmental
  Examination or Evaluation (IEE)
• The main conclusion will be a classification of
  the project according to its likely environmental
  sensitivity.
• This will determine whether an EIA is needed and
  if so, to what detail.
                                                     71
Scoping phase
• The aim of EIA is not to carry out exhaustive studies
  on all environmental impacts for all projects.
• Scoping is used to identify the key issues of
  concern at an early stage in the planning process
• The results of scoping will determine the scope,
  depth and terms of reference to be addressed
  within the Environmental statement.
                                                       72
Objectives of Scoping
• Scoping is done for the following purposes;
Identify concerns and issues for consideration in an EIA
Ensure a relevant EIA
Enable those responsible for an EIA study to properly
  brief the study team on the alternatives and on impacts
  to be considered at different levels of analysis
Determine the assessment methods to be used
Identify all affected interests
Provide an opportunity for public involvement in
  determining the factors to be assessed, and facilitate
  early agreement on contentious issues
Save time and money
Establish terms of reference (TOR) for EIA study
                                                     73
Environmental tools used in impact
prediction
• Choice of method is largely based on ease of
  method, cost and comprehensiveness of method.
• Several methods may be preferable to triangulate
  environmental impacts. 
                                                        74
1. Checklists
• Checklists are standard lists of the types of
  impacts associated with a particular type of
  project.
• Checklists methods are primarily for organizing
  information or ensuring that no potential impact is
  overlooked.
• They comprise list questions on features the
  project and environments impacts.
• They are generic in nature and are used as aids in
  assessment.
                                                      75
2. Modified Checklists
• A modified checklist is a result of collective
  brainstorming exercises to provide insight on the
  nature of likely impacts.
                                                                               76
ST=Short Term     LT=Long Term
R=Reversible    IR=Irreversible
L=Local      W =Wide
SI=Significant   N=Normal
                                  Nature of  impacts
Items                             Adverse                 Beneficiary
                                  ST    LT   R   IR    L  W ST LT         SI   N
Aquatic ecosystems                      X        X     XX                       
Fisheries                               X        X     X                        
Forests                                 X        X                              
Terrestrial wildlife                    X        X        X                     
Rare and endangered species             X        X        X                     
Surface water hydrology                 X                 X                     
Surface water quality                                                           
Groundwater                                            X                        
Soils                                                  X                        
Air quality                       X                           X       X         
Navigation                              X                                      X
Land transportation                                           X                X
Agriculture                                            X                        
Socioeconomic                          X                                       
Aesthetic                                                                       
                                                                            77
Checklists cont--
ISSUE                                                            YES   NO
1. Will the project result in displacement of people?
2. Will the project result in changes in lifestyle?
3. Will the project result in pollution?
4. Will the project result in excessive noise?
5. Will the project result in ground vibration?
6. Will the project result in offensive odour?
7. Will the project result in excessive electromagnetic waves?
8. Will the project result in greenhouse emissions?
9. Will the project result in hazardous wastes?
10. Will the project result in changes in groundwater quality?
                                                         78
2. Matrices
• Matrix methods identify interactions between
  various project actions and environmental
  parameters and components.
• They incorporate a list of project activities with a
  checklist of environmental components that might
  be affected by these activities.
• A matrix of potential interactions is produced by
  combining these two lists (placing one on the
  vertical axis and the other on the horizontal axis).
                                                     79
• They should preferably cover both the construction
  and the operation phases of the project, because
  sometimes, the former causes greater impacts
  than the latter.
• However, matrices also have their disadvantages:
  they do not explicitly represent spatial or temporal
  considerations,
• and they do not adequately address synergistic
  impacts.
                                                    80
3a. Decision focused or modified
matrix
• Modified matrix is valuable in comparing impacts
  of options to project operations.
• For each option or alternative, importance values
  for project activities are assigned to environmental
  caring.
• The entries in the matrix display the impact on each
  factor.
                                                            81
Assessment of Appropriate Energy Sources (After
Price Water House, 1993)
0 = No negative qualities; 2=Moderate 4= severe
  impacts
3= major Cost
Energy   negativeAesthetic
                  factors Availability Environment Totals
 Source
 Gas         2          1          2         0          5
 Wood        1          1          0         2          4
 Paraffin    2          1          1         1          5
 Solar       3          0          3         0          6
 Coal        2          2          2         1          7
 Generator   3          2          1         1          7
 ZESA        3          2          3         0          8
                                                      82
3b. Interaction matrix
• Also known as the Leopold's matrix, enlists
  environmental variables most affected by project
  activities on the vertical axis and rating of impacts
  on the horizontal axis.
