Proposal for
Commercial Solar Rooftop PV Plant
              For
    1 MW on-grid system
To,
Jignesh bhai
GRV Spintex Pvt Ltd
Executive Summary
Alfa energy offers end to end solar EPC solutions, grid-connected solar PV
systems, off-grid solar PV systems, solar power plants, rooftop solar PV systems
as well as integrated PV systems. Our experience of engineering and installing
high quality solar power systems and our uncompromising service is what makes
us a strong player. As a professional solar photovoltaic system supplier, we
monitor the project closely; provide on-time delivery, and accountability
throughout the life of the system.
Alfa energy is approaching Jignesh bhai with a proposal of installation and
commissioning of rooftop solar power plant system at their Padadhari campus.
Based on discussions and site survey, we are proposing a complete solution for
1MW solar PV system. The solution includes high-quality products, installation
and      commissioning        services     and      maintenance       support
1 Project Highlights
Based on site survey and electricity usage analysis from electricity bill, it is
suggested to install 1MW of solar PV system on the rooftop of commercial
building campus of Jignesh bhai
Below is high-level detail of the project:
Client Name                         Jignesh bhai
Project Capacity                    1 MW
Project Type                        On-grid solar rooftop PV plant
Generation of energy                5-6 units per day per KW
Required Area / Floor space         Approx. 3 acre
Area to be installed                Rooftop
Location                            Morbi
 2 System Design
Detailed system design will be done after carefully taking technical parameters into
consideration once the project is finalized; however, following is the list of proposed system
components and their specifications for the solar power plant:
       Item                      Description                      Make            Quantity
                        Poly Crystalline PV modules of
  Solar PV Module                  335 Wp                        Waaree/
                                                                                   3,000
                          5 years product warranty              Goldigreen/
                                                                                  modules
                       25 years performance warranty            Redren
                                 1MW Capacity
     On – grid                                               POLYCAB / ABB
                               Efficiency > 98%
      Inverter                                                   / Delta /          1 No.
                       5 years manufacturer warranty             waree
     Module
                             ISI approved GI Pipe
     Mounting                                                                        As
                         120 kmph wind load Capable                N.A.           Required
     Structure
                                                                                   As Per
                       IP 65 Junction box with required
       DCDB                                                 Industry Standard      Design
                            switch gear protection
                                                                                   As Per
                       IP 65 Junction box with required
       ACDB                                                 Industry Standard      Design
                            switch gear protection
                        ISI approved AC and DC cables
                      Cabling will be encapsulated in PVC       POLYCAB          As Required
  Wires / Cables
                                         pipes
    Earthing kit              Chemical Earthings            Industry Standard As per design
     Lightning                                                                     As per
                     Surge protection & lightning devices Industry Standard
     arrestor                                                                      design
3 Scope of Work
Feasibility Study:
   -   Alfa team shall survey the site and measure the available floor / roof
       space suitable for pv modules installation.
   -   The Electrical layout of the Building site will be properly studied and also needed
       information will be checked.
   -   Application for approval of project to respective authorities
Design:
   -   SSPL team shall suitably design the system to optimize the system performance and
       Client’s investment.
   -   Basic civil structure and mounting structure will be designed.
Installation:
   -   Documents submission for registration of the plant and subsidy
   -   Installation of Mounting structures
   -   Installation of PV Modules on Mounting structures, cabling & wiring to connect
       Modules to Inverters, connection of inverters to Inter- connection point, connection
       of Inverters.
   -   Installation of protection devices like SPD, Lightning arrestors, etc
       wherever required.
   -   Termination of Inverter Connections at Distribution Panel
Commissioning:
   -   Test report preparation and submission
Training of Personnel:
   -   SSPL team will train the Personnel / team nominated by the Client for
       maintaining the Plant on day to day basis and to handle emergency situations.
Notes:
   -   Customer will appoint a single point of contact person for all tasks related to
       installation and commissioning of the project. Permission to the building rooftop,
       arranging necessary approvals at customer end, decisions about placing of
       equipments and any other help required will be his responsibility.
   -   Arranging the accessibility to the roof is customer’s responsibility.
   -   Any civil work required additionally other than mentioned in this proposal will
       be customer’s responsibility.
 4 Quotation
                      Installation and commissioning of solar rooftop solar plant
 Price per KW                                                                             40,000
 System Size (KW)                                                                       1000 KW
 Final System Cost                                                                   4,00,00,000
Payment Terms:
    Price is exclusive of applicable taxes (5%)
      Transportation will be borne by customer as per actual
      Payment schedule:
          o 25% Advance Upon award of Contract
          o 50 % against dispatch of material
          o 25% Complete the inspection (throughout power on grid)
      The Proposal is valid for 30 days from the date of issue
      Any charges levied by DISCOM, Electrical Inspector and Nodal Agencies will
       be borne by the customer as per Actual
      All cheques / DDs are to be in favor of “Alfa energy, payable
       at Rajkot
5 ROI Calculation
Below table provides an estimation of return of investment from the project:
Unit Generation Estimate
•     Daily solar generation for 1 MW – 4,444 units
•     Monthly solar generation for 1 MW – 1,33,333 units
•     Yearly solar generation for 1 MW – 16,00,000 units
Pay-Back Period
    o Approx. 2.5-3 years (will be shorter if CFA is availed) Notes:
    o The generation of power is dependent on the environment conditions.
      Day to day generation might vary.
 6 Project Schedule
Below figure gives an idea of the project schedule:
                                          •Project Approval from Nodal Agency/DISCOM
         Govt Approvals                   •Usually 2-3 weeks
        Project Design /                  •Accurate design of sytem based on site conditions
                                          •Initiate material movement and deliver to
        Material Delivery                 customer •3-4 weeks
                                          •Civil work, module mounting, wiring and earthing
           Installation                    if required
                                          •3-4 weeks
                                          •Test reports and CEI approval
         Commissioning                    •Net/Bi-directional meter installation by
                                          Discom •GEDA/MNRE Approval
Notes:
        SSPL requires all documents duly signed by customer in order to submit
         the applications respective authorities.
        The installation of project depends on the size of the project and
         availability of material.
        Inspections from CEI and installation of net/bidirectional meter from
         Discom is done by respective authorities. Hence SSPL does not guarantee
         the timelines for the same.
7 Terms and Conditions
  All standard manufacturer warranties shall be transferred to the Client
  Govt. Charges for registration of the project for the subsidy will be charged
   extra
  SSPL shall raise Invoice to the Client as per registration of project.
  Company works under corporate ethics “Beneath it All”. Please refer in case of
     any query.
 
     Customer should not default in payment terms as per agreement,
     otherwise bank interest would be charged after credit period.
    Delay in project execution due to customer or act of God will not be waived.
    SPP contains electronics parts, to be operated in SOC (Standard Operating
     Conditions), defaulting such may result in withdrawal of warranty or termination
     of Service Contract.
    System Specifications may vary due to continuous development in Technology.
    8x6 technical support provided from Alfa energy
 8 Benefits of proposed solution
Some of the advantages of the proposed solar PV solution are as below:
   -   Reduce your electricity bill
   -   TAX Depreciation Benefits
   -   Its clean and green energy
   -   Minimal Operating cost
   -   Long term energy generation
   -   Reliable and safe
   -   Good amount of savings in electricity bills with net metering
   -   Tax Depreciation benefits from State & Central government
   -   Short term payback period
   -   Green Energy / Renewable energy