INDIRECT COST ESTIMATION
Project :
Variable:         >    WAGES AND SALARIES:
Fixed:            >    OFFICE EXPENSES:
                  >    SITE INSTALLATIONS:
                  >    OPERATION OF SITE INSTALLATIONS
                  >    OTHER:
                                                           Total Fixed Indirects:
            Total Indirect = Fixed Indirect + Variable Indirects ($/Day) x Project Dur
WAGES & SALARIES
================
SUPERVISION
                          No.           Rate / Day
PROJECT MANAGER :          0        X      0.0     =   0
PROJ. SUPERINT. :          0        X      0.0     =   0
GEN. SUPERINT. :           0        X      0.0     =   0
ASS. SUPERINT.:            0        X      0.0     =   0
TRADE SUPOERINT.:          0        X      0.0     =   0
MASTER MECHANIC :          0        X      0.0     =   0
ASSIST. MECHANIC :         0        X      0.0     =   0
OTHER:                     0        X      0.0     =   0
OTHER:                     0        X      0.0     =   0
                                        TOTAL =        0         Back
ENGINEERING
                          No.           Rate / Day
PROJECT ENGINEER:          0        X      0.0     =   0
OFFICE ENGINEER:           0        X      0.0     =   0
COST ENGINEER:             0        X      0.0     =   0
SCHEDULE ENGR. :           0        X      0.0     =   0
DESIGN ENGINEER:           0        X      0.0     =   0
FIELD ENGINEER:            0        X      0.0     =   0
ENGR. TECHNICIAN:          0        X      0.0     =   0
OTHER:                     0        X      0.0     =   0
OTHER:                    0    X      0.0    =    0
                                   TOTAL =        0          Back
OFFICE & CLERICAL
                         No.       Rate / Day
OFFICE MANAGER :          0    X      0.0     =   0
PERSONNEL MANGER:         0    X      0.0     =   0
PURCHASING AGENT:         0    X      0.0     =   0
ACCOUNTANTS:              0    X      0.0     =   0
PAYMASTER:                0    X      0.0     =   0
WAREHOUSE CHIEF:          0    X      0.0     =   0
GENERAL HELP:             0    X      0.0     =   0
EQUIPMENT CLERK:          0    X      0.0     =   0
OTHER:                    0    X      0.0     =   0
OTHER:                    0    X      0.0     =   0
                                   TOTAL =        0          Back
MEDICAL, SAFETY, & SECURITY
                         No.       Rate / Day
SAFETY SUPERVIS.:         0    X      0.0     =   0
FIRST AID MEN:            0    X      0.0     =   0
NURSES:                   0    X      0.0     =   0
SECURITY MEN:             0    X      0.0     =   0
WATCHMEN:                 0    X      0.0     =   0
OTHER:                    0    X      0.0     =   0
OTHER:                    0    X      0.0     =   0
                                   TOTAL =        0         Back
SALARIED STAFF EMPLOYEE BENEFITS
                               THIS ITEM COVERS :
                                -WORKMEN'S COMPENSATION
                                -SOCIAL SECURITY AND COMPANY PENSION PLAN
                                -UNEMPLOYMENT INSURANCE
                                -HEALTH AND WELFARE, GROUP INSURANCE
                                -VACATION AND HOLIDAY PAY
SUM OF CODES 9100, 9110, 9120, & 9130 =            0
                                PERCENT =       15.0           %(ADJUSTABLE)
                                         ---------------------
                                TOTAL =            0             Back
TRAVEL TIME PAY
   TRAVELLING EMP        No.       Rate / Day
                          0    X     0.0     =    0
                          0    X     0.0     =    0
                          0    X     0.0     =    0
                                                             Back
                              TOTAL =       0       Back
LABOR ADJUSTMENTS