• The ratings applied to each environmental variable
  may be numbers percentages, letters, or physical
  chemical, biological, culture and socio-economic
  categories.
                                                                                                                83
    E.G Matrix of environmental impacts associated with
    diamond prospecting activities in Gonarezhou National
    Park                                                
Environmental characteristic                                        Prospecting Activities
                               Aerial survey   Ground Survey and Exploration Drilling
                                               Camping              Vehicle access       Survey of Bore
                                                                                         samples samples
                                 S       E       S         E          S          E          S     E   S     E
Physical Environment                                                                                       
Landscape                                                            1         1         1      1          
Soil erosion                                   1           1                                               
Surface water                                                                                              
Ground water                                                                                        2     1
Water pollution                                   1        1                                               
Air pollution                                     1        1                                               
Noise pollution                1        1         1        1        1          1         1      1   1     1
Fire                                               2       2        0          0         2      2   2     2
Palaeoenvironment                             0         0          0          0         0      0   2     1
Biological Environment                                                                                     
Habitants                      0        0      2         1          2          1         2      1   2     1
Plant communities              0        0      1         1          1          1         1      1   1     1
Animal communities             1        1      1         1          1          1         1      1   1     1
Productivity                   0        0      1         1          1          1         1      1   1     1
Ecological process             0        0                           1          1         1      1   1     1
Socioeconomic environment                     1         1          1          1         1      1   1     1
Park visitors                  1        1                                                                  
                                                      84
4. Networks/ Impact trees
• These are cause effect flow diagrams used to help in
  tracing the web relationships that exist between
  different activities associated with action and
  environmental system with which they interact.
• They are also important in identifying direct and
  cumulative impacts. They are more complex and need
  expertise for their effective use.
• Relies on cause – effect relationship based on the fact
  that Environmental features are generally
  interconnected and show through web-interconnected
  features.
• 
                                                                     85
                Loss of
                Agricultural
                land             Reduced
                                 Agricultural
                                 income and
                                 employment
               Construction
Expansion of   of new
settlement     houses
                                 Improved living
                                 conditions
                                                   Increased waste
                                                   production
                                 Immigration
               New industries                      Traffic
               and Services
                                Employmen t
                                                   Pollution
                                                    86
Consultations
• Usually done with decision-makers, affected
  communities, environmental interest groups to
  ensure that all potential impacts are detected.
• However there can be danger in this when
  excessive consultation is done and some
  unjustifiable impacts included in the ToR
                                                        87
5. Baseline data collection
• The term "baseline" refers to the collection of
  background information on the biophysical, social
  and economic settings proposed project area.
• Normally, information is obtained from secondary
  sources, or the acquisition of new information
  through field samplings, interviews, surveys and
  consultations with the public.
• The task of collecting baseline data starts right from
  the period of project inception; however, a majority of
  this task may be undertaken during scoping and
  actual EIA.
                                                      88
Purpose of baseline data
Baseline data is collected for two main purposes;
1. To provide a description of the current status and
   trends of environmental factors (e.g., air pollutant
   concentrations) of the host area against which
   predicted changes can be compared and
   evaluated in terms of significance, and
2. To provide a means of detecting actual change by
   monitoring once a project has been initiated
NB. Only baseline data needed to assist prediction of
   the impacts contained in the ToR and scoping
   report should be collected.
                                                      89
Use of GIS technology
• In this simplest form, overlay mapping is a series
  of single factor maps, such as geology, hazards,
  solid, vegetation, farm, cultural sites and landmarks.
• Overlays of these maps on the site of the proposed
  action may identify which of the factors that have
  been mapped will be affected.
• The maps and the information they portray should
  also provide some dimension on the significance
  of the impact.
                                                     90
Public participation in EIA
Participation’ is defined as 'a process by which
 stakeholders influence decisions which affect them’
There is growing consensus that public
 participation is essential for effective and
 sustainable environmental management.
Putting emphasis on public participation also
 improves the predictive quality of the EIA
Essentially, the public should be involved from the
 preliminary assessment stages and be maintained
 throughout the EIA process and the project life cycle
                                                      91
Origins of public participation
Principle 10 of Rio, for example, stipulates that:
• Environmental issues are best handled with the
  participation of all concerned citizens, at the
  relevant level.
