S.NO.
Test Test Test Conditions
number
1 Vibration 28 Clause 3.4.2 (c)
(Refer Table Endurance by sinusoidal with frequency sweep Frequency
4.28.2 Sl.1 & range:5-8 Hz
4) & 4.28.3) Amplitude:±6mm constant displacement
Frequency range:8-500 Hz
±15 m/s2 constant acceleration
Duration:2hrs in each axis
Sweep rate:1 Octave/min
UUT in unpacked & switched OFF condition. Visual
Examination & Performance Check to be carried out at the
end of each axis
2 High 17 Clause 3.2.6.1(a) Procedure 6 and test condition ‘K’
temperature Operation at:+550C±30c
Duration :24 hrs
The UUT is in switched ON condition during the 24 Hrs test
period. Performance Check to be carried out during final
hour of the test.
Visual examination and Performance check is carried out
after the test with recovery period of 2-4 hours.
Storage at: +700C±30C
Duration :24 hrs
The UUT is kept in switched OFF condition during the 24
Hrs test period.
Visual examination and Performance check is carried out
after the test with recovery period of 2-4 hours.
3 Damp heat 10 Clause 3
Temperature: +400C ± 20C
Relative humidity: 93 ± 5% Duration:16 hrs
The UUT is kept in switched OFF condition & UUT is
switched On during the last one hour and Performance
check is carried out.
Visual examination and Performance check is carried out
after the test with recovery period of 2-4 hours.
4 Low 20 Test condition ‘K’, Procedure 4
temperature Storage at:-300C±30c
Duration :16 hrs
The UUT is kept in switched OFF condition during the 16
Hrs test period.
Performance Check to be carried out during final hour of
the test.
Visual examination and Performance check is carried out
after the test with recovery period of 2-4 hours.
5 Altitude 3 Test Condition L2A2, Procedure 5
(Operational) Temperature: -30 0C ± 30C
Altitude:4500 meters
Air pressure: as per altitude
Duration:16 hrs
The UUT is kept in switched OFF condition during the 16
Hrs test period.
Visual examination and Performance check is carried out
after the test with recovery period of 2-4 hours.
6 Rapid 22 Clause 3.2.1 Procedure 1 Test Condition B
temperature Duration:
cycling High Temp: +550 ± 30C, RH <= 30% for 3hrs
Low Temp: -400 ± 30C for 3hrs
Transfer time: <= 15 min
No. of cycles: One
The UUT is kept in switched OFF condition. Visual
examination and Performance check is carried out after the
test with recovery period of 2-4 hours.
7 Sealing 23 Procedure 1
Temp: 20ºC ±2 degC
Test condition A (Air Pressure 25 kPA)
Duration:30 minutes
The air pressure reading at the end of 30 minutes period
should not have fallen by more than 10 kPa.
8 Driving Rain 12 Test Condition C:
The equipment shall be sprayed from 08 shower heads,
four of them being directed at an angle of 450 and four
directed horizontally at the centre of the area of each of the
four sides of the equipment.
Visual examination and Performance check is carried out
after the eqpt is dried by wiping or by applying a blast of air
at room temperature.
9 Immersion 19 Test condition C
Depth of Water : 1m
Period:2 hrs
UUT is in unpacked & switched OFF condition. Seals shall
be carried out, as required. UUT shall be completely
immersed in water. Visual examination and performance
check to be carried out after recovery period of 2-4hrs.
10 Dust 14 Clause 3
Temperature: 40±30C
RH<50%
Period:1 hr
UUT is in unpacked and OFF condition. Dust caps to be
fitted for all connectors. Visual examination for accumulation
of dust and performance check to be carried out after
recovery.
11 Tropical 27 Test Condition C
exposure Temperature raised to 350C±20C over 3 hrs
Relative humidity:95%
Duration:12 hrs
Temperature lowered to 200C±50C over 3 hrs
Duration:06 hrs
No. of cycles:28
Visual examination and Performance check to be carried out
after recovery of 2- 4 hrs for every 14 cycles.
12 Mould 21 Clause 3
growth Tests to be performed on sample representative material
Spray mixed spore suspension. Temperature: 30±10C
RH>90%
Duration: 28 days
UUT in switched OFF condition.
Visual Examination & Performance check (if required) to be
carried out after the test.
13 Corrosion 9 Procedure 2, Clause 3.3.2
(Salt) Salt mist spray for 2 hrs and storage for 22 hours at
350C±20C,
Relative Humidity:90-95%
Duration:22 hrs
Total No. of Cycles-3
Tests may be performed on sample representative material.
UUT in switched OFF condition. Visual Examination to be
carried out after the test.
14 Drop 13 Clause 3.2.3
Test Condition F: 1000mm
One drop at each corner, edge and face.
Total : 26 drops
UUT is in unpacked and switched OFF condition. Visual
and Performance check to be carried out after the test.
15 Toppling 26 Topple on all edges tilted angle 450 from a 100mm height.
No.of drops:4
UUT is in unpacked and switched OFF condition. Visual
and Performance check to be carried out after the test.
16 Bump 5 Shock Pulse: Half sine
No.of bumps :4000 ± 10
Peak acceleration : 400m/s2
Pulse duration:6ms
1 to 3 bumps per second.
UUT is in unpacked and switched OFF condition. Visual
and Performance check to be carried out after the test.
17 Shock 24 Procedure 2, Test Method A
Half sine wave pulse 18ms duration, 3 Shocks/side (total
18 shocks).
Test to be carried out with UUT in switched OFF condition.
Visual and Performance check to be carried out after the
test.