PROJECT NAME: DISMANTLING AND INSTALLATION OF THERMOPLASTIC ROOFING AND SIDINGS OF MULTI-PURPOSE AREA
PROJECT LOCATION: PHIVIDEC IND'L ESTATE, SAN MARTIN, VILLANUEVA, MISAMIS ORIENTAL
OWNER: SAN MARTIN MANUFACTURING CORPORATION
PROJECT DURATION: 4 CALENDAR DAYS
PROJECT AMOUNT ₱ 35,000.00
RELATIVE
SCOPE OF WORK COST OF LABOR DAY 1 DAY 2 DAY 3 WEEK 4
WEIGHT (%)
100.000
1. REMOVAL OF EXISTING G.I. ROOFING, 94.983
SIDINGS AND BENDED 19,782.609 56.522 18.84 18.84 18.84 84.949
89.966
81.075
77.200
2. PAINTING OF FRAMING
3. INSTALLATION OF THERMOPLASTIC
ROOFING 7,237.403 20.678 6.89276 6.89276
51.467 6.89276
4. INSTALLATION OF THERMOPLASTIC
SIDING 2,712.165 7.749
25.733
3.87452 3.87452
5. INSTALLATION OF THERMOPLASTIC
FLASHING/FULLTEKSCREW 5,267.823 15.051 5.02 5.02 5.02
TOTAL COST 35,000 100
25.73 25.73 25.73 3.87 3.87 5.02 5.02 5.02
Daily Accomplishment (%)
25.73 51.47 77.20 81.07 84.95 89.97 94.98 100.00
9,006.67 9,006.67 9,006.67 1,356.08 1,356.08 1,755.94 1,755.94 1,755.94
Daily Accomplishment (₱)
9,006.67 18,013.34 27,020.01 28,376.09 29,732.18 31,488.12 33,244.06 35,000.00
1 25.733
2 51.467
3 77.200
4 81.075
5 84.949
6 89.966
7 94.983
8 100.000
S-CURVE