RESPONSIBILITY MATRIX
“X” denotes the party responsible for the item of works.
                                                                    PARTY RESPONSIBLE
                                                                      FOR ITEMS OF
   S/N                         ITEM OF WORKS                             WORKS           REMARKS
                                                                    Works    Works By
                                                                    By TPL     SC
     A                                            SITE OFFICE AND TEMPORARY BUILDINGS
          Identify and allocate space for construction of
    A1                                                                X
          temporary offices and store for the SC.
          Provide, erect, maintain and remove the temporary
    A2                                                                          X
          office and stores for the SC
          Telecommunication facilities
    A3        Internet                                                         X
              Telephone
    A4    Power and electricity to SC offices and stores              X
    A5    Drinking water in site offices of SC                                  X
    A6    Accommodation for workers of SC                             X
   A7     Drinking water for workers at site                                    X
     B                                    UTILITIES, SCAFFOLDS, PLANTS AND MACHINERIES
   B1     Supply of temporary general area lighting                   X
          All Safety protection equipment such as PPE, Safety
          harness, Safety belt, life line rope, shoulder pads,
    B2                                                                          X
          hand gloves and goggles etc. as per Safety
          guideline specified in tender documents.
    B3    Provide scaffolding materials ( if required)                          X
          Ensuring all deployed machineries age below 5
    B4
          years
                                                                                X
   D                                                        LABOUR WELFARE
          Rest room, Mess-rooms, sanitary and welfare
    D1                                                                X
          facilities at worker colony and hard-standings, etc
    D2    Compliances                                                           X
    D3    Transport off site                                                    X
    D4    First aid facility at site                                  X         X
Role & Responsibility Matrix                          Page 1 of 4
                                                                 PARTY RESPONSIBLE
                                                                   FOR ITEMS OF
   S/N                       ITEM OF WORKS                            WORKS                       REMARKS
                                                                 Works     Works By
                                                                 By TPL      SC
     E                                  CO-ORDINATION AND INTERFACING OF WORKS
         Preparation of As-built drawings and resolving any
    E1   discrepancies and inconsistencies with the                           X                        .
         Contractor and other SCs
         Provide competent full time qualify                                          The proposed team structure shall
    E2   ed Project Manager and required staff on site for                    X          be submitted to the TPL for
         the proper coordination and supervision.                                                approval.
                                                                                         SC to submit their respective
    E3   Preparation and submission of progress reports                       X
                                                                                         progress reports to the TPL.
    E4   Survey works as per technical specifications.                        X         TPL will provide drawings only.
         Covering and protecting against all loss, breakages
         and/or damage to all executed and partly executed
    E5   Sub-Contract works which are incorporated into                       X
         the Main Contract Works including rectifying and
         replacing all damaged works, goods or materials
         Taking full responsibility for any loss of, or damage
         to his own materials, plant, tools and equipment
         which are not incorporated in the Main Contract
    E6                                                                        X
         Works including covering and protection against
         corrosion, all loss or damage, inclement weather,
         etc during storage and erection at the site
     F                                                       CLEANING UP
                                                                              X
    F1   Housekeeping / cleaning up                                                   To clean-up during working in areas
    F2   Final cleaning up                                                    X
         De-watering including slush removal & disposing
    F3   outside the site premise with required machinery,                    X
         pumps, tools & tackles
         Providing central disposal areas and dispose debris                          To clear and dump debris at central
    F4                                                                        X
         off site                                                                                disposal areas.
     G                                                        INSURANCES
                                                                   X
    G1   Contract or All Risk Policy
    G2   Workmen Compensation Insurance Policy                     X
         Insurance policies for Plant / Machinery as may be
    G3                                                                        X
         specifically stipulated and required
Role & Responsibility Matrix                       Page 2 of 4
                                                                 PARTY RESPONSIBLE
                                                                   FOR ITEMS OF
   S/N                     ITEM OF WORKS                              WORKS                        REMARKS
                                                                 Works     Works By
                                                                 By TPL      SC
     H                                                         OTHERS
    H1   Royalty/Mines
         Disposal of unserviceable excavated material from
    H2                                                                           X
         site premises for any lead.
         Deploying Man & Machinery as per the Project
    H3                                                                           X
         requirements
    H4   Site security                                             X                     TPL & SC to deploy security.
                                                                             X
                                                                                       The SC shall be liable for unsafe
                                                                                           work practices. Overall
    H5   Health Safety and Welfare                                               X    management/ responsibility of HSE
                                                                                              are with the TPL.
    H9   Dressing & compacting of loose soil up to PCC level                     X
     I                                        STATUTORY APPROVALS AND LIAISON
                                                                                      TPL shall obtain Labor License for
    I1   Labor license                                             X                  all workers on the site, including
                                                                                                those of the SC
    I2   PF,ESI & Bonus                                                          X
     J                                                         Materials
                                                                                        Wastages : Wastage allowed 1%
                                                                                      (concrete laying including concrete
    J1   Concrete Supply                                           X
                                                                                        pump or Boom Placer will be in
                                                                                                  Vendor Scope)
                                                                                        Wastages : Wastage allowed 2%
                                                                                         (cutting, bending, threading &
    J2   Reinforcement Supply                                      X
                                                                                        required machinery for all these
                                                                                       activities will be in Vendor scope )
    J3   Concrete Laying Activities                                              X
    J4   Bitumen                                                                 X
    J5   Materials other than concrete, reinforcement                            X
    J6   Safety PPE                                                              X
    J7   All Plant & Machinery other than Batching Plant                         X
    J8   POWER AND WATER                                           X
Role & Responsibility Matrix                     Page 3 of 4
                                                       PARTY RESPONSIBLE
                                                         FOR ITEMS OF
   S/N                   ITEM OF WORKS                      WORKS          REMARKS
                                                       Works    Works By
                                                       By TPL     SC
    J9   Hot Mix Plant                                             X
Role & Responsibility Matrix             Page 4 of 4