1. An inspection was conducted of balcony railings, drop visors, and unit squareness at various units. Several issues were found including railings being offset by up to 600mm, drop visors not being the correct height, and misalignments found along walls. 2. At Unit A, 25 points were inspected for squareness with 3 portions having different issues - the first 6 points were aligned correctly, points 7 and 12 were unplumbed, and points 14 and 22-25 required further work or had other problems. 3. For Unit V, a major misalignment was found from points 1 to 3 along the bedroom and living area walls, and the contractor will check their layout markers.

Uploaded by

vjh8bkmhqh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views1 page

Dar Dec 7

1. An inspection was conducted of balcony railings, drop visors, and unit squareness at various units. Several issues were found including railings being offset by up to 600mm, drop visors not being the correct height, and misalignments found along walls. 2. At Unit A, 25 points were inspected for squareness with 3 portions having different issues - the first 6 points were aligned correctly, points 7 and 12 were unplumbed, and points 14 and 22-25 required further work or had other problems. 3. For Unit V, a major misalignment was found from points 1 to 3 along the bedroom and living area walls, and the contractor will check their layout markers.

Uploaded by

vjh8bkmhqh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

DATE: DECEMBER 7, 2023

TWO REGIS
ACTIVITIES: ISSUES: REMARKS:

ARCHITECTURAL:
1.INSPECTION OF BALCONY RAILING OFFSET 400MM
AND ZOCALO AT 3RD FLR UNIT L 1. TOP OF RAILINGS: 599-600MM
2. BOTTOM AND MIDDLE OF RAILINGS:
534MM TO 530MM
3. ELEVATION FROM 1025MM: 1028MM
4. SPACING OFF SIDES AT 100MM`
5. OFFSET AT 598M TO 604MM
6. ZOCOLO WIDTH AT 100MM
2. INSPECTION OF DROP VISOR AT 2ND 1. ALL HEIGHT OF 6 POINTS 1850MM
FLOOR UNIT L
3. INSPECTION OF BALCONY RAILING OFFSET AT 400MM
- ZOCALO AT 3RD FLOOR UNIT K 1. FROM WALL TO EDGE OF ZOCALO AT
598 - 600MM
2. ZOCALO WIDTH AT 100MM
4. INSPECTION OF UNIT SQUARENESS NOTE: OFFSET AT 500MM AND 600MM, TOTAL OF
AT 3RD FLOOR UNIT A 1. POINT 11,15,16,17 - PREVIOUS 25 POINTS WITH 3 PORTION
CONTRACTOR ALREADY 1. PT 1- PT 6 - OKEY ALIGNMENT
APPLIED SKIMCOAT PRIOR TO 2. PT 7 - UNPLUMBED
UNIT SQUARENESS INSPECTION 3. PT 8 - PT 11 - OKEY ALIGNMENT
2. BALANCE MASONRY WORKS 4. PT 12 - UNPLUMBED
AT BEHIND DOOR DUE 5. PT 13 - OKEY ALIGNMENT
ELECTRICAL PVC PIPE NOT YET 6. PT 14 - UNPLUMBED AND NO CORNER
DONE BEAD
3. DOOR JAMBT TO TIGHT, DOOR 7. PT 15 - PT 17 - MISALIGNED
CAN’T CLOSE 8. PT 18 - PLASTERING NOT YET FINISH
9. PT 19 - PT 21 - OKEY
10. PT 22 - PT 25 - BALANCE AREAS
5. INSPECTION OF UNIT SQUARENESS 1. MAJOR MISALIGNMENT AT PT
AT 3RD FLOOR UNIT V 1 TO PT 3 ALONG BEDROOM TO
AND LIVING AREA,
CONTRACTOR WILL CHECK IF
THEIR MARKERS ARE
INCORRECT TO VERIFY WALL
SETTING LAYOUT