                             THIS ITEM COVERS :
                              -SHIFT PREMIUMS
                              -HIGHT PREMIUMS
                              -UNDERGROUND PREMIUMS
                              -COMPRESSED AIR PREMIUMS
                              -PRODUCTION BONUS
                              -EQUIPMENT PREMIUM
                   ESTIMATE (LE/Day) =      0       Back
=============== END OF WAGES & SALARIES ESTIMATION ==================
OFFICE EXPENSES
====================
OFFICE EQUIPMENT AND SUPPLIES
                                         COST(LE)
        -FURNATURE & FURNASHINGS:          0.0
        -EQUIPMENT(e.g. COMPUTERS):        0.0
        -SUPPLIES & STATIONARY:            0.0
        -POSTAGE, POSTAGE MACHINES:        0.0
        -BADGES, TENCILS:                  0.0
        -PAYROLL & ACC. COMPUTER:          0.0
        -OTHERS:                           0.0
                              TOTAL =       0       Back
ENGINEERING EQUIPMENT AND SUPPLIES
                                         COST(LE)
        -SURVEYING EQUP. & SUPPLIES :      0.0
        -REPRODUCTION EQUP. & SUPPL.:      0.0
        -DRAFTING EQUP. & SUPPLIES :       0.0
        -COMPUTER EXPENSES:                0.0
        -PHOTOGRAPHIC EQUP. & SUPPL.:      0.0
        -CONSULTING, TESTING & INSP.:      0.0
        -OTHERS:                           0.0
                              TOTAL =       0       Back
LEGAL & PUBLIC RELATIONS
                                         COST(LE)
        -LEGAL FEES:                       0.0
        -AUDIT FEES:                       0.0
        -DONATIONS:                        0.0
        -PUBLIC RELATIONS:                 0.0
        -OTHERS:                           0.0
                                                    Back
                           T TOTAL =               0       Back
MEDICAL & SAFETY SUPPLIES
                                                COST(LE)
       -MEDICAL EXAMINATIONS     :                0.0
       -MEDICAL SUPPLIES     :                    0.0
       -SAFETY & WEATHER WEAR      :              0.0
       -SIGNS & BARRICADES     :                  0.0
       -FIRE PROTECTION SUPPLIES :                0.0
       -OTHERS:                                   0.0
                               TOTAL =             0       Back
EMPLYEE MOVE IN, MOVE OUT
                                                COST(LE)
       -HOURLY EMPLOYEES                :         0.0
       -SALARIED EMPLOYEES                  :     0.0
       -HEAD OFFICE VISITS      :                 0.0
       -EXECUTIVES         :                      0.0
       -FAMILY MOVE IN/OUT          :             0.0
       -OTHERS:                                   0.0
                               TOTAL =             0       Back
CATERING COST OR SUBSISTANCE
                                                COST(LE)
       -ROOM AND BOARD ALLOWANCE :                0.0
       -LIVING EXPENSES ALLOWANCE :               0.0
       -OTHERS:                                   0.0
                               TOTAL =             0       Back
NON-RECOVERABLE INSURANCE COSTS
       -INSURANCE CLAIMS (e.g. AUTO             COST(LE)
        INSURANCE)        :                       0.0
       -OTHERS:                                   0.0
                               TOTAL =             0       Back
INSURANCE, TAXES & BONDS
                                                COST(LE)
       -INSURANCE           :                     0.0
       -TAXES (PROPERTY, BUISENESS):              0.0
       -BONDS (PERFORMANCE)      :                0.0
       -EQUIPMENT TAXES        :                  0.0
       -EQUIP. & VEHICLE LICENCE :                0.0
       -OTHERS:                                   0.0
                               TOTAL =             0       Back
                                                       Back
COMMUNICATION EXPENSES
                                           COST(LE)
        -RENTAL OF TELEPHONE, TELEX :        0.0
        -LONG DISTANCE CHARGES     :         0.0
        -TELEGRAPH CHARGES       :           0.0
        -TELEX, FAX LINE CHARGES :           0.0
        -OTHERS:                             0.0
                              TOTAL =         0        Back
FRIGHT EXPENSES
                                           COST(LE)
        -FRIGHT AND EXPRESS COST       :     0.0
        -HANDLING, PACKING    :              0.0
        -OTHERS:                             0.0
                              TOTAL =         0        Back
MISCELLANEOUS
                                           COST(LE)
        -SPECIAL GROUP PARTIES     :         0.0
        -ENTERTAINMENT         :             0.0
        -YARD, OFFICE RENTALS    :           0.0
        -DUES, LICENCES, PERMITS :           0.0
        -OTHERS:                             0.0
                              TOTAL =         0        Back
=============== END OF OFFICE EXPENSES     ==================
SITE INSTALLATIONS
=================
EQUIPMENT ASSEMBLY & ERECTION
        -COST OF ASSEMBLY OF PROJECT       COST(LE)
         EQUIPMENT..................         0.0
CONSTRUCTION OF NON-PAY ROADS & YARDS
                                           COST(LE)
        -CONSTRUCTION OF SITE HAUL :         0.0
        -PREPARATION OF CAMP SITES,
         YARD AREAS, & STORAGE SITES:        0.0
        -CONSTRUC. OF DOCKS, PIERS
         LOADING PLATFORMS, etc. :           0.0
        -CONSTRUCTION OF FENCES :            0.0
        -OTHERS:                             0.0
                              TOTAL =         0        Back
                                                     Back
PROJECT BUILDING ERECTION & DISMANTLE
                                          COST(LE)
        -OFFICE, WAREHOUSE, etc. :          0.0
        -CAMP AND HOUSE TRAILERS :          0.0
        -WORKSHOPS           :              0.0
        -EXPLOSIVES MAGAZINES      :        0.0
        -WORK PLATFORMS         :           0.0
        -MATERIAL WEIGH SCALES      :       0.0
        -OTHERS:                            0.0
                             TOTAL =         0       Back
SERVICES INSTALLATION & REMOVAL
                                          COST(LE)
        -WATER SYSTEM          :            0.0
        -SEWAGE SYSTEM           :          0.0
        -DRAINAGE SYSTEM          :         0.0
        -AIR SUPPLY AND DISTRIBUTION:       0.0
        -HEATING AND DISTRIB. SYSTEM:       0.0
        -STANDBY GENERATORS           :     0.0
        -POWERLINES,LIGHTING SYSTEM:        0.0
        -ELECTRICAL HOOK UPS        :       0.0
        -COMMUNICATIONS INSTALLATION:       0.0
        -OTHERS:                            0.0
                             TOTAL =         0       Back
SHOP EQUIPMENT & SHOP TOOLS
        -PURCHASE AND INSTALLATION OF
         SHOP TOOLS INCLUDING
         HOISTS,WINCHES, JACKS,           COST(LE)
         POWER TOOLS, SMALL TOOLS, etc.     0.0
        -OTHERS:                            0.0
                             TOTAL =         0       Back
FINAL CLEAN UP
        -COST OF LABOR, EQUIPMENT,OR      COST(LE)
         MATERIAL TO CLEAN UP THE SITE      0.0
        -OTHERS:                            0.0
                             TOTAL =         0       Back
=============== END OF SITE INSTALLATION ESTIMATE ==================
OPERATION OF SITE INSTALLATIONS
==============================
ROAD & YARD MAINTENANCE
       -COST OF SURFACE, DRAINAGE     COST(LE)
        MAINTENANCE, AND DUST CONTROL   0.0        Back
PROJECT OPERATION & MAINTENANCE
                                        COST(LE)
       -TRAILOR LOT RENTALS       :       0.0
       -BUILDING REPAIRES & MAINT. :      0.0
       -BUILDING INTERNAL SERVICES :      0.0
       -JANITORIAL SERVICES     :         0.0
