DEPARTMENT OF CIVIL ENGINEERING
TRAINING REPORT
              CONTENTS
    INTRODUCTION
    ABOUT PROJECT
    TECHNICAL REPORT
    SITE PLAN AND PLALLING OF BUILDING
    BUILDING MATERIAL
    REINFORCEMENT CEMENT CONCRETE AND
     DESIGN PHILOSAPY
    EFFECTS OF THE AGGREGATES PROPERTIES
     ON THE CONCRETE
    ADMIXTURES
    FROM WORK
    GENERAL NOTES
    INDEX
                                       INTRODUCTIO
                                                 N
The building is defined as any structure what so ever
purpose and of whatsoever materials constructed and ever
part thereof whether used as human habitation or not. For
this practical training.
                             I reported at Ansal palam vihar
Gurgoan at Construction of defence services officers
institute at Ansal palam vihar Gurgoan in response to Mr.
S. L. Baluja (General Manager) dated 12.05.2005. In
connection with same, I have reported to Mr. A. K.
Nijhawan (General Manager) at Ansal palam vihar
Gurgoan furthers ordered me to join project site. The site
incharge Mr. Jitendra Singh meet me at the site and gives
me brief introduction of this project as under.
                              2
          The project on which I take practical training this
  project is a construction of a CLUB for the DEFENSE
  SERVISES OFFICERS.
  This project has the following features:
Location                  : Ansal palm vihar gurgoan
Client                    : Ansal Group, Delhi
Construction Company : Ahaluwaliya construction co.
Structural consultant     : Pioneer Engg. Consultant
Cost of the Project       : 14.5 carore rupees
The building is fully air-conditioned. It have fire detection
system and fire fighting system and escape way in the
carious condition. This building is earth quack resistance. It
has both lifts car lift and man lift. This building have fully
power backup.
                              3
                             TECHNICAL REPORT
1. GENERAL
   1.1 Name of work                  Construction of defence
                                     servises officers institute
     1.2     Name of zone            Palam tringle, Ansal palam
                                     vihar, gurgoan
     1.3     Name of division        Gurgoan division
2. LOCATION OF THE LAND
   2.1 Location       Palam tringle, near at BSNL
                      Teliphone exchange, Ansal
                      palam vihar, Gurgoan
     2.2     Possession taken over/             Taken over
             not taken over
3.    REFERENCE OF APPROVED DRAWINGS
     s.no.    Detail            Drawing
      1.      Site plan        --    Approved by the project
      2.      Plans                   incharge shri Jitendra
      3.      Section                 singh & chief architect
      4.      Elevation
      5.      detail of compound wall
      6.      Sanitary / Water Supply &
              Drawing System
      7.       Electrification
      8.      Other Drawing
                                 4
4.     BRIEF SPECIFICATION                 As recieved from
                                           chief Architect
  4.1      Foundation concrete: Design mix concrete M-25
  4.2      Foundation:              R.C.C. Raft foundation
                                     having slab thickness
                                     700 mm
  4.3       Wall:               (a) Basement outer wall of
                                    R.C.C. Retaining type
                                    in cement concrete M-25
                                (b) Ground floor & first floor
                                    other wall of R.C.C. in
                                    cement concrete M-25 &
                                    Brick masonry in cement
                                    mortar 1:6 230 mm
                                    thick with bricks of class
                                    designation 100
 4.4      Structure                  The complete structure is
                                    of RCC frame structure in
                                    M-25 concrete.
4.5       Interior finish/exterior Shown in detailed in
          finish/flooring/joinery/ index
         white wash, cement
         paint & painting
 4.5    Sanitary & water
supply fitting                    (a) Conclealed G.I. fitting in
                                      side building with brass
                              5
                                      fitting.
                                (b) Out side fitting are of
                                      open type.
 4.6    Other specifications (a) Expansion &Contraction
                                     joint are provided.
                               (b) bitumen treatment are
                                     provided at the roof.
                               (c) Plasticizer used: cico
                                      plasticizer tape Crete P-
                                      151 polymer mix in the
                                    concrete at the rate of 1%
                                   of weight of cement used.
5. ESTIMATE COST                The estimate cost of above
                                building comes to Rs. 14.5
                                crores of double basement
                               & three floor.
6. PLINTH AREA RATE             Rs. 2100 per Sq. Ft.
7. CONPONY FOR CONSTRUCTION
Aluwaliya contrctors (india) ltd
                               6
     SITE PLAN AND PLANNING OF THE
                          BUILDING
The planning of the building has the most important role
in the civil engineering because well designed building
has the comfort and good working conditions for the
people who live and work in it.
             The project on which I take training it is a
construction of club for the defense officers. This
building is designed very carefully by keeping the
following views:
 1: Gymnasium
 2: Indoor Games
 3: Swimming Pool
 4: Car Parking
 5: CSD Canteen
 6: Shopping Complex
 7: Beauty parlour
 8: Cyber cafe
  and many of the facility for the defense officers.
This building is situated in the ansal palm vihar gurgoan.
There are the environmental condition is sun shiny and
hot arid zone, good rain fall, good neighboring
conditions. The facing of the building is south.
                           7
                           BUILDING MATERIAL
A building structure is composed of different types of the
material these materials are either called as building
material. The material use in the building on basis of the
avaibility and cost. For construct a building the essential
building material are as follow:
Cement
The cement often called the magic power is a fine
ground material consisting of compound of lime ,silica
alumina and iron. When mixed with water it forms a
paste which hardened and bind the aggregates (sand,
gravel, crushed rock, etc) together to form a durable
mass called the Concrete. Cement is the binder that
holds concrete and mortars together. Which is why it
play the most critical role in giving strength and
durability to your building. Cement uses for domestic
building such as home are basically of three types.
  Portland Slag Cement:      Portland slag cement
   (PSC) conforming to IS: 455 A combination of
   good quality blast furnace slag (from the iron steel
   industry) with clinker (which makes the OPC) and
   gypsum.
                           8
Portland Pozzolana Cement:    Portland pozzolana
 cement (PCC) conforming to IS: 1489 A
 combination of flyash (from thermal power plant)
 with clinker and gypsum. pozzolana cement is
 prepared by grinding Portland cement clinker with
 pozzolana. This type of cement is largely used in
 marine structure.
Ordinary Portland Cement:        Ordinary Portland
 cement (OPC) 33 grade conforming to IS: 269, 43
 grade conforming to IS: 8112 and 53 grade
 conforming to IS: 12269 A combination of clinker
 and gypsum of good quality. Ordinary Portland
 cement is manufactured by first burning at a very
 high temperature the mixture of calcareous (mainly
 calcium carbonate) and argillaceous (mainly clay)
 and then grinding the calcined product (i.e. clinker)
 with small amount of gypsum in to a fine power
 known as ordinary Portland cement.
Good quality cement has the following features:
  •   Reduced water requirement
  •   Improve Workability
  •   Less permissible to moisture
  •   Improved resistance to acid and chlorides
  •   Reduced heat of hydration
  •   Easier to finish
  •   Reduced shrinkage
                         9
  • Reduced leaching problems because it is low as
    free lime
Manufacture Of Cement
  Ordinary Portland cement is manufactured by
  crushing, milling and proportioning the following
  materials:
     Lime or calcium oxide, CaO: form limestone,
      chalk, shell, shale or calcareous rock
     Silica, SiO2: from sand, old bottles, clay or
      argillaceous rock
     Alumina, AL2O3: from bauxite, recycled
      aluminum, clay
     Iron, FE2O3: from clay, iron ore, scrape iron
      and fly ash
     Gypsum, CaSO4.2H2O: found together with
      limestone
             The materials with out the gypsum are
    proportioned to produce a mixture with the
    desired chemical composition and then ground
    and blended by one of two processes – Dry
    process and Wet process .The materials are then
    fed through a kiln at 2600 F to produce grayish
    black pellets known as clinker. The alumina and
    iron act as fluxing agents, which lower the
                      10
      melting point of silica from 3000 to 2600 F. After
      this stage, the clinker is cooled, pulverized and
      gypsum added to regulate the setting time. It is
      then ground extremely fine to produce cement.
             The kiln resembles a large horizontal pipe
      with a diameter of 10 to 15 feet (3 to 4.1 meters)
      and a length of 300 feet (90 meter) or more. One
      end is raised slightly. The row mix is placed in
      the high end and as the kiln rotates the materials
      move slowly toward the lower end. For each
      tones of material that goes in to the feed end of
      the kiln, two thirds of a tone comes out the
      discharge end, called clinker. This clinker is in
      the form of marble sized pellets. The clinker is
      very finely ground to produce Portland cement. A
      small amount of gypsum added during the
      grinding process to control the cement’s or rate of
      hardening.
Flow Diagram For Cement Manufacturer
                         11
  (Wet process)
  Calcareous Material                               Argillaceous Material
  Water
  i.e., Lime stone                          i.e. Clay
  Crushing                                                   Washing
  ----------------------
        Silos                              Storage Tank
           |            Hooper                  |
                      Wet Grinding Mill
                  Formation of Slurry
                   Correction Tank
 Coal
                    Storage Tank
Crushing Mill              Pump
                      Rotary Tank
                      Linker Cooler                 Gypsum
                  Grinding in Ball Mills
                     And Tube Mills
                     Cement Silos
                   Weighing and Packing in Bags
                     Dispatch
                                    12
  Cement Shorthand
  Because of the complex chemical nature of cement, a
  shorthand from is use to denote the chemical
  compounds. The shorthand for the basic compound is:
Compound           Formula       Shorthand form
Calcium Oxide      CaO               C
(Lime)
Silicon Dioxide    SiO₂          S
(Silica)
Aluminum Dioxide   Al₂O₃         A
(Alumina)
Iron Oxide          Fe₂O₃        F
Water               H₂O          H
Sulfate              SiO₃        S
Chemical composition of the clinker
                            13
 The cement clinker formed has the following typical
composition:
Compound         Formula          Shorthand      % by
                                   form          weight
Tricalcium       Ca₃Al₂O₆         C₃A            10
Aluminate
Tetracalcium Ca₄Al₂Fe₂O₁₀          C₄AF           8
aluminoferrite
Belite or dicalcium   Ca₂SiO₅      C₂S            20
Silicate
Alite or tricalcium   Ca₃SiO₄        CS               55
Silicate
Sodium Oxide          Na₂O           N                 )
Potassium Oxide       K₂O            K                 )Upto 2
Gypsum                 CaSO₄.2H₂O         CSH₂             5
These compounds contribute to the properties of cement in
different ways
                             14
Tricalcium aluminate, C₃A:-
It liberates a lot of heat during the early stages of hydration,
but has little strength contribution. Gypsum slows down the
hydration rate of CA. Cement low in CA is sulfate resistant.
Tricalcium silicate, C₃S: -
This compound hydrates and hardens rapidly. It is largely
responsible for Portland cement’s initial and early strength
gain.
Dicalcium Slicate, C₂S: -
CS hydrates and hardens slowly. It is largely responsible
for strength gain after one week.
Ferrite, C₄AF:
This is a fluxing agent, which reduces the melting
temperature of the row material in the kiln (from 3000 F to
2600 F). it hydrates rapidly, but does contribute much to
strength of the cement paste.
By mixing these compounds appropriately, manufacturers
can produce different types of cement to suites several
construction environments.
                               15
Sand
These are cohesion less aggregates of either, rounded sub
rounded, angular, sub angular or flat fragments of more or
less unaltered rock of minerals consisting of 90% of
particles of size greater than 0.06 mm and less than 2 mm.
Alternatively, these are coarse grained cohesion less
particles of silica derived from the disintegration of rock.
These are of three types:
Coarse sand: It is one which contains 90% of particles of
size greater than 0.6 mm and less than 2 mm.
Medium sand: It is one, which contains 90& of particles
of particles size greater than 0.2 mm and less than 0.6 mm.
Fine sand: It is one, which contains 90% of particles of
size greater than 0.06 mm and less than 0.2 mm.
Proper selection of sand is critical in the durability and
performance of concrete mixture. It should be:
   • Clear, angular and hard
   • Free from clay, mica and soft, flaky material
   • Graded, which means it should be a mix of fine,
     medium and coarse sand
   • Fee from contaminates like sea salt
                             16
 • Consistent in moisture (water) content which should
   not exceed 7%. When mixing concrete the moisture
   content must be taken in to consideration.
 The price of sand includes three or four components-
 base cost, transportation, handling and number of
 intermediaries. Procuring sand in bulk directly from the
 source will be cheaper. Your neighborhood dealer in
 this case is likely to be costlier, except when you need
 smaller quantities.
Building Stone
Building stones are obtained from the rocks occurring in
nature. The stones are used in to construct the
foundation, super structure and many of the building
component. The various stones derived from these types
of rocks are as follows:
  Principal stones from igneous rocks: Granite,
   Basalt and Trap
  Principal stones from sedimentary rocks: Sand
   stone, Shale, Lime stone
  Principal stones from metamorphic rocks:
   Quartzite, slate and marble
  Properties or requirement of good building stone:
                          17
    A good building stone should posses several
  characteristics such as high strength (crushing
  strength>1000kg/cm²), high durability, sufficient
  hardness (coefficient of hardness>14), high resistance
  to wear, good fire resistance, specific gravity more
  than 2.7, crystalline structure, high impact value
  (toughness index> 13) low water absorption
  (percentage absorption after 24 hour less than 0.6),
  weather resistance and better appearance.
  Bricks
Bricks are distinguished by their base (row) material and
size. Standard brunt clay bricks come in the size 10" x 5"
x 3". Modular bricks, rarely used because they are not
easily available, come in the size 200mm x 100mm x
100mm (including mortar thickness) Fly ash bricks,
sometimes also come in modular form.
         Conventional bricks have a ‘frog’ (depressed /
raised portion) on one of the larger surface bearing the
manufacturer’s brand. These also provide a good
mechanical key for bonding (lock ability) with mortar.
The modular bricks do not have the frog on them. Fly
ash bricks exhibit almost similar mechanical properties
as brunt clay bricks. Exposed brickwork with precise
pointing is possible if the shapes are perfect.
The four board categories of bricks used in construction:
                          18
1st class         2nd Class         3rd Class       Over brunt
Bricks             Bricks            Bricks           Bricks
1. Perfect in     Not so uniform    Much interior Absolutely
 Size/shape/      as 1st class      to 2nd class out shape of
quality of       bricks in shape/   bricks in terms and size,
   burning       size/quality of    of shape/size over burnt,
                  burning           and burning     fused with
                                                   more bricks,
                                                  with a honey
                                                  comb texture
2.Red to                                           Dark red to
cherry                                          black in colour
 red in colour
3.Do not     DO not absorb
absorb more more than 25%
than 15 to   water of own
17% of their weight if kept
 own weight submerged
if kept      under water
submerged     for one hour
for one hour
under water
4.Suitable for     Good for brick                   These bricks
precision          work whenever                  are unsuitable
work such          subsequent                      for any kind
as exposed          plastering is                  of brickwork
brickwork            to be done                 and are only
                                                 used in broken
                              19
                                             pieces for
                                            consolidation of
                                            foundation soil
                                           and base of floor
 Aggregate
 ‘Aggregates’ is a general term applied to those inert (that
 chemically inactive) material, which when bounded
 together by cement, form concrete. Most aggregates used
 in this country are naturally occurring aggregates such as
 sand, crushed rock and gravel.
 Aggregates for concrete are divided into three categories:
        •   Fine Aggregates: Most of which passes
            through 4.75 mm I.S. sieve and retained on 150
            micron.
        •   Coarse Aggregates: Most of which passes
            through 63 mm I.S. sieve and retained on 4.75
            micron.
        •     All in Aggregate: Mixed aggregate, as it
            comes from the pit or riverbed. It is some times
            used for unimportant work without separating
            into different sizes.
Properties of Natural Aggregates:
                             20
The properties should comply with the norms laid down in
IS: 38-1970 Specification for C.A. and F.A. from natural
sources for concrete. Aggregates should be chemically
inert, strong, hard, durable, of limited porosity (water
absorption when immersed in water for 24 hours should not
be more than 10%.), free from adherent coating, clay
lumps, coal and coal residues and should contain no
organic or other admixture that may cause corrosion of the
reinforcement or impair the strength or durability of the
concrete. The shape (rounded, irregular, angular and flaky)
and sizes of the aggregates should conform to the strength
and workability requirements.
Uses of the Aggregates:
  1. Naturally occurring crushed stone aggregates can be
     used for producing any type of good concrete or
     R.C.C. for construction purpose.
  2. Broken brick aggregates is used to produce plain
     concrete but not suitable for R.C.C. which is lighter
     than broken stone aggregate.
  3. Air- cooled blast furnace slag, which is a by- product
     in the process of pig iron, forms a stronger and durable
     concrete when mixed with sand, and has a high fire
     resistance.
  4. Lightweight aggregate produce low density concrete,
     which can be used for interior parts of the building
     where high strength are not desired.
                             21
Reinforcement Steel
RCC stands for reinforced cement concrete. To enhance
the load carrying capacity of the concrete it is reinforced
with steel bars of different diameters provided in an
appropriate manner. Such concrete is called reinforced
concrete and the bars are called the reinforcement. These
bare are provided at various locations to resist the
internal forces, which are developed due to the loads
acting on the structure.
   Reinforcing steel contributes to the tensile strength of
the concrete. Concrete has low tensile, but high
compressive strength. The tensile deficiency is
compensated by reinforcing the concrete mass through
insertion of plain or twisted mild steel bars. Both
branded and unbranded bars are available. It is wise to
buy good brands the names of which are marked on the
steel. During construction make sure that steel
reinforcement is provided exactly as the engineering
design specification.
Precautions:
   • Steel bars/rods should be responsibly clean and
     free of rust.
   • Bars that cannot be easily bent manually or
     mechanically should be rejected.
   • Optimum length bars must not be chosen to reduce
     wastage in cutting.
   • To avoid laps, shorter bars must not be accepted
                           22
   • Welded length of the bars should not be accepted
Water
The strength and durability of concrete depends also on
the amount of water mixed with it. Too much or to little
water can adversely effect the strength of concrete. After
concrete is cast, water is used to cure it so that the
temperature is controlled and concrete matures slowly.
    It is very important to use clean, potable water in
quality concrete production. Brackish or salty water must
never be used. Contaminated water will produce concrete
mortars with lower durability, erratic set characteristics
and inconsistent colour.
                          23
       THE EFFECTS OF THE AGGREGATE
  PROPERTIES ON THE CEMENT CONCRETE
            Concrete is a mixture of cementious material,
aggregate and water. Aggregate is commonly considered
inert filler, which accounts for 60 to 80% of the volume and
70 to 85% of the weight of the concrete. Although
aggregate is considered inert filler, it is a necessary
component that defines the concrete’s thermal and elastic
properties and dimensional stability.
                  Physical and mineralogical properties of
aggregate must be known before mixing concrete to obtain
a desirable mixture. These properties include shape and
texture, size gradation, moisture content, specific gravity,
reactivity, soundness, and bulk unit weight. These
properties along with water /cementitious material ratio
determine the strength, workability and durability of the
concrete.
     The shape and texture of the aggregate affects the
properties of fresh concrete more than hardened concrete.
Concrete ids more workable when smooth and rounded
aggregate is used instead of rough angular or elongated
aggregate. Crushed stone produces much more angular and
elongated aggregate, which have a higher surface to
volume ratio better bond characteristics but require more
cement paste to produce a workable mixture.
                             24
   The surface texture of the aggregate can be either smooth
or rough. A smooth surface can improve workability yet a
rougher surface generates a stronger bond between the
paste and the aggregate creating a higher strength.
      The grading or size distribution of aggregate is an
important characteristic because it determines the paste
requirement for workable concrete. The required amount of
the concrete paste is dependent upon the amount of void
space that must be filled and the total surface area that must
be covered. When the particles are of uniform size the
spacing is the greatest but when a range of sizes is used the
void spaces are filled, the less workable the concrete
becomes, therefore, a compromise between workability and
economy is necessary.
   The moisture content of an aggregate is an important
factor when developing the proper water/cementitious
material ratio.
    The density of the aggregate is required in mixture
proportioning to establish weight- volume relationships.
                              25
                 REINFORCEMENT CEMENT
                            CONCRETE
Plain concrete is very strong in compression but its
tensile strength is only about 1/10th of the strength in
compression. So, the use of the plain concrete is limited
to the structure in pure compression. Steel being equally
strong in compression and tension, is, there fore, used to
reinforce the concrete in a suitable way so that it can be
used to build supporting structure where tension also
develops. Concrete, thus reinforced is known as
“reinforced concrete”.
 This combination is made because long steel bars can
develops its full strength where it cannot carry equal
amount of compressive force due to its buckling which is
caused by the slenderness. Thus, the combination of
concrete and steel bars has proved to be ideal, as the two
material are used to resist the stresses for which they are
most suitable.
                           26
Properties of   the  reinforcement
     cement concrete
  1) The concrete develops very good bond with the
     surface of the steel bars and , there fore the stresses
     are transferred from one material to the other which
     cannot resist individually.
  2) The steel possesses a high tensile strength, a high
     modulus of elasticity and same coefficients of
     expansion and contraction as concrete. Due to equal
     linear coefficients, no internal stresses are set up
     within reinforced concrete due to variation in
     temperature.
  3) The coating of cement grout or paste on the surface
     of the reinforcement protects it from corrosion and
     at the same time it does not chemically react with
     the reinforcement.
 Advantage          of     the      reinforcement
 concrete:
  1) It is overall economical in ultimate cost.
  2) Its monolithic character provides more rigidity to
     the structure.
  3) It is highly durable and fire resisting. It is not
     affected by the vermin’s termite’s fungus or such
     other insects.
  4) Well-compacted R.C.C. structure is impermeable to
     moisture penetration.
  5) Care and cost of maintenance of R.C.C. structure
     are almost negligible.
                           27
  6) The fluidity of the concrete and flexibility of
     reinforcement make it to possible to mould the
     R.C.C. members into variety of shapes desired.
Design philosophy
R.C.C. design of building is being carried out mainly by
three methods of design. They are namely: (1) Working
stress method (2) Ultimate load method and (3) Limit
state method.
The Limit state method is now is vogue in all
government design offices and premier private
consulting firms. The B.I.S. have published I.S.: 456-
2000 incorporating the use of the Limit state method of
design. The designer should therefore get well versed
with the theory of Limit state method.
    Working Stress Method: In this method the design is
based on the working load and the criterion for the
strength of the structure is its capacity to sustain the
loads and forces imposed on it.
 Ultimate Load Method: The ultimate load method of
design is based on a determination of the load at which a
structure fails and a certain factor safety is obtained.
     Used over decades, this method is now practically
outdated in many advanced countries of the world,
because of its inherent limitation
                          28
The I.S.: 456-2000 code gives emphasis on Limit State
Method, which is modified from of Ultimate Load
Method.
Limit State Method is a judicious amalgamation of
Working Stress Method and Ultimate Stress Method,
removing the drawback of both of the method but
retaining their good points. It is also based on sound
scientific principles and backed by 25 year of research.
