Saic H 2059

The document is a Saudi Aramco inspection checklist for the surface preparation of pipe joints for field internal coating, detailing acceptance criteria and inspection checkpoints. It outlines requirements for coating materials, application procedures, and quality control measures to ensure compliance with specified standards. Additionally, it includes references to relevant specifications and procedures for conducting inspections and quality assessments.

Uploaded by

Vignesh Msd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
58 views3 pages

Saic H 2059

The document is a Saudi Aramco inspection checklist for the surface preparation of pipe joints for field internal coating, detailing acceptance criteria and inspection checkpoints. It outlines requirements for coating materials, application procedures, and quality control measures to ensure compliance with specified standards. Additionally, it includes references to relevant specifications and procedures for conducting inspections and quality assessments.

Uploaded by

Vignesh Msd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

#

SAIC NUMBER DATE APPROVED QR NUMBER


SAUDI ARAMCO INSPECTION CHECKLIST
Surface Preparation of Pipe Joints for Field Internal Coating SAIC-H-2059 31-Jul-22 COAT-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A General Requirements

Application of girth weld coatings shall be strictly in accordance with the


approved Vendor’s application procedure. Coating materials and SAES-H-201,
A1
method of application and equipment to be used shall be specified in Para. 8.1.1
this procedure.

Powder/liquid coating materials supplied to the Vendor shall be certified


by Manufacturer with the following information, which must meet initially
approved material:

a) The Manufacturer's name


b) Product description
SAES-H-201,
c) Mass or density of material
A2 Section 6.9
d) The material identification number
& Section 4
e) The batch number
f) Date of manufacture
g) Location of manufacturing
h) Temperature required for transportation and storage
i) The shelf life (or expiration date)
j) Material identification fingerprints

The finished coating shall have a uniform, glossy appearance and be


free of defects such as holidays, fish eyes, lumps, dry spray, sags and
SAES-H-201,
runs. Coating overlap shall be within the thickness specified in 09-
A3
SAMSS-089 for external and 09-SAMSS-091 for internal. DFT for liquid
Para. 9.2.5
girth weld coatings shall be in accordance with the applicable APCS
specification.

A PPT shall be conducted at the start of each shift to verify the correct
functioning of the used equipment. The PPT shall be conducted on a
spool similar to the pipes to be coated. The following tests in tables 2
SAES-H-201,
and 3 shall beconducted by the Vendor and the results shall be shared
A4 Para. 8.1.6
with Saudi Aramco inspector.

Tests in SAES-H-201, tables 2 and 3 shall be conducted by the Vendor


and the result shall be shared with Saudi Aramco inspector.

SAES-H-201,
Surface preparation shall be done by the Contractor, unless otherwise
Para. 8.2.5
specified in the scope of work. Pipe bung shall be used to protect shop-
A5 &
applied pipe coating.
SAES-H-001
Para. 6.3

Personnel involved in protective coating activities has been qualified SAEP-316,


A6
and certified to perfom their task. Para. 5.1

Pipe Girth Weld Preparation NOTE: The following inspection checkpoints shall be verified and modified in accordance with the
B
contractor's internal coating procedure approved by RSA of Saudi Aramco CSD.)

Saudi Aramco: Company General Use


# Saudi Aramco: Company General Use
#

Maximum dimensions of pipeline sections welded do not exceed its


dimensions as detailed in the Contractor Coating Procedure. Approved Coating
B1
Length:_______________ , Bend Radius:________________ , Procedure
Minimum ID for 12" Dia. Pipe: __________________

For welds that require post weld heat treatment (PWHT), coatings on
both Internal and External welds shall be applied after PWHT.
Demonstration shall be conducted prior to actual work to determine the SAES-H-201
B2
required internal and external cutback after the completion of PWHT. If Para. 8.1.2
the cutback is exceeding 280 mm, only approved liquid coating can be
used for the internal girth weld.

Prior to blast cleaning, all hydrocarbon contaminants within a 500 mm


wide band centered over the weld shall be removed from the pipe by
solvent cleaning per SSPC SP-1. Kerosene, diesel, or similar
SAES-H-201
B3 degreasers that leave an oily film shall not be used. For internal girth
Para. 8.2.1
weld, it should be done by the Contractor, unless otherwise specified in
the scope of work. The responsibilities of Contractor and Vendor for
internal girth weld coating are summarized in Table 4.

All weld joints including adjacent areas to be coated either Internally or


Externally shall be ground smooth and free from burrs, weld spatter,
sharp edges. Weld toes shall be merged smoothly and rounded with no
sharp undercuts. The weld cap or internal root protrusion shall not be SAES-H-201
B4
more than 1.5 mm. Still, weld curve shall be smooth enough for coating Para. 8.2.2
application regardless of protrusion eight. Increasing coating thickness
shall not be used to overcome
such defects.

The maximum length of the coating field application is limited by the


total length of the cutback, 50-75 millimeters (2-3 inches), plus a
SAES-H-201,
B5 reasonable overlap, 1-2 inches, to tie in with the parent FBE coating. In
Para. 8.1.4
the case of PWHT, demonstration shall be conducted to determine the
required length.

Field weld number is marked inside of the pipe at 12" (300mm) from the
Approved Coating
B6 field joint.
Procedure
This unique ID is per the SAEP-1160 Reqmts

C Visual Inspection & Inside Surface Preparation verified as specified in Approved Procedure

Abrasive blasting shall be carried out only when the steel surface is at SAES-H-001,
C1
least 3°C above the Dew Point. Para. 6.4.3

Surface preparation shall be done by the Contractor, unless otherwise SAES-H-201,


C2
specified in the scope of work. Pipe bung shall be used to protect shop- Para. 8.2.5
applied pipe coating.

Quality of compressed air used for blasting is checked at the start and
SAES-H-001
C3 mid point of 8 hour shift by blotter test. It shall be free of oil , moisture
Para. 6.5.1
and other contaminants.

The gloss shall be feathered out from the shop-applied FBE pipe
coating that will be overlapped by the field coating by light abrasive SAES-H-201,
C4
(sweep) blasting or sanding. Wire brushes shall not be used for this Para. 8.2.6
purpose.

The surface profile shall be measured by a stylus profilometer. Rz shall SAES-H-201,


C5
be in the range of 50 to 100 micrometers. Para. 8.2.4

Surface Preparation / Degree of cleanliness meets the following: SAES-H-002,


C6 APCS-102A, 102B, 102C & APCS-28 - Sa 3 (White Metal Finish). SAES-H-001
APCS-117, 118, 119, 120 - SA 21/2 (Near white Metal Finish) APCS-Sheet

Saudi Aramco: Company General Use


# Saudi Aramco: Company General Use
#

Surface Preparation / Anchor Profile meets the following:


APCS-28.......................................65-100 Microns Min-Max
APCS-102A, 102B, 102C ............50-100 Microns Min-Max
SAES-H-002,
APCS-117 & APCS- 120..............50-125 Microns Min-Max
C7 SAES-H-001
APCS-118.....................................75-175 Microns Min-Max
APCS-Sheet
APCS-119.....................................20-40 Microns Min-Max
APCS-118.....................................75-175 Microns Min-Max

Spent abrasive and debris are removed from the blast cleaned internal SAES-H-001
C8
surfaces by dry brushing and vacuum cleaning Para.8.4.1

SATR-H-2011 was completed in accordance with this checklist for Applicable


C9
production runs as identified. SATIP step
Remarks:
ATTACHMENTS: Non
REFERENCE DOCUMENTS:
1. SAES-H-001, Coating Selection and Application Requirements for Industrial Plants and Equipment (21 February 2018)
2. SAES-H-201: General Specification for External and Internal FBE Coatingsof Pipeline Field Girth Welds (31 March 2020)
3. SAES-H-002 Internal and External Coatings for Steel Pipelines and Piping (22 February 2018)
4. SAEP-316, Performance Qualification of Coating Personnel, (31 July 2016)
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED