CHAPTER TWO
POWER SYSTEM STABILITY
Prepared by: Ismael Kareem Saeed
Oscillations in Two Area System
A mechanical analogy to this phenomenon can be visualized
in figure below. Suppose that there is a set of balls of different
sizes connected to each other by a set of strings. The balls
represent generators having a specific mechanical
characteristic (that is, inertia). The strings represent the
transmission line interconnecting the generators.
Prepared by: Ismael Kareem Saeed
Mechanical Analogy of Transient Stability
Now suppose that there is a disturbance in which one of the
balls is struck with a cue. The ball now begins to swing, and as
a result, the string connected to the ball also oscillates. In
addition, the other strings to which this string is connected
are also affected, and this in turn affects the other balls
connected to these strings. As a result, the entire
interconnected system of balls is affected, and the system
experiences oscillations in the strings and motion of the balls.
If these oscillations in the strings become large, one of the
strings may break away from the rest, resulting instability. On
the other hand if the oscillation dies down and the entire
system comes back to rest as in the situation prior to the ball
being struck. This condition is analogous to a power system
being “transiently stable”.
Prepared by: Ismael Kareem Saeed
The Swing Equation
The motion of the synchronous generator’s rotor is determined by
Newton's second law, which is given as:
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
inertia constant, or “H” constant
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
The power output of the machine is given by
The steady state stability limit of a generator or system can be defined
as the maximum power that can be transmitted for a slow change in
load.
If the change in excitation is assumed to be initiated immediately
following the change in load (as happens with automatic voltage
regulator action), the stability limit under such conditions may be
termed dynamic stability limit. The dynamic limit will, in general, be
higher than the steady state stability limit as defined above.
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
𝑥1 0
x 0 =
𝑥2 0
∆𝛿𝑜
∆𝛿𝑜
= =
𝑑∆𝛿𝑜
Prepared by: Ismael Kareem Saeed 0
𝑑𝑡
Prepared by: Ismael Kareem Saeed
A 50Hz synchronous generator having inertia constant
H=9.94 MJ/MVA and a transient reactance Xd`=0.3pu is
connected to an infinite bus through the following network.
The generator is delivering 1.0pu to the infinite bus at a
voltage 1 pu. Determine the power angle equation and swing
equation for the system applicable to the operating
conditions. Assume the damping power coefficient is D=0.138
pu. Consider a small disturbance of 10o or 0.1745 radians.
Obtain equations of rotor and generator frequency motion.
Prepared by: Ismael Kareem Saeed
Solution
The series reactance between the terminal voltage and the infinite
bus is
And therefore; the 1.0 pu power output of the generator is determined by
the power angle equation
So that the terminal voltage is
Prepared by: Ismael Kareem Saeed
Hence, the desired equation is
Prepared by: Ismael Kareem Saeed
The power angle equation is plotted. Note that the mechanical input power
Pm is constant and intersects the sinusoidal power angle curve at operating angle
o = 36.378o. The swing equation for the machine may be written
Under the operating condition
which corresponds exactly to the mechanical power input Pm and the
acceleration is zero.
To obtain the equations of rotor and generator frequency motion
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Hence, the equations of rotor and generator frequency motion
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Example:
A synchronous generator, capable of developing 500MW
of power, initially operates at a power angle of 8o. By how much
can the input shaft power be increased suddenly without loss of
stability?
Prepared by: Ismael Kareem Saeed
Solution:
Initially, at
Let be the power angle to which the rotor can swing before losing
synchronism. Then the equal-area criterion requires that the equation
which yields,
must be satisfied.
Prepared by: Ismael Kareem Saeed
From figure shown
Substituting
By trial and error method, yields
Hence, without loss of stability, the system can accommodate a sudden
increase of
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
The critical clearing time ,denoted tc ,is the longest fault
duration allowable for stability.
Prepared by: Ismael Kareem Saeed
Example
A 50 Hz generator is supplying 550 MW to an
infinite bus (with 1.0 per unit voltage and unity p.f)
through two parallel transmission lines. Determine
the critical clearing time for a temporary three-
phase-to-ground fault which shown in figure below.
H = 20 seconds.
