The document is a Saudi Aramco inspection checklist for the pre-application inspection of cement lining, detailing acceptance criteria and requirements for materials and processes involved in cement-mortar lining. It includes specific standards for cleaning surfaces, material composition, and mixing procedures, referencing relevant documents and standards. The checklist is intended for use by contractors and third-party inspectors to ensure compliance with quality standards before proceeding with work.

Uploaded by

Vignesh Msd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
14 views2 pages

Saic H 2005

The document is a Saudi Aramco inspection checklist for the pre-application inspection of cement lining, detailing acceptance criteria and requirements for materials and processes involved in cement-mortar lining. It includes specific standards for cleaning surfaces, material composition, and mixing procedures, referencing relevant documents and standards. The checklist is intended for use by contractors and third-party inspectors to ensure compliance with quality standards before proceeding with work.

Uploaded by

Vignesh Msd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

SAUDI ARAMCO ID/PIEU-31-Jul-2022 - REV.2022.07.

00 (Standards Cutoff - July 31,2022) Rev 81 31-Jul-22


SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Pre-Application Inspection of Cement Lining SAIC-H-2005 31-Jul-22 COATING-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A General Requirements

Surfaces to be cement-mortar lined or cement-mortar coated are cleaned


to remove loose rust or other foreign matter that could interfere with the 01-SAMSS-005,
A1
adherence of the cement mortar. Sec. III (B)
(AWWA C205, Para. 4.3.1)

Cleaning Surfaces - All surfaces to be cement mortar lined shall be


01-SAMSS-005,
A2 cleaned in accordance with St2 of SIS-05-59-00 at the time of application
Para. 4.3.1
of the cement mortar.

Portland Cement conforms to the requirements of ASTM C150-00, Type


01-SAMSS-005,
A3 V, including the optional chemical & Physical requirements as per Table
Para. 4.2.2.1
1A & 2A.

Sand is fine aggregate as defined in ASTM C136 and the deleterious


substances do not exceed the following limits:
01-SAMSS-005,
A4 Clay Lumps and Friable Particles 3.00% by weight
Para. 4.2.3
Acid Soluble Chlorides {Cl} 0.06% by weight
Acid Soluble Sulfates {SO3} 0.40% by weight

01-SAMSS-005,
A5 Mixing water does not contain more than 500PPM of dissolved solids.
Para. 4.2.4

The Cement-mortar consist of one part cement to not more than 3 parts
01-SAMSS-005,
A6 fine aggregate by weight.
Sec. III (B)
(AWWA C205-07,Sec 4.4.1)

The free water content of the cement-mortar lining mix does not exceed
01-SAMSS-005,
A7 7'/2 gal (28.4L) per 94 lb (43 kg) of cement.
Sec. III (B)
(AWWA C205, Para. 4.4.1).

The cement mortar shall be mixed in batches. The amount of cement and
01-SAMSS-005,
A8 sand entering into each batch is measured by weight,
Sec. III (B)
(AWWA C205, Para. 4.4.3.2).

The quantity of water entering the mixer is measured automatically by an


adjustable device, to ensure that the correct quantity of water is being 01-SAMSS-005,
A9
added. Sec. III (B)
(AWWA C205, Para.4.4.3.2).

REMARKS:

Saudi Aramco: Company General Use


REFERENCE DOCUMENTS:
1. 01-SAMSS-005, Shop Applied, Internal Cement Mortar Lining of Steel Pipe (22 January 2019)
2. AWWA C205-07, STD FOR CEMENT-MORTAR PROTECTIVE LINING & COATING FOR STEEL WATER PIPE ( 4" & MORE)-SHOP APPLIED,
(1 Mar, 2008.)
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED