The document outlines the inspection checklist for the in-process inspection of APCS-113 coating systems used by Saudi Aramco, detailing acceptance criteria, weather conditions, application requirements, and final inspection procedures. It specifies the necessary qualifications for personnel, the types of coatings used, and the conditions under which painting should not occur. Additionally, it includes references to relevant Saudi Aramco standards and guidelines for quality control and inspection processes.

Uploaded by

Vignesh Msd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
48 views3 pages

Saic H 2049

The document outlines the inspection checklist for the in-process inspection of APCS-113 coating systems used by Saudi Aramco, detailing acceptance criteria, weather conditions, application requirements, and final inspection procedures. It specifies the necessary qualifications for personnel, the types of coatings used, and the conditions under which painting should not occur. Additionally, it includes references to relevant Saudi Aramco standards and guidelines for quality control and inspection processes.

Uploaded by

Vignesh Msd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

#

SAUDI ARAMCO ID/PIEU-31-Jul-2022 - REV.2022.07.00 (Standards Cutoff - July 31,2022) Rev 81 31-Jul-22

SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER

In-Process Inspection of APCS-113 Coating Systems


SAIC-H-2049 31-Jul-22 COAT-
Application
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A General Requirements
Saudi Aramco Paint Data Sheet of APCS-113 system applied on site is
provided.
Number of Coat specified : ________________________
Re-coat Time Interval: ____________________________ SAES-H-002V,
____________________________ SAES-
A1
____________________________ H-002 & APCS
Pot Life: ____________________________ Sheets
DFT of Total System : ____________________________

Personnel involved in protective coating activities has been qualified and SAEP-316,
A2
certified to perfom their task. Para. 5.1

APCS-113A coatings are used on new construction to:


(1) repair damaged FBE
(2) coat already cement lined pipe.
(3) coat short runs of pipe (60 meters or less) that will not require SAES-H-002,
subsequent bending. Para. 5.4.1
A3 (4) Top coat for Thrust bored pipes. CSD/Coatings Team shall confirm Para. 5.4.2
if applied APCS-113A has adequate abrasion resistance. Para. 5.1.12

APCS-113B Coatings are used for the external of buried pipes, fittings SAES-H-002,
A4 and appurtenances, particularly those with exposed bolts or sharp APCS-113B,
changes in surface transition. Sheet
APCS-113E are used on new construction:
SAES-H-002,
(1) For girth welds of pipes to be thrust bored
Para. 5.4.4
A5 (2) As fast Cure, Abrasion Resistance Coating for Thrust Boring Pipes in
APCS-113E
Road Crossing
Sheet
APCS-113F can be used on girth weld areas of pipeline, applied by
automatic rotational equipment. SAES-H-002,
A6
Para. 5.4.2

B Weather Conditions for Painting

Paint shall not be applied during adverse weather conditions such as, but
not restricted to following:
1) Wind is strong enough to blow sand, salt spray or other
foreign matter onto the surface being painted. SAES-H-001 Para
B1
2) Wind is 6.1.1
strong enough to cause dry spay or otherwise seriously
disturb the spray pattern when application is by spray gun.
3) Rain

Saudi Aramco: Company General Use


# Saudi Aramco: Company General Use
#

Paint shall not be applied if one or more of the following conditions exist
(unless paint is specifically formulated for averted condition):
a) Substrate temperature is less than 10°C of the temperature
limit given in the applicable Saudi Aramco Data Sheet SAES-H-001 Para
B2
b) Substrate temperature is more than the temperature limit 6.1.1
given in the applicable Saudi Aramco Data Sheet.
c) Substrate temperature is less than 3°C above the dew point.

Blast cleaned surfaces has been inspected for flash rusting prior to
priming or coating. SAES-H-001,
B3 Note: Flash rusting can occur on blast cleaned surfaces if held for Para 8.4.3
more than 4 hours, in less time during high humidity.

C Spray Application Requirements

All weld lines, edges, bolts, nuts and rivets are given brush applied stripe SAES-H-001,
C1
coat prior to all coating applications. Para. 9.3.2

Only airless spraying equipment with higher ratio pumps (45:1 or higher) SAES-H-001,
C2
shall be used. Para. 9.5.3

SAES-H-002V,
Coating nozzle tip size and fluid pressure are verified to be as specified in
C3 Paint
Saudi Aramco Paint Data sheets SAES-H-002V .
Data Sheets

Paints to be sprayed are filtered through a 30 to 60-mesh screen prior to SAES-H-001,


C4
use. Para 9.3.7

Paints shall be continuously agitated with a low-speed stirrer during SAES-H-001,


C5
application. Para 9.3.7

Proper spraying techniques and control of spray pattern are


demonstrated during paint application as follows:
A) Spray Gun is held perpendicular to surface at a distance that will
ensure that a wet layer of paint is deposited on the surface.
SAEP-316
B) Trigger of the gun is released at the end of each stroke.
Para.
C) Paint is applied in a uniform layer with over lapping at the edges of the
C6 4.4.4 (J) &
spray pattern.
As Referenced
Note 1: Spray application techniques per SSPC-PA 1 Par 7.3.4
(SSPC)
Note 2: Inspectors shall identify poor technique that results in any of
the unacceptable application defects (runs, sags, drips, etc)
Note 3: Corrective action shall be accepted when applications can
be performed without defects in accordance with Data sheets.

Coating shall be applied in a single coat "Wet-On-Wet" method to


achieve the required film thickness. SAES-H-001
Application of succeeding coats shall be made with in recoat interval time Para 9.4.3
C7
as specified in SA Data sheets. Beyond the the recoat interval time, the SAES-H-002V
succeeding coats can be applied after removing the gloss surface Paint Data Sheet
resulting from previous coat.

D Brush / Roller Application


Brush / Roller are used when allowed by the paint manufacturer or as SAES-H-002V,
D1
indicated in the paint manufacturer's data sheet. SA Data Sheet
SAES-H-001 Para
D2 The maximum brush size if used for painting is 125 mm.
9.3.6
E Final Wet Coat Inspection
Wet coating shall be free of application related defects such as runs, sags, SAES-H-001,
E1
drips or foreign matter. Para 9.3.5 b
Quality Control Records:
SAES-H-001
E2 Applied coat(s) Inspection and test results are recorded in:
Para 10.2.3
In-process Inspection Sheet (SATR-H-2006)

REMARKS:

REFERENCE DOCUMENTS:
1. SAES-H-001, Coating Selection and Application Requirements for Industrial Plants and Equipment (23 May 2019).
2. SAES-H-002 Internal and External Coatings for Steel Pipelines and Piping (22 February 2018)
3. SAES-H-002V, Approved Saudi Aramco Data Sheets for the Pipeline Maintenance External Coatings, (07 February 2017)
4. SAES-H-102: Safety requirements for Coating Applications (29 October 2017
5. SAEP-316, Performance Qualification of Coating Personnel (31 July 2016)
6. Steel Structures Painting Council, SSPC-PA 1, September 1993

Saudi Aramco: Company General Use


# Saudi Aramco: Company General Use
#

Contractor Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED

Saudi Aramco: Company General Use