Prepared by: Ismael Kareem Saeed
Solution
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
EXAMPLE:
The synchronous generator shown in figure is initially
operating in the steady-state condition, when a temporary
three-phase-to-ground bolted short circuit occurs on line 1-3
at bus 1, shown as point F in figure. Three cycles later the
fault extinguishes by itself. Due to a relay misoperation, all
circuit breakers remain closed. Determine whether stability is
or is not maintained and determine the maximum power
angle. The inertia constant of the generating unit is 3 per
unit-seconds on the system base. Assume Pm = 1 p.u and
remains constant throughout the disturbance. o = 23.95o =
0.4179 radian and f = 60 Hz. Also assume the infinite bus
receive 1 p.u real power at 0.95 p.f lagging.
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
SOLUTION:
Plots of Pe and Pm versus are shown in figure below.
Prepared by: Ismael Kareem Saeed
When the short circuit occurs, Pe instantaneously drops to
zero and remains at zero during the fault since power
cannot be transferred past faulted bus 1.
At t=3 cycles = 3/60 = 0.05 second,
Integrating twice with initial condition
Prepared by: Ismael Kareem Saeed
The accelerating area A1, shaded in figure is
Prepared by: Ismael Kareem Saeed
At t = 0.05 s the fault extinguishes and Pe instantaneously
increases from zero to the sinusoidal curve in figure.
continues to increase until the decelerating area A2 equals
A1. That is,
Prepared by: Ismael Kareem Saeed
The nonlinear algebraic equation can be solved iteratively to
obtain
Prepared by: Ismael Kareem Saeed
Solution:
𝑃𝑒 = 𝑃𝑚𝑎𝑥 sin(𝛿)
𝑃𝑚𝑒𝑐 = 𝑃𝑒 𝑎𝑡 𝛿𝑜
1 = 𝑃𝑚𝑎𝑥 sin(23.95)
𝑃𝑚𝑎𝑥 = 2.4638 pu
𝛿𝑚𝑎𝑥 = π − 23.95 = 156.050 = 2.7222 𝑟𝑎𝑑
1
𝛿𝑐 = 𝑐𝑜𝑠 −1 [ (2.7222-0.4179)+cos(156.05)]
2.4638
𝛿𝑐 = 88.776𝑜 𝑜𝑟 1.5494 𝑟𝑎𝑑
2∗3∗(1.5494−0.4179)
𝑡𝑐 = = 0.19 sec
𝜋∗60∗1
Prepared by: Ismael Kareem Saeed
3
𝑡(3 𝑐𝑦𝑐𝑙𝑒) = = 0.05 𝑠𝑒𝑐
60
∴ 𝑡𝑐 > 𝑡(3 𝑐𝑦𝑐𝑙𝑒)
Stability is maintained
Note: after 12 cycle , stability is losing from this system
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Transient Stability Analysis
For transient stability analysis we need to
consider three systems
1. Pre fault - before the fault occurs the
system is assumed to be at an equilibrium
point
2. During faulted - the fault changes the
system equations, moving the system away
from its equilibrium point
3. Post fault - after fault is cleared the system
hopefully returns to a new operating point
Prepared by: Ismael Kareem Saeed
Example
A 60 Hz generator is supplying 550 MW to an
infinite bus (with 1.0 per unit voltage and unity p.f)
through two parallel transmission lines. Determine
the critical clearing time for a fault midway down
one of the lines. H = 20 seconds.
Prepared by: Ismael Kareem Saeed
Solution
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Prepared by: Ismael Kareem Saeed
Further Considerations of the Swing Equation
In a stability study of a power system with many synchronous
machines only one MVA base common to all parts of the
system can be chosen. Since the right-hand side of the swing
equation for each machine must be expressed in per unit on
this common system base, it is clear that H on the left-hand
side of each swing equation must also be consistent with the
system base.
𝐻𝑠𝑦𝑠𝑡𝑒𝑚
𝑆𝑚𝑎𝑐ℎ
= 𝐻𝑚𝑎𝑐ℎ
𝑆𝑠𝑦𝑠𝑡𝑒𝑚
Prepared by: Ismael Kareem Saeed
In a stability study for a large system with many machines
geographically dispersed over a wide area it is desirable to
minimize the number of swing equations to be solved.
Machines which swing together are called coherent
machines.
Consider a power plant with two generators connected to the
same bus which is electrically remote from the network
disturbances. The swing equations on the common system
base are
Prepared by: Ismael Kareem Saeed
Adding the equations together and denoting 1 and 2 by
since the rotors swing together, we obtain
where H = ( H1 + H2 ), Pm = ( Pm1 + Pm2 ), and Pe = ( Pe1 + Pe2).
