0% found this document useful (0 votes)
1 views12 pages

STEWA 25EH0055

The document provides a series of statements detailing the time elapsed and work accomplished for various construction projects managed by the Department of Public Works and Highways in Romblon, Philippines. Each project includes information such as contract ID, project name, location, contractor, original and revised contract amounts, original and revised completion dates, and percentages of planned and actual accomplishments. The reports indicate varying levels of completion and time management across different projects, with some projects achieving full completion while others show slippage in timelines.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1 views12 pages

STEWA 25EH0055

The document provides a series of statements detailing the time elapsed and work accomplished for various construction projects managed by the Department of Public Works and Highways in Romblon, Philippines. Each project includes information such as contract ID, project name, location, contractor, original and revised contract amounts, original and revised completion dates, and percentages of planned and actual accomplishments. The reports indicate varying levels of completion and time management across different projects, with some projects achieving full completion while others show slippage in timelines.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


ROMBLON DISTRICT ENGINEERING OFFICE
Odiongan, Romblon

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


for the period of 16 July 2023 to 10 September 2023

1. Project Components :
2. Contract ID : 23EH0108
3. Name of Project : CONCRETING OF BRGY. MAPULA
FMR
4. Location : Brgy. Mapula, Romblon, Romblon
5. Contractor : MT. GUITING-GUITING
CONSTRUCTION
6. Original Contract Amount : Php 11,696,892.45
7. Revised Contract Amount : Php 11,937,401.01
(due to approved V.O. No. 1)
8. Original Contract Time : 73 Calendar Days
9. Revised Contract Time (CTE No. 1) : 88 Calendar Days
10. Revised Contract Time (CTE No. 2) : 108 Calendar Days
11. Date Started : May 26, 2023
12. Original Completion Date : August 06, 2023
13. Revised Completion Date (CTE No. 1): August 21, 2023
14. Revised Completion Date (CTE No. 2): September 10, 2023
15. % Planned Accomplishment (December 10, 2023) : 100.00 %
16. % Actual Accomplishment (December 10, 2023) : 96.19 %
17. Slippage : (-) 3.81 %
17. Percent of Time Elapsed : 100.00 % (state elapsed calendar
days out of revised contract time)

Prepared by:

EDWARD R. RAMILO
Project Engineer III
Date: __________________

Noted:

ELMER M. TOLENTINO
Chief of Construction Section
Date: _____________

Website: www.dpwh.gov.ph
Tel. No(s).: (042) 567 2311
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ROMBLON DISTRICT ENGINEERING OFFICE
Odiongan, Romblon

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


for the period of March 28, 2023 to June 26, 2023

3. Project Components : P00620264LZ-CW1


4. Contract ID : 22EH0015-R1
3. Name of Project : Construction/Maintenance of Flood
Mitigation Structures and Drainage
Systems - Construction of Batiano
Boulevard Flood Mitigating Structure
4. Location : Odiongan, Romblon
5. Contractor : ROLCO CONSTRUCTION AND
DEVELOPMENT
6. Original Contract Amount : Php 93,995,729.32
7. Revised Contract Amount : Php 96,485,051.38
(due to approved V.O. No. 1)
8. Original Contract Time : 304 Calendar Days
9. Revised Contract Time (CTE No. 1) : 364 Calendar Days
10. Revised Contract Time (CTE No. 2) : 424 Calendar Days
11. Date Started : March 29, 2022
12. Original Completion Date : January 26, 2023
13. Revised Completion Date (CTE No. 1): March 27, 2023
14. Revised Completion Date (CTE No. 2): May 26, 2023
15. Revised Contract Amount : Php 96,485,036.56
(due to latest approved V.O. No. 2)
16. % Planned Accomplishment : 100.00 %
14. % Actual Accomplishment : 100.00 %
15. Slippage : 0.00 %
16. Percent of Time Elapsed : 107.31 % (state elapsed calendar
days out of revised contract time)

Prepared by:

DANTE F. FETALVERO
Project Engineer III
Date: __________________

Noted :

ELMER M. TOLENTINO
Chief of Construcion Section
Date: _____________
Website: www.dpwh.gov.ph
Tel. No(s).: (042) 567 2311
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ROMBLON DISTRICT ENGINEERING OFFICE
Odiongan, Romblon

PIF-06-BIL-08 Rev 00

Website: www.dpwh.gov.ph
Tel. No(s).: (042) 567 2311
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ROMBLON DISTRICT ENGINEERING OFFICE
Odiongan, Romblon

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


From: September 24, 2022 to January 31, 2023

5. Project Components : P00620264LZ-CW1


6. Contract ID : 22EH0015-R1
3. Name of Project : Construction/Maintenance of Flood
Mitigation Structures and Drainage
Systems - Construction of Batiano
Boulevard Flood Mitigating Structure
4. Location : Odiongan, Romblon
5. Contractor : ROLCO CONSTRUCTION AND
DEVELOPMENT
6. Original Contract Amount : Php 93,995,729.32
7. Revised Contract Amount : Php 96,485,051.38
(due to latest approved V.O. No. 1)
8. Original Contract Time : 304 Calendar Days
9. Revised Contract Time : 364 Calendar Days
10. Date Started : March 29, 2022
11. Original Completion Date : January 26, 2023
12. Revised Completion Date : March 27, 2023
13. % Planned Accomplishment : 85.42 %
14. % Actual Accomplishment : 73.72 %
15. Slippage : (-) 11.70 %
16. Percent of Time Elapsed : 84.89 % (state elapsed calendar
days out of revised contract time)

Prepared by:

DANTE F. FETALVERO
Project Engineer III
Date: __________________

Noted :

ELMER M. TOLENTINO
Chief of Construcion Section
Date: _____________

PIF-06-BIL-08 Rev 00
Website: www.dpwh.gov.ph
Tel. No(s).: (042) 567 2311
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ROMBLON DISTRICT ENGINEERING OFFICE
Odiongan, Romblon

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


From: May 24, 2023 to September 13, 2023

1.Project Components : P0725879LZ-CW1


2. Contract ID : 23EH0078
3. Name of Project : CONSTRUCTION OF PAG-ALAD
FLOOD MITIGATING STRUCTURE
(PHASE 2) ALONG PARPAGOHA
RIVER CONTROL
4. Location : San Andres, Romblon
5. Contractor : MRRM TRADING & CONSTRUCTION /
KPSL GENERAL CONTRACTOR INC.
JOINT VENTURE
6. Original Contract Amount : Php 91,876,451.08
7. Revised Contract Amount : Php 94,085,449.70
(due to latest approved V.O. No. 1)
8. Original Contract Time : 335 Calendar Days
9. Revised Contract Time :
(due to approved C.T.E )
10. Date Started : March 09, 2023
11. Original Completion Date : February 6, 2024
12. Revised Completion Date :
(due to approved C.T.E.)
13. % Planned Accomplishment : 100.00 %
14. % Actual Accomplishment : 100.00 %
15. Slippage : 0.00 %
16. Percent of Time Elapsed : 100.00 % (state elapsed calendar
days out of revised contract time)

Prepared by: Noted:

CELESTIAL G. ALAG ELMER M. TOLENTINO


Project Engineer III Chief of Construction Section
Date: __________________ Date: __________________

PIF-06-BIL-08 Rev 00

Website: www.dpwh.gov.ph
Tel. No(s).: (042) 567 2311
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ROMBLON DISTRICT ENGINEERING OFFICE
Odiongan, Romblon

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


For the Period of May 24, 2023 to September 13, 2023

1.Project Components : P0725879LZ-CW1


2. Contract ID : 23EH0078
3. Name of Project : CONSTRUCTION OF PAG-ALAD
FLOOD MITIGATING STRUCTURE
(PHASE 2) ALONG PARPAGOHA
RIVER CONTROL
4. Location : San Andres, Romblon
5. Contractor : MRRM TRADING & CONSTRUCTION /
KPSL GENERAL CONTRACTOR INC.
JOINT VENTURE
6. Original Contract Amount : Php 91,876,451.08
7. Revised Contract Amount : Php 94,085,449.70
(due to latest approved V.O. No. 1)
8. Revised Contract Amount : Php 94,151,638.38
(due to latest approved F.V.O)
9. Original Contract Time : 335 Calendar Days
10. Revised Contract Time :
(due to approved C.T.E )
11. Date Started : March 09, 2023
12. Original Completion Date : February 6, 2024
13. Revised Completion Date :
(due to approved C.T.E.)
14. % Planned Accomplishment : 60.28 %
15. % Actual Accomplishment : 100.00 %
16. Slippage : (+) 39.72 %
17. Percent of Time Elapsed : 56.42 % (state elapsed calendar
days out of original contract time)

Prepared by: Noted:

CELESTIAL G. ALAG ELMER M. TOLENTINO


Project Engineer III Chief of Construction Section
Date: __________________ Date: __________________

PIF-06-BIL-08 Rev 00

Website: www.dpwh.gov.ph
Tel. No(s).: (042) 567 2311
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ROMBLON DISTRICT ENGINEERING OFFICE
Odiongan, Romblon

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


For the Period of: 09 November 2023 to 10 January 2024

1.Project Components : P00741943LZ-CW1


2. Contract ID : 23EH0102
3. Name of Project : CONSTRUCTION OF ACCESS ROAD
TO TORREL – LOOBAN
4. Location : Odiongan, Romblon
5. Contractor : MT. GUITING-GUITING
CONSTRUCTION
6. Original Contract Amount : Php 14,508,453.91
7. Revised Contract Amount : Php 14,847,247.35
(due to latest approved V.O. No. 1)
8. Revised Contract Amount : Php 14,845,148.14
(due to latest approved F.V.O.)
9. Original Contract Time : 153 Calendar Days
10. Revised Contract Time : 213 Calendar Days
(due to approved C.T.E )
11. Date Started : May 12, 2023
12. Original Completion Date : October 11, 2023
13. Revised Completion Date : December 10, 2023
(due to approved C.T.E.)
14. % Planned Accomplishment (December 10, 2023) : 100.00 %
15. % Actual Accomplishment (December 10, 2023) : 96.19 %
16. Slippage : (-) 3.81 %
17. Percent of Time Elapsed : 114.55 % (state elapsed calendar
days out of revised contract time)
Prepared by:

DANTE F. FETALVERO
Project Engineer III
Date: __________________

Noted:

ELMER M. TOLENTINO
Chief of Construction Section
Date: __________________

Website: www.dpwh.gov.ph
Tel. No(s).: (042) 567 2311
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ROMBLON DISTRICT ENGINEERING OFFICE
Odiongan, Romblon

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


for the period of February 21, 2023 to October 10, 2023

1. Project Components :
2. Contract ID : 23EH0075
3. Name of Project : Construction of Multi-Purpose
Building, Brgy. Dapawan
4. Location : Brgy. Dapawan, Odiongan, Romblon
5. Contractor : RNV CONSTRUCTION
6. Original Contract Amount : Php 4,850,868.08
7. Revised Contract Amount : Php 5,007,242.58
(due to approved V.O. No. 1)
8. Original Contract Time : 120 Calendar Days
9. Revised Contract Time (CTE No. 1) : 180 Calendar Days
10. Revised Contract Time (CTE No. 2) : 206 Calendar Days
11. Revised Contract Time (CTE No. 3) : 232 Calendar Days
12. Date Started : February 21, 2023
13. Original Completion Date : June 20, 2023
14. Revised Completion Date (CTE No. 1): August 19, 2023
15. Revised Completion Date (CTE No. 2): September 14, 2023
16. Revised Completion Date (CTE No. 3): October 10, 2023
17. % Planned Accomplishment : 100.00 %
18. % Actual Accomplishment : 100.00 %
19. Slippage : 0.00 %
20. Percent of Time Elapsed : 100.00 % (state elapsed calendar
days out of revised contract time)

Prepared by:

THERESA LYN A. DE CASTRO


DPWH, Junior Project Engineer
Date: __________________

Noted :

ELMER M. TOLENTINO
Chief of Construcion Section
Date: _____________

PIF-06-BIL-08 Rev 00
Website: www.dpwh.gov.ph
Tel. No(s).: (042) 567 2311
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ROMBLON DISTRICT ENGINEERING OFFICE
Odiongan, Romblon

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


For the Period of April 08, 2024 to July 30, 2024

1.Project Components : P00844549LZ-CW1


2. Contract ID : 24EH0102
3. Name of Project : CONSTRUCTION OF TORREL-
LOOBAN FLOOD CONTROL
STRUCTURE
4. Location : Odiongan, Romblon
5. Contractor : ATHENA CONSTRUCTION AND
DEVELOPMENT
6. Original Contract Amount : Php 19,010,538.18
7. Revised Contract Amount : Php 19,328,183.56
(due to latest approved V.O. No. 1)
8. Revised Contract Amount :
(due to latest approved F.V.O)
9. Original Contract Time : 196 Calendar Days
10. Revised Contract Time :
(due to approved C.T.E )
11. Date Started : April 08, 2024
12. Original Completion Date : October 20, 2024
13. Revised Completion Date :
(due to approved C.T.E.)
14. % Planned Accomplishment : 42.15 %
15. % Actual Accomplishment : 68.69 %
16. Slippage : (+) 26.53 %
17. Percent of Time Elapsed : 43.88 % (state elapsed calendar
days out of original contract time)