• At the national level, each individual shall have
  appropriate access to information concerning the
  environment that is held by public authorities,
  including information on hazardous materials and
  activities in their communities,
• and the opportunity to participate in decision-
  making processes.
                                                   92
• States shall facilitate and encourage public
  awareness and participation by making information
  widely available.
• Effective access to judicial and administrative
  proceedings, including redress and remedy, shall be
  provided (UN 1992).
                                                          93
In addition, principle 20 cements the call to involve
  women.
• The principle states that ‘Women have a vital role in
  environmental management and development. Their
  full participation is therefore essential to achieve
  sustainable development’.
• Public participation comes virtually in every stage
  during the EIA process or should one say at every stage
  where a decision has to be made about the proposed
  development.
• However, for clarity, the following are the key stages in
  which the public must be engaged without compromise:
  the scoping phase, impact identification and mitigation,
  and during draft EIA statement review.
                                                       94
Importance of public participation
1. A project creates change which may either be
   positive and negative which may be disconcerting to
   people and when people are informed there suffer
   less anxiety.
2. When people are informed ,they can pursue
   opportunities associated with the project, such as
   employment.
3. Creates a sense of ownership to the community
4. Stakeholders have a wealth of information about
   local conditions which is valuable to those carrying
   out EIA
5. People expect to be consulted about projects that
   could affect their way of life, failure to do so could
   result in delays, failure to achieve intended goals.
                                                        95
Stakeholders defined
Howlett and Nagu (1997) define stakeholders as ‘all
 those people and institutions who have an interest in the
 successful design, implementation and sustainability of
 the project.
This includes those positively and negatively affected by
 the project.
Stakeholder participation involves processes whereby
 all those with a stake in the outcome of a project can
 actively participate in decisions on planning and
 management.
They share information and knowledge, and may
 contribute to the project, so as to enhance the success
 of the project and hence ultimately their own interests
                                                         96
Examples of Key Stakeholder Groups in
a Typical EIA
 Organisations
 Co-ordination: Planning commissions and
   departments; government agencies at national,
   regional, district and village level; EMA,
Advisory: Research institutes, universities, colleges;
Regulatory: Government authorities at national,
   regional, district and village level;
Implementation: Relevant ministries/departments at
   national, regional and district levels, training
   organisations, private companies, NGOs;
Funding: Development assistance agencies, banks ,
   entrepreneurs, taxpayers; and
Conservation: Environment departments, museums,
   zoos, botanical gardens.
97
                                                      98
Public and community stakeholder
groups
Political: Members of Parliament (MPs), local
 councillors, party functionaries, lobbying groups;
 Cultural: Community and religious leaders,
 community service groups, community
 organisations/NGOs, traditional leaders;
 Business: Business leaders, Chambers of
 Commerce, trade unions, resource owners and
 those with tenure rights, common property
 resource users; and
 Environment: Community interest groups,
 international and local environmental NGOs, local
 experts.
                                                               99
 Participation typologies
There are a number of ways in which the public can be
 involved in the EIA process and these include the following:
1. Passive participation -Consultant or extension worker
   appears in village and tells villagers that an irrigation
   scheme will be constructed to ‘improve’ crop yields.
2. Participation in information giving -Consultant or
   extension worker appears in village and asks for
   information about their crops, and about seasonal water
   flows. Records their answers and leaves, this is usually
   done through public meetings
                                                      100
3. Participation by consultation -Consultant or
   extension worker explains that crop yields need
   to be improved, and that the government intends
   to build an irrigation scheme.
• The developer seeks the views and responses of
  villagers (for example, how they feel it might
  increase soil erosion), and then leave, this is usually
  done through community workshops and
  interviews this can be done through newspapers
  and media.
                                                      101
4. Functional participation - Consultants or extension
   workers inform villagers that they intend to
   construct an irrigation project.
•   The consultants then facilitate the development
    of a village committee to discuss particular
    aspects of the project (such as minimising soil
    erosion, downstream impacts on fisheries; or to
    agree on arrangement for water management).
                                                    102
5. Interactive participation
• Local villagers identify their own needs, and
   external facilitators work with them to assist in
   finding solutions to potential negative impacts -
   and improving positive effects
•   In some cases, new institutions will develop at the
    local level, which might then play a role in the
    management of their own project and its impacts.
    Villagers then have a real stake in maintaining
    structures or practices.
                                                    103
6. Self-Mobilization- Villagers plan and identify their
   own irrigation structures, perhaps learning from
   experience in a nearby village.
• They may develop contacts with external
   institutions for resources and technical advice
   they need, but retain control over how resources
   are used
                                                   104
Constraints to full public participation
• Stakeholder involvement in EIA can be constrained
  by many factors which may vary according to
  circumstance and context. These include the
  following:
1. Time and money (Financial Resources to
   participate)
• Participation may be constrained by the financial
  situation of local people, because participation
  requires time away from other tasks and may
  involvement cash for transportation and subsistence
  while away from home.
• In many cases, incentives or compensation will be
required to secure their inputs.
                                                   105
2. Language and literacy
• Care must be taken to ensure that local people can
  use a with which they can best represent their
  interests, express their ideas, and convey
  knowledge.
• Shortage of key material in local language is
  another constraint at grass root level.
3. Culture
• Cultural norms may limit the participation of some
  groups, such as women in the participatory
  process established for the environmental impact
  assessment
                                                      106
4. Education
• Low levels of education, and the ‘technical’ nature of
  many development-related issues, can be a major
  barrier to effective participation in EIA.
• For example, a villager in Bangladesh, when asked
  whether he had ‘participated’ in the EIA process for a
  major flood control and irrigation project that would
  radically alter his livelihood prospects, responded
  thus
“If I were to be consulted what would I say? You see
  I'm just an ordinary man. I don't know anything. All I
  know is that
one has to have meals every day'. (cited in Adnan et al,
  1992)
                                                          107
5. Gender
• Insensitivity to gender issues, and particularly to the
  lower status accorded to women in decision-making in
  many parts of the world, is a common constraint to
  effective stakeholder involvement.
 6. Mistrust and elitism
• Mistrust often pervades the relationships between
  project proponents and different stakeholders
 7. Physical remoteness (Rural Settings)
• It is costly and time consuming for practitioners to
   reach small, diverse and scattered groups in remote
   areas, and conversely, it is difficult for the inhabitants
  of such areas to gain access to information relevant to
  development plans and to EIA.
                                                     108
8. Existing legal systems
• Conflicting traditional and modern legal systems i.e
  rights and responsibilities for local resources
  potentially can affect the participatory process.
9. Diversity of Opinion
• Communities are comprised of people with
  different perceptions , values, and objectives and all
  these should be equally represented
                                                            109
Outcomes of Public participation
• Public participation play a pivotal role in EIA
• Provides information on natural resources in the
  area
• Outlines the community goals and aspirations in
  relation to the proposed development
• Contribute to social, cultural, and economic
  evaluation of the project
• Provides vital information that helps in decision
  making process
• Assist in all the stages of a project life cycle ( i.e.
  Planning, implementation, management and the
  monitoring )
                                                          110
Outcomes cont---
• Offers all the stakeholders a sense of commitment
  and ownership of the proposal,
• It allows for views and values which otherwise may
  have not been considered to be brought to bear on
  the proposal,
• It ensures that the final proposal is the optimal one,
  representing the best compromise of all conflicting
  interests
                                                     111
 3.IMPACT Analysis, Prediction and
 Management Phase
• Predicting the magnitude of a development likely
  impacts and evaluating their significance is core
  of environmental assessment process
• Prediction should be based on the available
  environmental baseline of the project area. Such
  predictions are described in quantitative or
  qualitative terms.
                                                       112
 Considerations in impact prediction
a. Magnitude of Impact
• This is defined by the severity of each potential
   impact and indicates whether the impact is
   irreversible or, reversible and estimated potential rate
   of recovery.
• The magnitude of an impact cannot be considered
   high if a major adverse impact can be mitigated.
                                                    113
2. Extent of Impact
• The spatial extent or the zone of influence of the
   impact should always be determined.
• An impact can be site-specific or limited to the
   project area; a locally occurring impact within the
   locality of the proposed project; a regional impact
   that may extend beyond the local area and
• a national impact affecting resources on a
   national scale and sometimes trans-boundary
   impacts, which might be international.
                                                 114
3. Duration of Impact
• Environmental impacts have a temporal
   dimension and needs to be considered in an EIA.
• Impacts arising at different phases of the
   project cycle may need to be considered.
• An impact that generally lasts for only three to
   nine years after project completion may be
   classified as short-term.
• An impact, which continues for 10 to 20 years,
   may be defined as medium-term, and impacts
   that last beyond 20 years are considered as
   long-term.
                                                      115
4. Significance of the Impact
• This refers to the value or amount of the impact.
