TARIFF FOR HIGH TENSION CONSUMERS FOR FY 2014-15
Sl.No Category Tariff EXISTING TARIFF NEW TARIFF
Demand Energy Demand Energy
Charges Charges Charges Charges
(Rs / kVA / (Ps / Unit) (Rs / kVA (Ps / Unit)
Month) / Month)
1 Industries IA 300 550 350 635
2 Railway Traction IB 250 550 300 635
3 Govt. and Govt. aided educational II A 300 450 350 635
institution
4 Private educational institutions and hostels II B 300 550 350 635
run by them
5 Commercial III 300 700 350 800
6 Lift Irrigation (*) IV 0 350 0 635
7 Temporary Supply V 300 950 350 1100
(*) Tariff charges are to be borne by the Government of Tamil Nadu as per the existing policy
TARIFF FOR LOW TENSION CONSUMERS FOR FY 2014-15
Sl.No Category Tariff EXISTING TARIFF NEW TARIFF
Fixed Energy Charges Fixed Charges Energy
Charges Charges
(Rs / bi (Ps / Unit) (Rs / bi monhtly) (Ps / Unit)
monhtly)
1 Domestic /Residential IA
Consumption upto 50 units monthly or 100 units bimonthly
0-100 units bimonthly
20 260 30 300
Consumption from 51 units to 100 units per month or 101 units to 200 units for two months
0-200 units bimonthly 20 280 30 325
Consumption of 101 units to 250 units per month (or) 201 units to 500 units for two months
0-200 units bimonthly 300 350
30 40
201-500 units bimonthly 400 460
Consumption of 251 units and above per month (or) 501 units and above for two months
0-200 units bimonthly 300 350
201-500 units bimonthly 40 400 50 460
501 and above bimonthly 575 660
2 Rs.250/Service /bi-monthly Rs.290/Service/bi-monthly
Huts (Till Installation of Energy Meters) (*) IB (borne by the Govt fully as (to be borne by Govt fully as
subsidy) subsidy)
Huts (On Installation of Energy Meters) (*) 0 430 0 495
3 Bulk supply IC 100 400 120 460
4 Public Lighting and Water Supply II A 0 550 120/kW 635
5 Govt. and Govt. aided Educational Institutions II B (1) 100 /kW 500 120/kW 575
6 Private educational Institutions II B (2) 100 /kW 650 120/kW 750
7 Places of Pub. Worship II C
Upto 120 units bimonthly 500 575
100 / kW 120/kW
above 120 units bimonthly 500 575
8 Cottage and Tiny Industries III A (1)
0-500 units bimonthly 350 400
30 / kW 40/kW
501 units and above bimonthly 400 460
9 Power Looms III A (2)
(i) Consumers who consume upto 250 units per month (or) 500 units for two months
0 to 250 units per month or 0 to 500 units
100/kW 450
bimonthly (*) 120/kW 520
(ii) For consumers who consume 251 units and above per month (or) 501 units and above
for two months
0 to 250 units per month or 0 to 500 units
450
bimonthly (*) 520
251 to 500 units per month or 501-1000 units
500
bimonthly
501 to 750 units per month or 1001-1500 units 100/kW 120/kW
500 575
bimonthly
From 751 units and above per month or 1501
500
units and above bimonthly
Industries III B
10
(for all units) 60 /kW 550 70/kW 635
Rs 2500 / HP / Annum Rs.2875/HP/Annum
Agriculture (Till Installation of Energy
11 Meters) (*)
(borne by the Govt fully as (to be borne by the Govt
subsidy) fully as subsidy)
IV
Agriculture (On installation of Energy
0 280 0 322
Meters) (*)
12 Commercial V
For consumer with consumption 50 units per
430 500
month or 100 units bimonthly
For consumers with consumption above 50 units 120 /kW 140/kW
per month or above 100 units bimonthly (for all 700 805
units)
13 Temporary supply for temporary activities,
Rs.300/kW/
construction of buildings and lavish VI 1050 Rs.345/kW /per 1200
per month
illumination month
(*) Tariff charges are to be borne by the Government of Tamil Nadu as per the existing policy