Construction Cost Of
5 Marla Grey Structure
Item Quantity Rate Cost Unit
Bricks,Sand ,Crush & Rori
Bricks 50,000 10.50 525,000 Nos.
Sand 3,850 35.00 134,750 Cft
Crush 1,500 48.00 72,000 Cft
Rori 1 25,000 25,000 -
Sub-Total 756,750
Cement,Kasu & Steel
Cement 525 570.00 299,250
Steel 3 120,000 360,000
Kasu 1 50,000 50,000
Sub-Total 709,250
Plumbing & Wiring
Plumbing 2,000 40.00 80,000
Wiring 2,000 17.50 35,000
Sub-Total 115,000
Grill ,Gate & Chougat
Chougat (M.S) 50,400
Grill 190.00 57,000
Gate 800.00 60,000
Sub-Total 167,400
Labour
Labour 2,125 320.00 680,000
Sub-Total 680,000
Others
Misc. - 50,000
Sub-Total 50,000
Total Estimated Cost Rs:- 2,478,400
Construction Cost Of
5 Marla Finishing Work
Item Quantity Rate Type Cost Unit
Bricks,Sand ,Crush & Rori
Tiles Floor 180 1,600 Master 288,000
Bath Tiles 76 1,600 Master 121,600
Terrace Tiles 18 1,500 Master 27,000
Porch Tiles 21 1,500 Master 31,500
Stairs Marble - - - 55,000
Kitchen Shelves - - - 30,000
Labour - - - 115,000
Sub-Total 668,100
Electrical
Lights 150 250.00 China A+ 37,500
Fans 11 6,500 Royal/GFC 71,500
Switch Boards 20 1,150 OPAL 23,000
Power Plugs 18 575.00 OPAL 10,350
Exaust Fans 6 2,500 Royal/GFC 15,000
Braker/DB - - 30,000
Sub-Total 187,350
Kitchen & Bath Accessories
Hood 2 45,000 - 90,000
Sink 2 10,000 - 20,000
Vanity 4 9,000 - 36,000
Commodes 4 14,000 - 56,000
Bath Set 3 19,000 - 57,000
Bath Hangings 4 5,000 - 20,000
Sub-Total 279,000
Paint & Ceilling
Ceilling 2125 65 - 138,125
Paint - - - 30,000
Rockwall/Exterior - - - 300,000
Sub-Total 468,125
Windows & Mirrors
Windows Aluminum + Glass - - - 165,000
Mirrors - - - 20,000
Stairs Railling - - - 40,000
Sub-Total 225,000
Woodwork
Doors - - 1 semi solid rest arine ply 120,000
Wardobes - - UV Ply Sheets 144,000
Kitchen woodwork - - UV Ply Sheets 120,000
Door Handle - - - 20,000
Sub-Total 404,000
Total Estimated Cost Rs:- 2,231,575