       -GARBAGE PICK-UP       :           0.0
       -FUEL SUPPLY         :             0.0
       -OTHERS:                           0.0
                             TOTAL =       0       Back
SERVICES, OPERATION & MAINTENANCE
     COST TO OPERATE AND MAINTAIN       COST(LE)
      -WATER SYSTEM          :            0.0
      -SEWAGE SYSTEM           :          0.0
      -DRAINAGE SYSTEM          :         0.0
      -AIR SUPPLY AND DISTRIBUTION:       0.0
      -HEATING AND DISTRIB. SYSTEM:       0.0
      -STANDBY GENERATORS           :     0.0
      -POWERLINES,LIGHTING SYSTEM:        0.0
      -ELECTRICAL HOOK UPS        :       0.0
      -COMMUNICATIONS INSTALLATION:       0.0
      -OTHERS:                            0.0
                             TOTAL =       0       Back
INDIRECT TRANSPORTATION
       -PICKUPS, CREW-CABS, CREW-       COST(LE)
        TRANSPORT, CREW BUSES, etc.:      0.0
       -OTHERS:                           0.0
                             TOTAL =       0       Back
WAREHOUSE OPERATIONS
                                        COST(LE)
       -VEHICLE AND DRIVER         :      0.0
       -PICK UP SERVICES      :           0.0
       -YARD EQUIPMENT         :          0.0
       -OTHERS:                           0.0
                             TOTAL =       0       Back
SERVICE & MAINTENANCE EQUIPMENT
                                        COST(LE)
        -SHOP SUPPLIES (e.g. BOLTS) :       0.0
        -WELDING SUPPLIES       :           0.0
        -GENERAL SHOP LABOUR        :       0.0
        -OTHERS:                            0.0
                              TOTAL =        0       Back
EXPENDABLES
        -COST OF MACHINE ATTACHEMENTS
         THAT UNDERGO WEAR (e.g. BITS, COST(LE)
         CUTTING EDGES, etc.  :          0.0
ELECTRICAL POWER CHARGES
                                          COST(LE)
                    TOTAL ESTIMATED =       0.0      Back
PROJECT SMALL TOOLS
        -ITEMS OF INDIVIDUAL PURCHASE     COST(LE)
         OF LESS THAN $2000 EACH. :         0.0
        -COST OF AXES, NAILERS, PIPE
         BENDERS, STAPLERS       :          0.0
        -OTHERS:                            0.0
                              TOTAL =        0       Back
=============== END OF OPERATION OF SITE INSTALLATION ==================
OTHERS
=======
FINANCING
        -COST OF FINANCING THE JOB CALCULATED
         AT CURENT INTEREST COST ON TH COST(LE)
         YEARLY INVESTED CAPITAL    :     0.0
HEAD OFFICE SUPPORT
        -CONTRIBUTION TO MAINTENANCE      COST(LE)
         HEAD OFFICE FACILITIES & STAFF     0.0      Back
ESCALATION
                                          COST(LE)
                              -VALUE:       0.0
CONTINGENCIES
        -ESTIMATED COST OF INTERFER-
         ENCES INCLUDING; FLOODS, STRIK COST(LE)
         TAX INCREASE, EARTHQUAKES :      0.0
BONUS OR PENALTY
                                       COST(LE)
                            -VALUE:      0.0         Back
=============== END OF ESTIMATION OF OTHER COSTS ==================
ESTIMATION
                              0          LE / Day
Total Fixed Indirects:        0          LE
e Indirects ($/Day) x Project Duration
      Back
      Back
      Back
      Back
ND COMPANY PENSION PLAN
ARE, GROUP INSURANCE
     %(ADJUSTABLE)
       Back
      Back
      Back
      Back
ATION ==================
      Back
      Back
      Back
Back
Back
Back
Back
Back
Back
      Back
      Back
      Back
      Back
============
      Back
      Back
      Back
      Back
      Back
      Back
TE ==================
Back
Back
Back
Back
Back
      Back
      Back
      Back
LATION ==================
      Back
       Back
TS ==================
\C
MESG1
FILE2
FULL
REP
QTIT
QUITY
CONTMESG
PRNT
\0
SUB2
MENU1
NEWLY
                         INDIRECT COSTS
WAGES & SALARIES                          OFFICE EXPENSES                         SITE INSTALLATIONS
SUPERVISION                               OFFICE EQUIPMENT AND SUPPLIES           EQUIP. ERECTION
          PROJECT MANAGER :                      -FURNATURE & FURNASHINGS:
          PROJ. SUPERINT. :                      -EQUIPMENT(e.g. COMPUTERS):      NON-PAY ROADS & YARDS
          GEN. SUPERINT. :                       -SUPPLIES & STATIONARY:
          ASS. SUPERINT.:                        -POSTAGE, POSTAGE MACHINES:
          TRADE SUPOERINT.:                      -BADGES, TENCILS:
          MASTER MECHANIC :                      -PAYROLL & ACC. COMPUTER:
          ASSIST. MECHANIC :              ENGIN. EQUIPMENT AND SUPPLIES
ENGINEERING                                      -SURVEYING EQUP. & SUPPLIES :
          PROJECT ENGINEER:                      -REPRODUCTION EQUP. & SUPPL.:    BUILDING ERECTION & DISMANTLE
          OFFICE ENGINEER:                       -DRAFTING EQUP. & SUPPLIES :
          COST   ENGINEER:                       -COMPUTER EXPENSES:
          SCHEDULE ENGR. :                       -PHOTOGRAPHIC EQUP. & SUPPL.:
          DESIGN ENGINEER:                       -CONSULTING, TESTING & INSP.:
          FIELD ENGINEER:                 LEGAL & PUBLIC RELATIONS
          ENGR. TECHNICIAN:                      -LEGAL/AUDIT FEES:
OFFICE & CLERICAL                                -DONATIONS / PR:                 SERVICES INSTALL. & REMOVAL
           PERSONNEL MANGER:              MEDICAL & SAFETY SUPPLIES
           PURCHASING AGENT:                     -MEDICAL EXAMINATIONS:
           ACCOUNTANTS:                          -MEDICAL SUPPLIES:
           PAYMASTER:                            -SAFETY & WEATHER WEAR:
           WAREHOUSE CHIEF:                      -SIGNS & BARRICADES:
           GENERAL HELP:                         -FIRE PROTECTION SUPPLIES:
           EQUIPMENT CLERK:               EMPLYEE MOVE IN, MOVE OUT
MEDICAL & SAFETY                                 -HOURLY EMPLOYEES:
           SAFETY SUPERVIS.:                     -SLARIED EMPLYEES:
           FIRST AID MEN:                        -HEAD OFFICE VISITS\:            SHOP EQUIP. & SHOP TOOLS
           NURSES:                               -EXECUTIVES:
           SECURITY MEN:                         -FAMILY MOVE IN/OUT:
EMPLOYEE BENEFITS                         CATERING COST                           FINAL CLEAN UP
           -WORKMEN'S COMPENS.                   -ROOM AND BOARD ALLOWANCE:
           -SOCIAL SEC. & PEN. PLAN              -LIVING EXPENSES ALLOWANCE:
           -UNEMPLOYMENT INS.             NON-RECOVERABLE INS. COSTS
           -HEALTH, WELFARE, GROUP INS.          -INSURANCE CLAIMS (e.g. AUTO):
           -VACATION AND HOLIDAY PAY      INSURANCE, TAXES & BONDS
TRAVEL TIME PAY                                  -INSURANCE:
           TRAVELLING EMPLOYEES                  -TAXES (PROPERTY, BUISENESS):
LABOR ADJUSTMENTS                                -BONDS (PERFORMANCE):
           -SHIFT PREMIUMS                       -EQUIPMENT TAXES:                OTHERS
           -HIGHT PREMIUMS                       -EQUIP. & VEHICLE LICENCE:       ===================================
           -UNDERGROUND PREMIUMS          COMMUNICATION EXPENSES                  FINANCING
           -COMPRESSED AIR PREMIUMS              -LONG DISTANCE CHARGES:
           -PRODUCTION BONUS                     -TELEX, FAX LINE CHARGES:
           -EQUIPMENT PREMIUM             FRIGHT EXPENSES
                                                 -FRIGHT AND EXPRESS COST:        HEAD OFFICE SUPPORT
                                                 -HANDLING, PACKING:
                                          MISCELLANEOUS
                                                 -PARTIES / ENTERTAINMENT:
                                                 -DUES, LICENCES, PERMITS:
                                                 -YARD, OFFICE RENTALS:
                                INDIRECT COSTS (Cont.)