  The Limit State Method has proved to have an edge
over the Working Stress Method from the economic
point of view. Consequently we need no stick to
Working Stress Method any more.
  Accordingly design circle in P.W.D. is designing the
R.C.C. structure as per Limit State Method.
       Besides analytical part of the structural design,
following factors should also be kept in mind while
designing the structure.
     a) Strength of structure.
     b) Durability of structure.
     c) Serviceability of structure during construction as
        well as during design lifetime of structure.
     d) Economy in building material and ease of
        constructions.
     e) Economy in centering and formwork.
     f) Aesthetics of structure
                          29
Cement concrete
 Cement concrete is a composite material used for
 construction of various civil engineering structures. It is
 obtained by mixing the basic ingredients such as cement,
 fine aggregate (normally sand) and coarse aggregate
 (normally stone pieces) in required proportions. Water is
 added in the required measure and the mixture is put into
 a mechanical mixer to achieve concrete. Concrete is
 poured into the formwork (mould made up of plywood,
 steel plates and timber) to get the desired shape. It is then
 vibrated to achieve proper compaction (uniform
 denseness). High temperature is generated through
 chemical reaction in this process. Curing (control of
 temperature) with water is essential to achieve the
 desired strength of the concrete.
      Concrete gains compressive strength progressively
 with time. The strength achieved at the end of the 28
 days is called the Characteristics Compressive Strength
 of the concrete and is designed as a Grade. About 60% of
 this strength is achieved at the end of the 7 days from the
 date of casting. Concrete continues to gain strength even
 beyond 28 days, albeit marginally. The form is
 subsequently removed. Different compressive strength of
 the concrete can be achieved by mixing the basic
 ingredients in different proportions. Being a material
 moulded at site, the durability of the concrete over a long
 period of time depends on its mixing, placement,
                             30
  vibration and curing which together contribute to its
  ‘workmanship’.
    The following table shows guideline proportions for
  some commonly used grades of concrete:
Proportions of the concrete without fly- ash
  Description     M20      M25      M30     M35     M40
  O.P.C. cement   320/     370/     420/     439/   475/
  Of 43 grade     6.4      7.4      8.4      8.78   9.5
  (Kg)
  20 mm Agg.      724/  709/        740/     721/  691/
  (Kg)            113.2 95.81       88.1    92.12 72.73
  10 mm Agg.      480/     474/     497/    481/     372/
  (Kg)             75      64.05    59.17   54.78   39.15
  sand            564/     549/     454/    510/     644/
  (Kg)            88.12    74.19    54.05   58.08   67.79
  water           208.6/   207.9/   207.5/ 190.2/ 182.2/
  (lit.)          32.59    28.1     24.74   21.66 19.19
  Proportion of concrete with fly ash: -
                             31
O.P.C. cement M25      M35
of 43 grade   350      451
   (Kg)
Fly ash       60       127
   (Kg)
 Sand(Kg)      565    510
 Agg. 10 mm 467       422
 Agg. 20 mm 700       625
 Water(lit)    186    199
 Plastisizer   4.10
Properties of Cement concrete
 Strength of concrete:-
 It should be have high compressive strength. The tensile
 and shear strengths are generally about 8 to 12 % and 8
 to 10 % of their compressive strength respectively.
 The compressive strength of concrete is effected by
 several factors such as (a) quality of the material and
 grading of the aggregates (b) water (c) water cement
 ratio (d) cement content (e) age of the concrete (f)
 method of mixing placing compacting and curing
 Workability of concrete
                            32
The concrete should have sufficient workability. The
workability of the concrete indicates the ease with which
it can be mixed, placed and compacted. Generally the
strength decreases with increases of the workability.
Durability of concrete
The concrete posses a high durability value, as it is not
much affected by atmospheric action. On the contrary,
with the age, the concrete goes on hardening, thereby
increase in the strength. It is this property, which gives
this material a distinct place among the building
material.
Elasticity of concrete
The concrete is not a truly elastic material and elastic
modulus is effect by the strength, age, and moisture
content of the concrete and the type of the aggregate
used. The concrete undergoes an extra strain in addition
to instantaneous strain on application of a load or stress,
sufficient time. T his extra strain is called ‘creep of
concrete’ and is permanent in character not recovered on
the removal of load.
Shrinkage of concrete
The concrete has a tendency to shrink under following
conditions:-
                           33
(a) There is initial shrinkage of cement concrete, which
is mainly due to loss of water through forms, absorption
by surface of forms.
(b) The shrinkage of cement concrete occurs as it is
hardened. This tendency of shrinkage on one-hand
causes cracks in concrete, while on the other, it grips the
reinforcement tightly and hence proper bond between
concrete and reinforcement when used in R.C.C. work
Fire resistance of concrete
Concrete is good insulator and has a fairly good fire
resistance owing to the presence of pores and also water.
Workability
Workability is the most elusive property of concrete. A
concrete is said to be workable if it can be easily mixed,
handled, transported, placed in position and compacted.
A workable concrete should not show any segregation
Or bleeding.
   The segregation is said to occur when the coarse
aggregate tries to separate out from the finer material and
this result in concentration of coarse aggregate at one
place and fine material at another place in the mass
concrete. The segregation creates larger voids and
reduces the durability and strength both.
  The bleeding of concrete is said to occur when excess
water comes up at the surface of the concrete. This
causes the undesirable small pores through the mass of
the concrete.
                           34
  The workability of the concrete effected by many
  factors: -
  (a) Shape of the aggregates (b) grading and size of the
  aggregates (c) ratio and coarse and fine aggregates (d)
  efficiency of mixing (e) quantity of water and use of any
  mixture.
  For maximum strength, the desired workability of fresh
  concrete can be attained by the following measure:
         (i)     The proportion of coarse aggregate may
                 be reduced, because the finer is the
                 grading, the greater will be the
                 workability.
         (ii)    The proportion of coarse aggregate may
                 be reduced while on the other hand
                 corresponding increases may be made in
                 that of the finer aggregates.
         (iii)   The process of mixing concrete can be
                 repeated second time by use of the
                 vibrator.
         (iv)    Proportionate increases may be made in
                 the quantity of water and cement as well
                 such that the water cement ratio is
                 maintained.
The suggested range of workability of concrete measured in
accordance with IS 1199
Water cement ratio
Water cement ratio is the ratio of the water in a mix
(excluding water absorbed already by the aggregate) to the
                            35
weight of cement their in. ‘water cement ratio’ is the most
important factor governing the strength of concrete. The
strength of the concrete depend mainly open the amount of
cement and the amount of water in it. The correct quantity
Of water cement ratio required for a particular mix depends
upon various factors such as mix proportions, type and
grading of aggregate, method of compaction applied and
weather condition.
       On the other hand workability of a concrete mix
increases as the water content or water cement ratio of mix
increased, because the water lubricate the mixture. But, at
the same time increases in water content deceases the
strength. Excess of water, further weaken the concrete,
produces shrinkage cracks and decreases density.
Manufacture of the concrete
In the manufacture of concrete, it is almost important to
ensure that a concrete of predetermined proportion is
continuously placed in position in such a way that each
batch almost like the other batches as far as possible.
Batching of the concrete
After fixing the proportion of different ingredients of
concrete for a particular work, the material C.A., F.A.,
cement and water measured out in batches for mixing. The
process is known as Batching. This process of batching
may be carried out by weight or by volume.
                            36
  (i)    Weight batching:- The unit of weight, for
         material of concrete, is usually Kilogram. The
         batching of material by weight is absolutely
         straightforward, the cement, sand and coarse
         aggregate being all weighed directly in Kilogram.
  (ii)   Volume batching:- In batching by volume, all
         ingredient i.e. water, cement, sand and coarse
         aggregate are measured in liters, where the
         resulting concrete (being) solid measured in cubic
         meters.
Mixing of concrete
Mixing of concrete may be carried out by hand or machine
(by using a mechanical mixture) but the mixing by machine
is always preferred.
  (i)    Mixing by hand:- In this, mixing carried out
         by hand on a clean, hard and water tight platform.
         Firstly cement, sand, aggregate are mixed by
         hand with the help of the shovel and a desired
         quantity of the water added to it and mix
         properly. This type of mixing carried out in the
         small work and unimportant work.
  (ii)    Mixing in machine: - The machine used for
         mixing concrete is known as mechanical concrete
         mixer. There are two main type of concrete mixer
         is commonly use namely:
                            37
     Continuous mixers are used in massive construction
  such as dams, bridges, etc., which involve the use of
  large masses of concrete and also required the
  continuous flow of concrete.
  Batch mixer is most commonly used and consisting of a
  revolving drum with blades or baffles inside it. In batch
  mixer, all the material of desired proportioned mix are
  fed into the hopper of the revolving drum on being
  rotated at a certain speed mixes the material with the aid
  of a series of blades providing inside, the resulting mix is
  finally discharged from the drum and conveyed for used.
Transportation of concrete
 Transporting the concrete mix is defined as the transferring
of concrete from the mixing plant to the construction site.
Keep in mind that not all concrete is mixed on the actual
construction site and could require some significant travel.
This is most common for ready mixed concrete. The main
objective in transporting concrete is to ensure that the water
cement ratio, slump or consistency, air content,
homogeneity are not modified from there intended states.
The concrete transport commonly by the steel pipes.
Placing and finishing of concrete
   Mixing, transporting, and handling of concrete should be
carefully coordinated with placing and finishing operations.
Concrete should not be deposited more rapidly than it can
be spread, struck off, consolidation, and bull floated.
                              38
Concrete should be deposited continuously as near as
possible to its final position. In slab construction, placing
should be started along the perimeter at one end of the
work with each batch placed against previously dispatched
concrete. Concrete should not be dumped in separate piles
and then leveled and worked together; nor should the
concrete be deposited in large piles and moved horizontally
into final position.
   Consolidation
  In some types of construction, the concrete is placed in
  forms, and then consolidated. The consolidation
  compacts fresh concrete to mold it within the forms and
  around embedded items and reinforcement and to
  eliminate stone pockets, honeycomb and entrapped air. It
  should not remove significant amount of intentionally
  entrained air.
   Vibration either internal or external is the most widely
  used method for consolidating concrete. When concrete
  is vibrated, the internal friction between the aggregate
  particles is temporarily destroyed and the concrete
  behave like a liquid; it settles in the forms under the
  action of gravity and the large entrapped air voids rise
  more easily to the surface. Internal friction is
  reestablished as soon as vibration stops.
  Finishing
   Concrete that will be visible, such as slab like driveway,
  highway or patios often need finishing. Concrete slabs
  can be finished in many ways, depending on the intended
                             39
service use. Options include various colors and textures,
such as exposed aggregate or a patterned stamped
surface. Some surface may require only strike off and
screeding to proper contour and elevation, while for
other surface a broomed, floated, or troweled finish may
be specified. In slab construction screeding or strike off
is the process of cutting off excess concrete to bring the
top surface of the slab to proper grade. A straight edge is
moved across the concrete with a sawing motion and
advanced forward a short distance with each movement.
Bull floating eliminates high and low spots and embeds
large aggregate particles immediately after strike off.
This look like a long handled straight edge pulled across
the concrete. Joining is required to eliminate unsightly
random cracks. Construction joints are made with a
groover or by inserting strips of plastic, wood, metal, or
performed joints material into the unhardened concrete.
Saw cut joints can be made after the concrete is
sufficiently hard or strong enough to prevent the
reveling. After the concrete has been jointed it should be
floated with a wood or metal hand float or with a
finishing machine using float blades. This embeds
aggregate particles just beneath the surface; removes
slight imperfections, humps, and voids; and compacts the
mortar at the surface in preparation for addition finishing
operations. Where a smooth, hard, dense surface is
desired, floating should be followed by steel troweling.
Troweling should not be done on a surface that has not
been floated; troweling after only bull floating is not an
adequate finish procedure. A slip resistant surface can be
                           40
produced by brooming before the concrete has
thoroughly hardened but it should be sufficient hard to
retain the scoring impression.
Curing of concrete
Curing is one of the most important step in concrete
construction, because proper curing greatly increase
concrete strength and durability. Concrete hardened as a
result of hydration: the chemical reaction between
cement and water. However, hydration occurs only if
water is available and if the concrete temperature stays
within a suitable range. During the curing period from
five to seven days after placement for conventional
concrete the concrete surface needs to be kept moist to
permit the hydration process. New concrete can be wet
with soaking hoses, sprinklers or covered with wet
burlap, or can be coated with commercially available
curing compounds, which seal in moisture.
          After concrete is placed, a satisfactory moisture
contents and temperature (between 50º F and 75º F) must
be maintained, process called curing. Adequate curing is
vital to quality concrete. Curing has a strong influence on
the properties of hardened concrete such as durability,
strength, water tightness, abrasion resistance, volume
stability and resistance to freezing and thawing and
deicer salts. Exposed slab surfaces are especially
sensitive to curing. Surface strength development can be
reduced significantly when curing is defective.
                           41
        Curing the concrete aids the chemical reaction
called hydration. Most freshly mixed concrete contains
considerably more water than is required for complete
hydration of the cement; however, any appreciable loss
of water by evaporation or by otherwise will delay or
prevent the hydration. If temperature are favorable,
hydration is relatively rapid the first few days after
concrete I s placed; retaining water during this period is
important. Good curing means evaporation should be
prevented or reduced.
Removal of the formwork
The period for which forms should be left in place
depends upon the temperature of air, the shape and
position of structural member (i.e. horizontal vertical or
inclined), the nature of the loads likely to come and the
character of the cement and cement paste. Generally, the
use of rapid hardening cement, higher temperatures, low
water cement ratio and lighter loads, will permit early
removal of formwork.
    Under normal conditions where temperature is above
20ºC and ordinary cement is use, forms may be removed
after the expiry of the period given below:
Particulars of the structural         period of
member                             removing of formwork
(a) Vertical slides of slabs, beams     24 to 48 hours
    columns and wall
                           42
(b) Slabs (props or vertical supporting   3 days
     member left under)
(c) Beams soffits (props left under)      7 days
(d) Bottom of slabs up to a span           7 days
    of 4.5 m.
(e) Bottom of slabs above 4.5 m            14 days
    span, bottom of the beams up
    to 6 m span, and bottom of arch
     ribs up to 6 m span
(f) Bottom of beams over 6 m span             21 days
    and bottom of arch ribs over 6 m span
Placing of concrete in hot weather
In tropical countries such as India, air temperature may
rises up to 50C during summer month. Such temperature
combined with the high wind velocity and low humidity
the rate of the evaporation of the water increase the rate
of the hydration of cement, which reduce the setting time
of the concrete and due to rapid evaporation of the water
t5here is increase drying and shrinkage which tend to
develops the cracks soon after placing even before
hardening is completed.
Water forms about 1/6 & 1/8 the total weight of
concrete. The quantity of mixing water in a unit of
concrete is decided primarily by the workability desired.
So due to accelerate hydration and to increase the
workability and maintain the required consistency, water
                          43
content will have to be increase and due to this the
concrete not develop its full strength.
      As far as possible cold weather should be used for
the concreting. In hot weather, protect the concrete from
exposure to sun and drying hot winds with wet gunny
bags or hers ion cloth as far as possible and pounding
should start water curing as soon as possible.
Common tests on the fresh concrete
Concrete is tested to ensure that the material that was
specified and bought is the same material delivered to
the job site. There are a dozen different test methods for
freshly mixed concrete and at least another dozen tests
for hardened concrete, not including test method unique
to organization like the Army Corps of Engineers, the
Federal Highway Administration, and State department
of transportation.
     Slump, air content, unit weight and compressive
strength tests are most common tests.
   Slump is a measure of consistency, or relative
    ability of the concrete to flow. If the concrete can’t
    flow because the consistency or slump is too low,
    there are potential problems with proper
    consolidation. If the concrete won’t stop flowing
    because the slump is too high, there are potential
                          44
  problems with mortar loss through the formwork,
  excessive formwork pressure, finishing delays and
  segregation.
 Air content measure the total air content in a sample
  of fresh concrete, but does not indicate what the
  final in-place air content will be, because a certain
  amount of air is lost in transportation Consolidating,
  placement and finishing. Three field tests are widely
  specified: the pressure meter and volumetric method
  are ASTM standards and the Chace Indicator is an
  AASHTO procedure.
 Unit weight measures the weight of a known
  volume of the fresh concrete.
 Compressive strength is testes by pouring cubes of
  fresh concrete and measuring the force needed to
  break the concrete cubes at prescribed interval as
  they harden. According to Building Code
  Requirements for reinforced concrete (ACI 318) as
  long as no single test more than 500 psi below the
  design strength and the average of three consecutive
  tests equals or exceed the design strength then the
  concrete is acceptable. If the strength tests don’t
  meet these criteria, steps must be taken to raise the
  average.
                        45
                                      ADMIXTURES
Admixtures are defined as the material other than the
aggregate, water and cement added to the concrete. The
use of suitable admixture can result in the enhancement
the performance of concrete.
Types of Admixture
Air Entraining Agents
   Air entraining agents are used primarily to increase the
resistance of freezing and thawing. They also supply
greater resistance to deicing chemicals, improve
workability, lower water demands for a particular slump,
reduce the amount of fine aggregate needs in the
mixture, reduce segregation and bleeding, increase
durability, and improve pump ability. Even though air
entrainments have no effect on drying shrinkage, they do
create a slight loss in the concrete strength.
                           46
Water Reducing Agents
   A certain amount of the water is added to concrete to
make the concrete place able and to ignite the hydration
reaction of Portland cement. Over 50% of the water have
no useful effect and have direct results in drying
shrinkage, durability, and the strength of concrete. Water
reducing agents added to the concrete reduce the water
demands of the mix, maintain the workability, increase
the strength, reduce the cost, reduce bleeding, reduce
segregation, reduce honeycombing, reduce cracking and
permeability, increase bond strength of concrete to steel,
and reduce drying shrinkage. An average of 12-15 %
reduction in the total water content will attain this goal.
Set Retarding Agents
These agents are primarily used for delaying the setting
time of concrete. Set retards are useful, but are not the
solution to poorly designed mixes, inferior materials, or
low cement factors. The set retarder must be uniformly
dispersed throughout the whole mix. Failure to do so will
result in the admixture remaining in voids, causing some
areas to remain plastic. This leads to plastic shrinkage.
Accelerating Agents
Accelerating agents are used to shorten the setting time
and increase the early strength of the concrete. These
agents are mainly used for concrete needing to be used
immediately.
                           47
Calcium chloride
Calcium chloride is generally used in cold weather to
hasten the setting time and produces an early finish of
the concrete. Calcium chloride can effect the
characteristics of concrete causing temperature rise,
increased internal stresses, corrosion of unprotected
reinforcement, a decrease in the resistance to freeze, an
increase in the attack of sulfates, and an increase in the
amount of drying shrinkage between 10 to 50 %.
                          48
                                        FORMWORK
‘Temporary Supporting Structure’ is those structures,
which are temporarily required in building construction
either for supporting the laying of concrete till it gets
matured, such as formwork or forms or shuttering. As
fresh concrete is in a plastic state, when it is placed for
construction purposes, so it becomes necessary to
provide some temporary structure to confine and support
the concrete, till it gains sufficient strength for self-
supporting. The temporary structure is known as
Formwork or shuttering.
Requirement of the formwork
God forms for concrete structure should satisfy the
following requirements;
(1) It should be strong enough to resist the pressure or
     the weight of the fresh concrete and the
     superimposed loads due to equipment, men etc.
     This requires careful design of formwork, because
     the consideration of overloads will affects the
     economy whereas of under loads may cause failure
     of the forms work.
                           49
(2) It should be rigid enough to retain the shape without
    undue deformation.
(3) It must be made or constructed so light that it does
    not allow the cement paste to leak through the
    joints.
(4) The inside surface of the formwork should be
    smooth so as to give good appearance to the
    resulting concrete surface. To achieve this, the
    inside surface of formwork is usually applied with
    crude oil or soft soap solution. This also facilitates
    the removal of the formwork.
(5) The entire formwork should be so made that it can
    be removed easily without causing the least injury
    to the surface or edges of the concrete.
(6) It should be made economical by reducing the cost
    through proper design, construction and use of
    formwork.
                               GENERAL NOTES
                          50
The general notes specify the quantities and quantities of
materials, the proportion of the mortar, workmanship.
The method of preparation and execution and the
methods of the measurement.
The company prepares the general notes of various items
of work, and gets them printed in the book from under
the name of general notes. Some of the general notes are
given below related to Building Construction.
1. Earthwork              in     excavation           in
foundation:-
  Excavation- Foundation trenches shall be dug out to
   the exact width of the foundation concrete and the
   sides shall be vertical. If the soil is not good and
   does not permit vertical sides, the sides should be
   sloped back or protected with timber shoring.
   Finish and Trench- the bottom of the foundation
   trenches shall be perfectly leveled both
   longitudinally and transversally and the sides of the
   trench shall be dressed perfectly vertical from
   bottom up to least thickness of lose concrete may be
   laid to the exact width as per design. The bed of the
   trench shall be tightly watered and well rammed.
   Soft or defective spots shall be dug out excess
   digging if done through mistake shall be filled with
   concrete.
  Water in Foundation- water if any accumulates in
   trench. Should be baled or pumped out without any
                          51
  extra payment and necessary precautions shall be
  taken to prevent surface water to enter in trench.
 Trench Filling- after the concrete has been laid and
  masonry has been constructed, the remaining
  portion of the trench shall be filled up with earth in
  layers of 51 cm and watered and well rammed.
 Measurement- the measurement of the excavation
  shall be taken in cu m as for rectangular trench,
  bottom width of concrete multiplied by the vertical
  depth of the foundation from ground level and
  multiplied by the length of the trench.
2. Foundation
 The foundation of the building should be so planned
  and the lay out of the foundation should be on the
  ground should be correct in the measurement.
 Should not place the concrete in the foundation
  before checked by the Engineer-in charge.
 If building has the basement more than two raft
  foundations should be provided.
 In the P.C.C. it should be in the ratio of 1:4:8 and
  75 mm thick 75 mm projected beyond raft
  foundation.
 The concrete provided in the raft foundation should
  be M-25 grade conforming to IS456.
 The design and thickness of the raft foundation
  provided by the soil testing.
 Schedule of the raft foundation
                         52
Grade of Thickness         Reinforcement
Concrete D     T      continuous    extra distribution
         mm     mm b11      t11 t12 t21 t22 t23
M-25    1300    700 20      20                  16@
                      @     @                   200
                    240     120
3. Reinforcement Concrete Work
      All reinforcement shall be of tested quality high
       yield strength deformed bars conforming to IS 1786
       shall be used as reinforcement steel.
     The lap length of bars shall be equal to Ҟ (splice
       factor) X Dia of small bar. The value of Ҟ shall be
       as per following table:-
       Grade of the      value of the splice factor
       concrete           for column       for other
     M-20                  40                 50
     M-25                  35                 45
     M30                   35                 45
     M-35                 30                  40
     M-40                 30                  40
      Lapping of bars shall be suited staggered and in no
      case more than 50% bars shall be lapped at any
     section.
    The chair to support the raft foundation bars can be
     provided at the distance of the one-meter.
                           53
     The length of the anchorage should be 300mm
     The reinforcement should be provided as per the
        detailed drawing specification.
     The bars of the reinforcement should straight not be
        in the zigzag manner.
     Check the slump of the concrete when concrete is
        placing.
     Clean cover to the main reinforcement shall be as
        follows:
Structural element                Top    Bottom Sides
  1. Footing/raft                  50      50         50
  2. Column dimension              -       -          25
      up to 230
  3. Column dimension up           -       -          40
     above 230
  4. R.C.C. wall up to 150 thk.     25    25           25
  5. R.C.C. wall above 150 thk. 40        40           40
  6. Beams                          25    25           25
  7. Lintel up to 200 depth        15     15           15
  8. Lintel above 200 depth         25    25           40
  9. Slab & chhaja                  15    15           25
 4. Brick Work I Class
      Bricks- all bricks shall be first class of standard
       specification, made of good brick earth
       thoroughly brunt, and shall be keep cherry red
       and copper colour, brick should be regular in
       shape and other edges should be sharp and small
                           54
 emit clear ringing sound on being struck, and
 shall be free from crack, chips, flaws and lumps
 of any kind. Brick shall not absorb water more
 than one-sixth of their weight after one hour of
 soaking by immersion in the water. Brick shall
 have a minimum crushing strength of 105 Kg per
 sq cm (1500 lbs per sq in.)
Mortar- For mortar, cement shall be fresh
 Portland cement of standard specification. Sand
 shall be clean and free from organic and foreign
 matters. For rich mortar coarse or medium sand
 used and for weak mortar local fin sand may be
 used. Proportion of the cement sand mortar may
 be of 1:3 as specified.
Material of mortar shall be measured to have the
 required proportion and first mixed thoroughly by
 turning at least three times. Fresh mixed mortar
 shall be use, old and stale mortar shall not be
 used and mortar for one-hour work only shall be
 mixed with water so that the mortar may be used
 before setting starts.
Soaking of brick- brick shall be fully soaked in
 clean water by submerging in tank for a period of
 12 hour immediately before use.
Laying- brick shall be well bonded laid English
 bond. Every course shall be truly horizontal and
 wall shall be truly in plumb vertical of
 consecutive coarse shall not come directly over
 one another. Vertical joints in alternate course
 shall come directly over one another. Mortar
                    55
    joints shall not exceed 6 mm in thickness and
    joints shall be fully filled with mortar.
   Curing- the brickwork shall be kept wet for a
    period of at least 10 days after laying. At the end
    of days work the topes of the walls shall be
    flooded with water by making small weak mortar
    edging to contain at least 2.5 cm deep water.
   Protection- the brickwork shall be protected from
    the effect of sun, rain, frost etc. during
    construction and until such time it is green and
    likely to be damaged.
   Scaffolding- necessary and suitable scaffolding
    shall be provided to facilitate the construction of
    the brick wall. Scaffolding shall be sound and
    strong and sup[port and members sufficiently
    strong so as to withstand all loads likely to come
    upon them.
   Measurement- brickwork shall be measured in cu
    m different kinds of brickwork with different
    with different mortar shall be taken under
    separate items. The width of wall shall be
    measured as multiple of half brick. The rate shall
    for the complete work including scaffolding and
    tools and plants.
5. Plastering
 The joints of the brick work shall raked out to a
  depth of 12 mm and the surface of the wall washed
                        56
  and clean and kept wet for the two days before
  plastering. The material of mortar should be of
  standard specification.
 The thickness of the plastering shall be of 12mm to
  ensure uniform thickness of plaster; patches of 15
  cm shall be applied first at about 2 m apart to act as
  guide. First mortar shall be dashed and pressed over
  the surface and then brought to a true smooth and
  uniform surface by means of float and trowel. Wall
  plastering shall be started from top and worked
  down towards floor,. Ceiling plastering shall be
  completed before starting of wall plaster. All corner
  and edge shall be rounded. The plastered surface
  shall be kept wet for 10 days the surface should be
  protected from rain, sun, frost, etc.
 For wall plastering 1:5 cement mortar and for
  ceiling plastering 1:3 cement mortar with coarse
  sand is used.
6. 25 cm Cement Concrete floor
 The cement concrete shall be of proportion 1:2:4
  cement shall be fresh Portland cement of standard
  specification. The coarse aggregate shall be hard
  and tough of 3 cm gauge, well graded and free from
  dust, dirt, etc. the sand shall be coarse of 5 mm
  maximum size and down, well graded, clean and
  free from dust, direct and organic matters.
 The floor shall be leveled and divided into panels or
  bays of maximums size or 1.2m x1.2m and the sides
                         57
  of the panels shall be bounded with teak wood
  battens 2. cm thick and 5 cm wide or flat iron of
  same thickness and fixed with weak mortar, or with
  nails or hooks. Required camber or slope should be
  given in floor for draining wash water.
 Mixing of concrete shall be down by measuring
  with boxes to have the required proportion as
  specified. First cement and sand mixed dry and the
  dry mix of cement and sand mixed with ballast dry,
  and the mixed by adding water slowly and gradually
  to the required quantity, and mixed thoroughly to
  have a uniform plastic mix.
 Base – In ground floor the c.c. floor shall be laid on
  a 7.5cm base of weak cement concrete as per
  standard specifications.
7. White washing
   Fresh white lime slaked at site of work should be
  mixed with sufficient water to make a thin cream. It
  shall then be screened through a coarse cloth, and
  gum in proportion of 100 gms of gums to 16 liters of
  wash shall be added.
   The surface should be dry and thoroughly
  cleaned from dust and dirt. The wash shall be applied
  with Moonj or jute brush, vertically and horizontally.
  And the wash kept stirred in container while using.
  Two or three coats shall be applied as specified, and
  each coat shall perfectly dry before the succeeding
  coat is applied over it. Dry before the succeeding
                         58
  coat shall be applied as specified, and each coat shall
  be perfectly dry before the succeeding coat is applied
  as specified, and each coat shall be perfectly dry
  before the succeeding coat is applied over it. After
  finishing the surface shall be of uniform colour. The
  white wash should not splash on the floor and other
  surfaces. In old surface, the surface should be
  cleaned and repaired with cement mortar where
  necessary and allowed to dry before white wash is
  applied.
8. Wood work
   All wood work of which the scantling exceeds
  20 sq cm in section and which is not specially
  moulded or carved comes under carpenter’s work.
  This include all timer work in choukhats of door and
  windows, in roof works as beams, struts, ties, rafters,
  purlins, in timber bridge, etc.
   the timber shall be of the kind as specified, may
  be teak, shisham, sal, deodar, etc. the timber shall be
  of best quality, well seasoned and free from sap,
  knots, warps, creaks, and other defects. All
  woodwork shall be planed, and neatly and truly
  finished to the exact dimensions. Al joints shall be
  neat and strong, truly and accurately fitted, and
  coated with white lead before being fitted together.
   All portions of timber built into or in contact of
  masonry or concrete shall be given two coats of
  solignum or tar or other approved preservatives,
                         59
exposed surface of timber shall be painted with two
coats of approved paint over a coat of priming.
 All beams shall be bedded on plates with a
minimum bearing of 25 cm and 6 mm clear air space
shall be left on each side.
 Measurement of wood work shall be taken in cu
m for the finished work fixed in position including
sawing, planning, joining, nails, screws etc. painting
of wood work shall be measured under separate item.