• Once an impact has been predicted, its
   significance must be evaluated using an
   appropriate choice of criteria.
• The most important forms of criterion are:
Specific legal requirements e.g. national laws,
 standards, international agreements and
 conventions, relevant policies etc.
Public views and complaints
Threat to sensitive ecosystems and resources e.g.
 can lead to extinction of species and depletion of
 resources, which can result, into conflicts.
Geographical extent of the impact e.g. has trans-
 boundary implications.
                                                   116
Cost of mitigation
Duration (time period over which they will occur)
Likelihood or probability of occurrence (very likely,
 unlikely, etc.)
Reversibility of impact (natural recovery or aided by
 human intervention)
Number (and characteristics) of people likely to be
 affected and their locations
Cumulative impacts e.g. adding more impacts to
 existing ones.
Uncertainty in prediction due to lack of accurate
 data or complex systems. Precautionary principle
 is advocated in this scenario.
                                                            117
Impact prediction methodologies
• Several techniques can be used in predicting the impacts.
• The choices should be appropriate to the circumstances.
  These can be based on;
 a. Professional judgment with adequate reasoning and
    supporting data. This technique requires high professional
    experience.
 b. Experiments or tests. These can be expensive
 c. Past experience
 d. Numerical calculations & mathematical models. These
    can require a lot of data and competency in mathematical
    modelling without which hidden errors can arise
 e. Physical or visual analysis. Detailed description is needed
    to present the impact.
 f. Geographical information systems,
 g. Risk assessment, and
 h. Economic valuation of environmental impacts
                                                          118
Analysis of alternatives
• Analysis of alternative is done to establish the preferred
  or most environmentally sound, financially feasible and
  benign option for achieving project objectives
• Requires systematic comparison of proposed
  investment design in terms of site, technology,
  processes etc in terms of their impacts and feasibility of
  their mitigation, capital, recurrent costs, suitability under
  local conditions and institutional, training and monitoring
  requirements .
• For each alternative, the environmental cost should be
  quantified to the extent possible and economic values
  attached where feasible, and the basic for selected
  alternative stated. The analysis of alternative should
  include a NO PROJECT alternative.
                                                   119
Mitigation and impact management
• Mitigation is done to avoid, minimize or offset
  predicted adverse impacts and, where appropriate,
  to incorporate these into an environmental
  management plan or system.
• For each potential adverse impact the plan for its
  mitigation at each stage of the project should be
  documented and costed, as this is very important in
  the selection of the preferred alternative.
                                                 120
Objectives of mitigation
To;
• find better alternatives and ways of doing things;
• enhance the environmental and social benefits of a
  project
• avoid, minimise or remedy adverse impacts; and
• ensure that residual adverse impacts are kept
  within acceptable levels
                                                                                121
    Design of mitigation measures
Approach     Examples
Avoid        Change of route or site details, to avoid important ecological or
             archaeological features
Replace      Regenerate similar habitat of equivalent ecological value in
             different location.
Reduce       Filters, precipitators, noise barriers, dust, enclosures, visual
             screening, wildlife corridors, and changed time of activities
Restore      Site restoration after construction
Compensate   Relocation of displaced communities, facilities for the affected
             communities, financial compensation for the affected individuals
             etc
                                                  122
Environmental Management Plan (EMP)
• An Environmental Management Plan (EMP) is a
  detailed plan and schedule of measures necessary to
  minimize, mitigate, etc. any potential environmental
  impacts identified by the EIA
• Once the EIA has identified the significant impacts it
  is necessary to prepare an Environmental
  Management Plan.
• An EMP should consist of a set of mitigation,
  monitoring and institutional measures to be taken
  during the implementation and operation of the
  proposed project to eliminate adverse environmental
  impacts, offset them or reduce them to acceptable
  levels.
                                                    123
The EMP should also include the actions needed to
  implement these measures, including the following
  features:
• Mitigation based on the environmental impacts
  reported in the EIA, the EMP should describe with
  technical details each mitigation measure.
• The EMP should then include monitoring objectives
  that specifies the type of monitoring activities that
  will be linked to the mitigation measures.
                                                        124
Specifically, the monitoring section of the EMP
  provides:
• A specific description, and technical details, of
  monitoring measures that includes the parameters
  to be measured, the methods to be used, sampling
  locations, frequency of measurements, detection
  limits (where appropriate), and definition of
  thresholds that will signal the need for corrective
  actions
• Monitoring and reporting procedures to ensure early
  detection of conditions that necessitate particular
  mitigation measures and to furnish information on
  the progress and results of mitigation.
