Mabini Colleges
Daet, Camarines Norte
PROPOSAL FOR THE CONSTRUCTION OF
COMFORT ROOMS ON THE SECOND AND
THIRD FLOOR OF MABINI COLLEGES
Starting Date: APRIL 2017
Duration: 30 DAYS
Project Directors: CREO, Jokoz; RICERRA, Agnetha Larize Noemi Lynn;
FAJARDO, Danna Cenn; NAGERA, Marc Hancel;
CUELA, Mary Antonette; LATOSA, Abigail
Total Amount of Funds Requested: P 200,000.00
TABLE OF CONTENTS
I. ABSTRACT ...............................................................................................................1
II. INTRODUCTION ....................................................................................................2
III. NEEDS/PROBLEMS .............................................................................................3
IV. GOALS/OBJECTIVES............................................................................................3
V. PROJECT PLAN ......................................................................................................4
VI. EVALUATION..........................................................................................................4
VII. DISSEMINATION ...................................................................................................5
VIII. KEY PERSONNEL ..................................................................................................5
IX. EQUIPMENT AND FACILITIES ........................................................................6
X. BUDGET ....................................................................................................................8
ABSTRACT
This proposal addresses the construction of new comfort rooms in Mabini Colleges. The need for
its construction should be considered. The inadequacy and inconveniency of its location primarily
affects the students and the other members of the school community. Its main objective is basically
to increase the satisfaction of the targeted population. It is significant because it can help not just
the students, but also the faculty and non-faculty members of the school. The outcomes will include
the approval of the whole population, the satisfaction, and the increase in work. This will be
disseminated to the Sublime Torch distributed by the Mabini Colleges.
1
INTRODUCTION
Mabini Colleges is an institution offering and cultivating a culture of excellence and quality
education. It aims to transform students into: God-fearing, nation-loving, earth-caring, law-abiding,
PRODUCTIVE, and locally and globally competitive persons. Focus on the word PRODUCTIVE.
The school built high-standard facilities, but is it adequate and convenient enough for the whole
population? For the students to be productive, they should not be burdened. The location of the
facilities may or may not affect the students’ productivity. Its’ compatibility with the other
facilities next to it can greatly influence each one’s growth as a student.
Comfort rooms are built not just for the students, but also to all individuals involved with the
institution. Mabini Colleges’ main campus have comfort rooms located on the ground floor, (one
right next to room 108, which is for the male population AND one near the clinic, which is for the
female). Other comfort rooms, like the one located on the third floor, is closed and not functioning.
The school also have comfort rooms near the high school building, but it can be inconvenient
sometimes because of its location, its size, and basically, not everyone can use it. Some rooms,
like the faculty room, only allow authorized personnel to use it. The construction of comfort rooms
in Mabini Colleges should be considered because it is a must in every building for an efficient
work.
2
PROBLEMS / NEEDS
The problem to be addressed is the inadequacy and inconveniency of comfort rooms in Mabini
Colleges. The need for the construction of new comfort rooms, specifically on the second and third
floor should be considered. The target population is the overall population of the institution, the
students, faculty and non-faculty members. Specifically, the following are needed to be address:
• How does the location of the comfort rooms affect the students, faculty and non-faculty
members?
• What are the pros and cons of constructing new comfort rooms?
• Will the new comfort rooms satisfy the need of the targeted population?
GOALS/ OBJECTIVES
This project proposal will focus on the construction of comfort rooms in the roof garden of Mabini
Colleges for their students and employees. Specifically, this project will satisfy the following:
To provide the need of the students and employees for a more convenient location of
comfort rooms.
To avoid wastage of time.
To encourage students to use the bathroom.
3
PROJECT PLAN
Provided below are the detailed information of the proposed procedures:
1. Gathered the specific details of the proposal for the construction of comfort rooms in
the second floor and third floor of Mabini Colleges.
2. Formulated a survey questionnaires. [40 Respondents- 20 Male, 20 Female]
3. The construction of comfort rooms will be patterned to the comfort rooms in the Mabini
Colleges main building.
EVALUATION
To evaluate the success of this project proposal, we will conduct a survey by using questionnaire.
The questionnaire will contain the following questions:
Can the newly built comfort rooms satisfy your need for a nearer comfort room?
Is it quicker now to use the comfort room?
Does the new comfort room encourage you to use it?
These questions can be answered by shading YES or NO. Through this, we can obtain the
necessary information for us to know if the newly built comfort rooms give any differences.
4
DISSEMINATION
Students that have rooms residing on the second and third floor will not be hasty in excusing
themselves to class just to go to the comfort room. Students won’t miss some important details in
class during discussion because the time spent going back and forth to the ground floor up to the
upper floors will be lesser. Student will have better access of the comfort rooms. This improvement
will be written in the Sublime Torch of Mabini Colleges.
KEY PERSONNEL
Below is a list of key personnel who will be responsible for the completion of the project, as well
as the other personnel involved in the project.
Client: MABINI COLLEGES
Project Manager: MABINI COLLEGES MANAGEMENT
Team: MABINI COLLEGES MANAGEMENT
Other: CREO, JOKOZ CUELA, MARY ANTONETTE
LATOSA, ABIGAIL NAGERA, MARC HANCEL
FAJARDO, DANNA CENN RICERRA, AGNETHA LARIZE
NOEMI LYNN
5
Quantity Description Unit Price Amount
2 pcs PVC Door (60 x 210) P 970.00 P 1,940.00
2000 pcs Hollow Blocks 10.00 20,000.00
30 bags Cement 210.00 21,000.00
100 pcs Tiles 27.00 2,700.00
10 bags Ceramic tile adhesive 120.00 1,200.00
2 gal Enamel (paint) 575.00 1,150.00
2 gal Flat (paint) 460.00 920.00
2 pcs Toilet Bowls 9,000.00 18,000.00
1 pc Male Urinal 8,000.00 8,000.00
2 pc Sinks (faucet included) 6,500.00 13,000.00
2 pc Wall Mirrors 1,200.00 2,400.00
4 pc LED tube lamps 950.00 1,900.00
2 pc Exhaust fan 1,000.00 2,000.00
2 pc Hygienic Spray 1,500.00 3,000.00
2 pc Pail 50.00 100.00
2 pc Dipper 20.00 40.00
2 pcs Trash bins 90.00 180.00
50 pcs Coco Lumber (2x2) 50.00 2,500.00
5 pcs Plywood (1/4) 300.00 1,500.00
4 pcs Plywood (3/4) 400.00 1,600.00
100 sacks Gravel and Sand 60.00 6,000.00
2 kls Nail 70.00 140.00
2 kls Tire Wires 120.00 240.00
70 pcs Iron Rods (10mm) 258.00 18,000.00
Total P 127,510.00
EQUIPMENT AND FACILITIES
The following is a summary of materials that are needed for the project. The amounts represented
below are to be used as an estimate only.
LABOR
5 foreman x P500.00 per day = P2,500.00 x 30 days = P 75,000.00
SNACKS
5 foreman x P50.00 per day = P250.00 x 30 days = P 7,500.00
Total Labor and Snacks P 82,500.00
Total P 210,010.00
BUDGET 7
The estimated amount for constructing a comfort room is P210,010.00. This value is spent on the
materials including labor.
The amount of P127,510.00 is divided into the following materials: PVC Door (60 x 210) P
1,940.00; Hollow Blocks P 20,000.00; Cement P21,000.00; Tiles P2,700.00; Ceramic tile adhesive
P1,200.00; Enamel (paint) P1,150.00; Flat (paint) P920.00; Toilet Bowls P18,000.00; Male Urinal
P8,000.00; Sinks (faucet included) P13,000.00; Wall Mirrors P2,400.00; LED tube lamps
P1,900.00; Exhaust fan P2,000.00; Hygienic Spray P3,000.00; Pail P100.00; Dipper P40.00; Trash
Bins P180.00; Coco Lumber (2x2) P2,500.00; Plywood (1/4) P1,500.00; Plywood (3/4) 1,600.00;
Gravel and Sand P6,000.00; Nail P140.00; Tire Wires P240.00; Iron Rods (10mm) P18,000.00.
The figures P82,500.00 is the estimated amount for the labor and snacks. Labor cost is P500.00
per day with five laborers for thirty days amounting to P75,000.00 and snacks for P50.00 each day
for the total amount of P7,500.00