Doc No.                         Rev.
ERECTION CHECK LIST                                                00
                                         PLC PANEL                     ECQP xxx                            00
CUSTOMER CUSTOMER                     PROJECT PROJECT                  PLANT Plant
PLANT UNIT XXNN                   EQUIPMENT CODE NN              DESCRIPTION
DOCUMENTS REF. XXXX-XXNN
Ste                                      REPORT     DATE     TEST RESULT
    SCOPE OF INSPECTION AND TEST                                                          REMARKS
 p                                       Y   No.           PAS FAIL   NA
 1   INPUT DOCUMENTS
 2   INTEGRITY OF EQUIPMENT
 3   LABELING OF EQUIPMENT
 4   INSTALLATION OF EQUIPMENT
 5   SPACE AROUND THE EQUIPMENT
 6   FLOOR HOLES FOR CABLES
 7   MECHANICAL CONNECTION
 8   CABLE ENTRY AND CLAMPING
 9   CABLE LABELING
10   EARTHING
11   CLEANLINESS OF THE
     EQUIPMENT
12   DOORS AND COVERS
13   MODIFIED DOCUMENTS
REMARKS
Witnessed/Reviewed by "       "     Witnessed/Reviewed by "Customer"        Witnessed/Reviewed by "    "
Name                      Surname Name                Surname Name                      Surname Name
Signature
Date
                                   PRECOMMISSIONING CHECK              Doc No.                         Rev.
                                            LIST                                                        00
                                                                       ECQP xxx                            00
                                         PLC PANEL
CUSTOMER CUSTOMER                     PROJECT PROJECT                  PLANT Plant
PLANT UNIT XXNN                   EQUIPMENT CODE NN              DESCRIPTION
DOCUMENTS REF. XXXX-XXNN
Ste                                      REPORT     DATE     TEST RESULT
    SCOPE OF INSPECTION AND TEST                                                          REMARKS
 p                                       Y   No.           PAS FAIL   NA
 1   INPUT DOCUMENTS
 2   EQUIPMENT CLEANELINESS
 3   DEVICES INSTALL
 4   EARTHING
 5   SAFETY
 6   FIELD POWER SUPPLY
 7   POWER SUPPLY
 8   POWER SUPPLY UNITS
 9   CONDITIONING SYSTEM
10   SW INSTALL
11   PLC WARNINGS
12   NETWORKS
13   DIGITAL-ANALOG INPUTS
14   DIGITAL-ANALOG OUTPUTS
15   EMERGENCY
16   FIXED SPEED MOTORS
17   COMMISIONING AUXILIARES
     UNITS
18   MANUAL MOVEMENTS TESTS
19   MODIFIED DOCUMENTS
REMARKS
Witnessed/Reviewed by "       "     Witnessed/Reviewed by "Customer"        Witnessed/Reviewed by "    "
Name                      Surname Name                Surname Name                      Surname Name
Signature
Date
                                                                       Doc No.                             Rev.
                                   COMMISSIONING CHECK LIST                                                 00
                                         PLC PANEL                     ECQP xxx                            00
CUSTOMER CUSTOMER                     PROJECT PROJECT                  PLANT Plant
PLANT UNIT XXNN                   EQUIPMENT CODE NN               DESCRIPTION
DOCUMENTS REF. XXXX-XXNN
Ste                                      REPORT      DATE     TEST RESULT
    SCOPE OF INSPECTION AND TEST                                                          REMARKS
 p                                       Y   No.            PAS FAIL   NA
 1   INPUT DOCUMENTS
 2   EMERGENCY
 3   SW INSTALL
 4   I/O SETUP
 5   I/O ON HMI
 6   LOGIC SEQUENCES
 7   SYSTEM SHUTDOWN-REBOOT
 8   AS BUILT DOCUMENTS
 9
10
11
12
13
14
15
16
17
18
19
REMARKS
Witnessed/Reviewed by "       "     Witnessed/Reviewed by "Customer"       Witnessed/Reviewed by "     "
Name                      Surname Name                 Surname Name                     Surname Name
Signature
Date