SITE INSTALLATIONS                        OPERATION OF SITE INSTALLATIONS
EQUIP. ERECTION                           ROAD & YARD MAINTENANCE
                                                     -COST OF SURFACE MAINTENANCE
NON-PAY ROADS & YARDS                                DUST CONTROL, SNOW REMOVAL,
          -CONSTRUCTION OF SITE HAUL:                DRAINAGE MAINTENANCE:
          -PREPARATION OF CAMP SITES,     PROJECT OPERATION & MAINT.
           YARD AREAS, & STORAGE SITES:              -TRAILOR LOT RENTALS:
          -CONSTRUC. OF DOCKS, PIERS                 -BUILDING REPAIRES & MAINT. :
           LOADING PLATFORMS, etc.:                  -BUILDING INTERNAL SERVICES :
          -CONSTRUCTION OF FENCES:                   -JANITORIAL SERVICES:
BUILDING ERECTION & DISMANTLE                        -GARBAGE PICK-UP:
          -OFFICE, WAREHOUSE, etc.:                  -FUEL SUPPLY :
          -CAMP AND HOUSE TRAILERS:       SERVICES, OPERATION & MAINT.
          -WORKSHOPS:                                -WATER SYSTEM :
          -EXPLOSIVES MAGAZINES:                     -SEWAGE SYSTEM :
          -WORK PLATFORMS:                           -DRAINAGE SYSTEM:
          -MATERIAL WEIGH SCALES:                    -AIR SUPPLY AND DISTRIBUTION:
SERVICES INSTALL. & REMOVAL                            -HEATING AND DISTRIB. SYSTEM:
           -WATER SYSTEM:                              -STANDBY GENERATORS:
           -SEWAGE SYSTEM:                             -POWERLINES,LIGHTING SYSTEM:
           -DRAINAGE SYSTEM:                           -ELECTRICAL HOOK UPS:
           -AIR SUPPLY AND DISTRIBUTION:               -COMMUNICATIONS INSTALLATION:
           -HEATING AND DISTRIB. SYSTEM:    INDIRECT TRANSPORTATION
           -STANDBY GENERATORS:                        -PICKUPS, CREW-CABS, CREW-
           -POWERLINES,LIGHTING SYSTEM:                 TRANSPORT, CREW BUSES, etc.:
           -ELECTRICAL HOOK UPS:            WAREHOUSE OPERATIONS
           -COMMUNICATIONS INSTALLATION:               -VEHICLE AND DRIVER:
SHOP EQUIP. & SHOP TOOLS                               -PICK UP SERVICES:
           -PURCHASE / INSTALL. OF HOISTS,             -YARD EQUIPMENT:
            SMALL TOOLS, WINCHES, JACKS, etcSERVICE & MAINT. EQUIPMENT
FINAL CLEAN UP                                         -SHOP SUPPLIES (e.g. BOLTS) :
           -COST OF LABOUR, EQUIP.,OR MATERIAL         -WELDING SUPPLIES:
           TO CLEAN UP THE SITE AT COMPLETION          -GENERAL SHOP LABOUR:
                                            EXPENDABLES
                                                       -COST OF MACHINE ATTACHEMENTS
                                                        THAT UNDERGO WEAR (e.g. BITS)
                                            ELECTRICAL POWER CHARGES
                                            PROJECT SMALL TOOLS
=========================================================================
FINANCING                                ESCALATION
          -COST OF FINANCING THE JOB
           CALCULATED AT CURENT RATE     CONTINGENCIES
                                                   -ESTIMATED COST OF INTERFER-
HEAD OFFICE SUPPORT                                 ENCES INCLUDING; FLOODS, STRIKES,
          -MONTHLY OR % CONTRIBUTION                TAX INCREASE, EARTHQUAKES :
           TO MAINTENANCE OF HEAD
           OFFICE FACILITIES & STAFF :   BONUS OR PENALTY