This fact is often used in stability studies involving many
machines in order to reduce the number of swing equations
which need to be solved.
Prepared by: Ismael Kareem Saeed
For any pair of noncoherent machines in a system swing
equations
Multiplying each side by H1 H2 / ( H1 + H2 ) and rearranging,
we find that
which also may be written more simply in the form of the
basic swing equation as follows:
Prepared by: Ismael Kareem Saeed
where δ12 = δ1 - δ2
Prepared by: Ismael Kareem Saeed
A noteworthy application of these equations concerns a two-
machine system having only one generator (machine one)
and a synchronous motor (machine two) connected by a
network of pure reactances. Whatever change occurs in the
generator output is thus absorbed by the motor, and we can
write
Prepared by: Ismael Kareem Saeed
Under these conditions, Pm12 = Pm and Pel2 = Pe , so
equation reduce to
Let us assume that the transmission line is loss less. Then in
the simple case where the power from machine 1 flows to
machine 2, we get
Now since the system is lossless, will also imply that Pm1 = -
Pm2 . This means that in the steady state, the power
generated at machine 1 is absorbed through machine 2, we
get Prepared by: Ismael Kareem Saeed
Let us now assume that H1 = H2 = H , V1 = V2 = 1.0 per unit
and Pm1 = 0. We then get from
where the oscillation frequency ω is given by
Thus the weighted difference of angles will approximate
simple harmonic motion for small changes in δ12 and the
frequency will decrease for an increase in inertia H or
impedance X . Prepared by: Ismael Kareem Saeed
Design methods for improving transient stability
There are a number of design measures that can be
implemented to improve the transient stability of a power system:
1. Improve the maximum power transfer capability
Improving the maximum power transfer capability of a system means
that power can be transferred through alternative un-faulted portions of the
network when a fault occurs. The effect of a fault on the system will not be as
extreme. The maximum transfer capability of a system can be improved by the
following methods:
a. Implement and use higher system voltage levels (system losses will
decrease as current flows will be lower, especially important in cases
where line distances are large)
b. Install additional transmission lines.
c. Install lines and transformers with smaller reactance values
d. Install series capacitive transmission line compensation to reduce the
overall reactance of lines
e. Install static VAR compensators and flexible AC transmission systems
(FACTS) Prepared by: Ismael Kareem Saeed
2. Implement high speed fault clearing
It is vital to clear faults before the critical clearing time is reached
so the quicker a fault is cleared the better.
3. Implement high speed re-closure of circuit breakers
As the majority of transmission line short circuits are temporary,
re-closure post fault can be beneficial in providing better power transfer
capability. Care must be taken in this case to ensure that the re-closing
on a permanent fault and any subsequent re-opening will not adversely
affect the stability of the system.
4. Implement single pole switching
The majority of short circuits are single line to ground and the
independent switch out of only the faulted phase means that some
power flow can continue across the faulted line. Studies have shown
that single line to ground faults are self-clearing even when only the
faulted phase is de-energized.
Prepared by: Ismael Kareem Saeed
5. Use generators with larger machine inertia and with
lower transient reactance
A larger synchronous machine inertia constant (H) results in a
reduction in angular acceleration and therefore a slowing down of
angular swings. The critical clearing time is increased.
Reducing the machine transient reactance increases the power transfer
capability during faults and in the periods post fault.
6. Use fast responding, high gain exciters
Modern excitation systems can be designed to act quickly and
with high gain in the event of sensing a low terminal voltage during
faults. The effect is to increase the generator output during the fault and
post fault periods. Critical clearing times are increased.
Prepared by: Ismael Kareem Saeed
7. Implement fast valve
Some steam turbines are equipped with fast valve to divert
steam flows and rapidly decrease the mechanical output. When a fault
occurs near to the generator the electrical power output is reduced and
the fast valve acts to balance the mechanical and electrical powers. This
provides reduced acceleration and longer critical clearing times.
8. Breaking Resistors
In power systems, areas of generation can be temporarily
separated from the load areas. When the separation occurs the
breaking resister can be inserted into the generation area for a second
or two in order to slow the acceleration.
Prepared by: Ismael Kareem Saeed