Prepared by: Noted:

JULIEN MARIE M. EVANGELIO ELMER M. TOLENTINO


Project Engineer I Chief of Construction Section
Date: __________________ Date: __________________

STATEMENT OF
Website: www.dpwh.gov.ph
Tel. No(s).: (042) 567 2311
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ROMBLON DISTRICT ENGINEERING OFFICE
Odiongan, Romblon

TIME ELAPSED AND WORK ACCOMPLISHED


From: May 21, 2025 to July 15, 2025

1.Project Components : P00941437LZ-CW1


2. Contract ID : 25EH0043
3. Name of Project : CONSTRUCTION OF FLOOD
CONTROL STRUCTURESITIO
CENTRO, BARANGAY TABOBO-AN
4.Location : Odiongan, Romblon
5.Contractor : SUNWEST, INC.
6.Original Contract Amount : Php 137,944,034.20
7.Revised Contract Amount : Php 137,938,468.72
8.Original Contract Time : 360 Calendar Days
9.Revised Contract Time :
(due to approved C.T.E )
10. Date Started : May 21, 2025
11. Original Completion Date : May 15, 2025
12. Revised Completion Date :
(due to approved C.T.E.)
13. % Planned Accomplishment : 7.26 %
14. % Actual Accomplishment : 44.64 %
15. Slippage : 0.00 %
16. Percent of Time Elapsed : 15.66 % (state elapsed calendar
days out of original contract time)

Prepared by:

CELESTIAL G. ALAG
Project Engineer III
Date: __________________

Noted:

ELMER M. TOLENTINO
Chief of Construction Section
Date: __________________

PIF-06-BIL-08 Rev 00

Website: www.dpwh.gov.ph
Tel. No(s).: (042) 567 2311
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ROMBLON DISTRICT ENGINEERING OFFICE
Odiongan, Romblon

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


From: June 21, 2025 to July 24, 2025

1.Project Components : P00939483LZ-CW1


2. Contract ID : 25EH0053
3. Name of Project : CONSTRUCTION OF
SEAWALL/LEADING TO POBLACION,
PHASE 3
4.Location : Odiongan, Romblon
5.Contractor : SUNWEST, INC.
6.Original Contract Amount : Php 132,399,165.70
7.Revised Contract Amount :
8.Original Contract Time : 357 Calendar Days
9.Revised Contract Time :
(due to approved C.T.E )
10. Date Started : May 21, 2025
11. Original Completion Date : May 15, 2025
12. Revised Completion Date :
(due to approved C.T.E.)
13. % Planned Accomplishment : 13.047 %
14. % Actual Accomplishment : 63.14 %
15. Slippage : 52.75 %
16. Percent of Time Elapsed : 17.65 % (state elapsed calendar
days out of original contract time)

Prepared by:

CELESTIAL G. ALAG
Project Engineer III
Date: __________________

Noted:

ELMER M. TOLENTINO
Chief of Construction Section
Date: __________________

PIF-06-BIL-08 Rev 00

Website: www.dpwh.gov.ph
Tel. No(s).: (042) 567 2311
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
ROMBLON DISTRICT ENGINEERING OFFICE
Odiongan, Romblon

STATEMENT OF TIME ELAPSED AND WORK ACCOMPLISHED


From: June 21, 2025 to July 28, 2025

1.Project Components : P00921654LZ-CW1


2. Contract ID : 25EH0055
3. Name of Project : CONSTRUCTION OF FLOOD
CONTROL STRUCTURE, TABOBO-AN
RIVER, ODIONGAN, ROMBLON
4.Location : Odiongan, Romblon
5.Contractor : SUNWEST, INC.
6.Original Contract Amount : Php 141,855,510.56
7.Revised Contract Amount :
8.Original Contract Time : 361 Calendar Days
9.Revised Contract Time :
(due to approved C.T.E )
10. Date Started : April 11, 2025
11. Original Completion Date : April 06, 2026
12. Revised Completion Date :
(due to approved C.T.E.)
13. % Planned Accomplishment : 26.89 %
14. % Actual Accomplishment : 81.22 %
15. Slippage : 54.33 %
16. Percent of Time Elapsed : 30.19 % (state elapsed calendar
days out of original contract time)

Prepared by:

CELESTIAL G. ALAG
Project Engineer III
Date: __________________

Noted:

ELMER M. TOLENTINO
Chief of Construction Section
Date: __________________

PIF-06-BIL-08 Rev 00

Website: www.dpwh.gov.ph
Tel. No(s).: (042) 567 2311

You might also like