PROJECT: RESIDENTIAL BUILDING
TASK START DATE DAYS TO COMPLETE
CLEARING THE LOT 10-Oct 2
FOOTINGS AND FOUNDATIONS 12-Oct 8 FOOTINGS
FRAMING 20-Oct 10
WINDOWS AND EXTERIOR DOORS 11-Nov 7
PLUMBING, MECHANICAL, AND ELECTRIC ROUGHS 17-Nov 12
SIDING, ROOFING, AND EXTERIOR TRIM 27-Nov 22 WINDOWS AN
INSULATION AND DRYWALL 2-Dec 3
CABINETS, TILE, AND GLASS 10-Dec 8 PLUMBING, MECHANICAL, AND
PAINTING, PAPER, AND FLOOR COVERINGS 18-Dec 9
HARDWARE, EQUIPMENT, AND FIXTURES 27-Dec 11 SIDING, ROOFING, A
FINISH PLUMBING, MECHANICAL, AND ELECTRIC 2-Jan 6
FINISH GRADING AND LANDSCAPING 10-Jan 10 INSULAT
CABINET
PAINTING, PAPER, AND
HARDWARE, EQUIPM
FINISH PLUMBING, MECHAN
FINISH GRADING
Gantt Chart
10-Oct 30-Oct 19-Nov 9-Dec 29-Dec 18-Jan 7-Feb
CLEARING THE LOT
FOOTINGS AND FOUNDATIONS
FRAMING
WINDOWS AND EXTERIOR DOORS
PLUMBING, MECHANICAL, AND ELECTRIC ROUGHS
SIDING, ROOFING, AND EXTERIOR TRIM
INSULATION AND DRYWALL
CABINETS, TILE, AND GLASS
PAINTING, PAPER, AND FLOOR COVERINGS
HARDWARE, EQUIPMENT, AND FIXTURES
FINISH PLUMBING, MECHANICAL, AND ELECTRIC
FINISH GRADING AND LANDSCAPING
18-Jan 7-Feb