                                                    125
• The EMP should also provide a specific description
  of institutional arrangements i.e. who is responsible
  for carrying out the mitigating and monitoring
  measures (for operation, supervision, enforcement,
  monitoring of implementation, remedial action,
  financing, reporting, and staff training).
• Additionally, the EMP should include an estimate of
  the costs of the measures and activities
  recommended.
• It should consider compensatory measures if
  mitigation measures are not feasible or cost
  effective.
• EMP must be operative throughout the whole
  Project Cycle.
                                                   126
Environmental Monitoring
• Environmental monitoring is the systematic
  measurement of key environmental indicators
  over time within a particular geographic area
  (World Bank, 1999).
• Monitoring should focus on the most significant
  impacts identified in the EIA.
• Various types of monitoring activity are currently
  in practice.
                                                127
Types of Monitoring in an EIA
Baseline Monitoring
• A survey should be conducted on basic
  environmental parameters in the area surrounding
  the proposed project before construction begins.
• Subsequent monitoring can assess the changes in
  those parameters over time against the baseline
                                                   128
Impact Monitoring
• The biophysical and socio-economical (including
  public health) parameters within the project area,
  must be measured during the project
  construction and operational phases in order to
  detect environmental changes, which may have
  occurred as a result of project implementation e.
  g. air emission, dust, noise, water pollution etc
                                                    129
Compliance Monitoring
• This form of monitoring employs a periodic
  sampling method, or continuous recording of
  specific environmental quality indicators or
  pollution levels to ensure project compliance with
  recommended environmental protection standards.
• Monitoring should be regular and performed over a
  long period of duration. Interruptions in monitoring
  may result in generating insufficient data to draw
  accurate conclusion concerning project impact.
                                                   130
• The main aim of EIA monitoring is to provide the
  information required to ensure that project
  implementation has the least possible negative
  environmental impacts on the people and
  environment.
What to avoid in monitoring:
• Overestimation of data needed as this can lead to
  drowning in data without information.
• Under-estimation of time and cost for data analysis
• Weak coordination between the data collection with
  project time table and seasonal factors
• Ignoring requirements for baselines
                                                   131
Environmental Impact Statement (EIS)
• The final EIA report is referred to as an
  Environmental Impact Statement (EIS).
• Most national environmental laws have specified
  what the content of EIS should have. Multilateral
  and bilateral financial institutions have also defined
  what should be contained in an EIS.
                                                         132
Ideally, the content of an EIS should have the following:
• Executive Summary
• Policy, Legal and Administrative Framework
• Description of the environment
• Description of the Proposed Project in detail
• Significant Environmental Impacts
• Socio-economic analysis of Project Impacts
• Identification and Analysis of Alternatives
• Mitigation Action/Mitigation Management Plan
• Environmental Management Plan
• Monitoring Program
• Knowledge gaps
• Public Involvement
• List of References
• Appendices including
Reference documents, photographs, unpublished data
Terms of Reference
 Consulting team composition
Notes of Public Consultation sessions
                                                        133
Decision making
• The EIS is submitted to designate authority ( EMA)
  for scrutiny before the final decision.
• The authority, together with technical review panel
  determines the quality of EIS and gives the public
  further opportunity to comment.
• Based on the outcome of the review, the designated
  authority or lending institution will accept, reject or
  make further modifications to avoid future
  confrontation.
• If the EIS is accepted, an EIA license is issued and if
  otherwise, additional studies or recommendations
  are made before issuance of a license
                                                    134
EIA post Auditing
• The principal purpose of post-auditing is to
  provide feedback in EIA, and to provide the
  essential opportunity to learn from past
  experience and apply the lessons learned to
  future actions
• Post-auditing can highlight the types and
  categories of impacts that tend to be predicted
  less accurately than others .
• This should stimulate gradual improvements in,
  and requirements of, the techniques used to
  make such predictions
                                                    135
• over time, and again if properly used, post-auditing
  may lead to advances in accuracy, utility and
  predictive capability
• It can also provide baseline information for future
• Provides information about the effectiveness of
  mitigation measures and the overall success of
  environmental management and protection
• Post-auditing may also be used to identify and
  correct (or mitigate) unanticipated impacts
                              136
Compiled by Thembuluwo Moyo
• 2000@com0303zimemai
• 2018/19/06
137
138