                                              INDEX
                       60
Basic data for the Building
A.   (1). Thickness of the raft                     0.70 m
     (2). Projection of raft beyond footing         0.50 m
     (3). Projection of raft beyond basement        0.50 m
     (4). Depth of sand filling on the raft         0.50 m
     (5). Thickness of P.C.C. below raft            0.075 m
     (6). Projection of P.C.C. beyond raft          0.075 m
     (7). Depth of lift pit                         1.70 m
B.    Floor Height
     (1). Top of pad to first basement level        4.00 m
     (2). Top of first basement to ground level     3.30 m
     (3). Ground floor to first floor               4.20 m
     (4). First to second & second to third floor   4.20 m
     (5). Third floor to roof                       4.15 m
C.   Depth of excavation
     (1). First lift                                1.50 m
     (2). Second lift                               7.375 m
                                       61
   Quantity of work proposed
S. no.    Item description              unit   quantity      total   R/F
A.     Earth work
  (1). Earth work in the excavation     cum     5878         5878
       up to 1.5 m
  (2). Earth work in excavation below   cum     26370        26370
       1.5 m
  (3). Earth in back filling            cum     5278         5278
  (4). Disposal of surplus earth work   cum     26970        26970
  (5). Sand fill on the raft            cum     1393         1393
B.    Total P.C.C. (1:4:8)              cum      276.6    276.6
C.    Reinforcement Concrete
 (1). Raft M-25                      cum         2401.7                80
 (2). Retaining wall M-25            cum         78.5                 120
 (3). Water tank wall M-25          cum           69                  120
 (4). Pedestal M-35                 cum           269.6               200
 (5). Column M-35                   cum           232.2               320
 (6). Column M-30                   cum           331.0               240
 (7). Beam M-35                     cum           1533.2              180
 (8). Water tank base slab M-25     cum           64.4                  80
 (9). Water tank top slab M-25      cum           21.7                  80
 (10). Slab M-25                    cum            1394.73              80
 (11). Staircase M-25               cum            98.58              160
 (12.) Sump M-25                    cum            68.88               80
 (13). Slab on grade M-20           cum            286.74              60
 (14). Mics.                        cum             200.0             100
           Total                       cum            7492.12
  D. Shuttering
 (1). Raft                          Sq. m.         311.38
 (2). Retaining wall                Sq. m          4173.33
 (3). Pedestals M-35                Sq. m          273.29
 (4). Columns                       Sq. m          4012.2
 (5). Beams                         Sq. m           9597.1
 (6). Slabs                         Sq. m          7353.5
 (7). Water tank base slab          Sq. m           338
 (8). Water tank top slab           Sq. m           1084
                                   62
 (9). Water tank wall M-25    Sq. m         389.8
 (10). Staircase              Sq. m         492.9
 (11). Sumps                  Sq. m         196.8
  (12). Mics.                 Sq. m         400.0
          Total                  Sq. m        26942.4
E.   Reinforcement           metric tones   943
F.   Covered slab area        Sq. m         11446.4
G.   Rein/ area of slab       Kg/ Sq. m     82.4
H.   Rein concrete (Kg.)                    125.8
I.   Conc./area of slab       cum/ Sq. m    0.65
J.   Shuttering                             3.60
                              63
   Specification for the floor, paint, ceiling &
   door and window
   Banquet Hall
Flooring                        Marble flooring with udaipur green
border
Wall                      Textured paint
Ceiling                   POP false ceiling with cornice
Door & windows            Paneled & Glazed
   Bar/ Restaurant/ Dining room
     Flooring                Marble flooring
Wall                           texture paint with panel of stone and
tile
                          combination
Ceiling                   POP false ceiling
Door & windows            paneled & glazed
   Swimming pool
Internal                  Glazed tiles
Deck area                 Red agra & Dhaulpur combination flooring
   Kitchen/ Pantry
Flooring                  Polished kota stone/ Non skid tile
Wall                      Ceramic tile up to 7 feet
Ceiling                   White wash over plaster
Door & window             Flush door & glazed paneled window
   Toilet/ Changed room
                               64
    Flooring                Udaipur green & jaisalmer yellow
    combination
Counters                 Granite stone
Chinaware                pleasing pastel colours
Fitting                  C.P. single lever fitting
Dado                     ceramic tiles up to 7 feet
Door/ window             Flush door & glazed paneled window
Kids entertainment/ Squash/ Bridge/ Card room/ Carom/
Library/ Gym/ Billiards room/ Conference room/ ATM/
Mini cinema
Flooring                 Udaipur green & jaisalmer yellow
combination
Walls                    Textured paint
Ceiling                  Gypsum board false ceiling
Door & windows           paneled & glazed
   Suites/ Double room
Flooring                 Carpet over IPS flooring
Wall                     Textured paint
Ceiling                  POP false ceiling
Door & windows           paneled & glazed
                                65
Schedules of the different structural elements
 1.Schedules of the raft
 S.no. grade of thickness       reinforcement            distribution
       concrete D. T       continuous      extra
                         t11 t11 t12 t21 t22 t23
       M-25         20 20                                 16@200
                    @   @
                    240 120
Schedules of the ramp wall reinforcement
 s.no. wall    wall     wall     Base     vertical       Horizontal
       mkd.    Thick    height   width    a1 a2       b1 b2 c1 c2
 1.   Rm w1 300        up to     2050     12 16       12 12 10 10
                        3000              @  @        @ @ @ @
                                         240 240     240 240 240 240
 2. Rm w2 450          3000      2750    12 16       12 12 10 10
                       -4000              @ @         @ @ @ @
                                         240 240     240 240 200 200
 3. Rm w3     550       4000     3350    16 20       16 16 10 10
                       -5000             @ @          @ @ @ @
                                         220 220     220 240 175 175
                                   66
Levels of the basement & floor levels
                    +17950 mm
                           Roof terrace
                     +13800 mm
                                Third floor
                   +9600 mm
                                 Second floor
                    +5400 mm
                                First floor
                   +1200 mm
                                  Ground floor
                          0.00 mm
----------------------------------- Ground level
                     -3300 mm
                                    First basement
                      -7500 mm
                                        67
                                    Second basement
                      -8800 mm
                                    P.C.C. level
Test result from the site
1. Cube testing of design mix M-25:
Casting date :    24/5/05   Mix proportion:      Design mix
Grade:               M-25   Location of casting: Basement raft
Water cement ratio: 0.53    Cement content: 350Kg/m3
Slump: 140mm (concrete by batching plant & concrete plant)
Required strength: 175Kg/m3 on 8 days
No.     weigth of       cross section        due date     max. load    7 days
       the specimen       area               for 7 days   (Kg)        strength
          gm             cm2                 strength                 Kg/cm2
1.      7850              225                 31/5/05      21000         120
2.      7895              225                             32000         142.22
3.      7895              225                             31000         137.77
4.      7865              225                             30000         133.33
Average stregth after 7 days testing is found: 133.33 Kg/cm2
Remarks: only 53% of 250 Kg/cm2 strength is taken by the cube so initial
strength is low.
Action: control Watre cement ratio of batching plant strictly for better result.
  (there are another test results this is a sample test report)
2. Test for coarse aggregate
(a) For 10 mm size
                                        68
        Specific gravity     2.67
        Voids content       50.5%
s.no.         sieve size   % passing            according to table-2 of Is
                                                 383-1970 % passing for
                                                   10mm single size
1.            40 mm         100                      -
2.            20mm          100                      -
3.            10mm          86.9                     85-100
4.            4.75mm        0                        0-10
The above result conform coarse aggregate of 10 mm single size aggregate.
(B) For 20 mm size
        Specific gravity   2.69%
        Void content       49.4%
S.no.       sieve size       % passing              according to table-2 of
Is 383-1970
                                                    % passing for 20mm
single size
1.                40 mm        100                          100
2.                20 mm        95.75                         86-100
3.                10 mm        1.75                          0-20
4.                 0           0                            0-5
The above result compare coarse aggregate of 20 mm single size. The
proportion of the above two size (10 mm & 20 mm) were 0.33:0.67 in
proposed mix.
SLIT TEST
The slit found in the sand sample is 10.34%
F.M. (sieve test)- 3.6%
                                    69
Remarks: the slit content is beyound the permissible limit, make slit test
mandatory before getting material unloaded at site.
                                      70