The document outlines the Saudi Aramco Inspection Checklist for in-process inspection of FBE coating application on external field girth welds, including acceptance criteria and procedures for various stages of the coating process. It specifies requirements for personnel qualifications, heating of pipe surfaces, powder application, visual inspections, dry film thickness measurements, holiday testing, and repairs. Reference documents and inspection approvals are also included to ensure compliance with standards and quality control.

Uploaded by

Vignesh Msd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
19 views4 pages

Saic H 2015

The document outlines the Saudi Aramco Inspection Checklist for in-process inspection of FBE coating application on external field girth welds, including acceptance criteria and procedures for various stages of the coating process. It specifies requirements for personnel qualifications, heating of pipe surfaces, powder application, visual inspections, dry film thickness measurements, holiday testing, and repairs. Reference documents and inspection approvals are also included to ensure compliance with standards and quality control.

Uploaded by

Vignesh Msd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

#

SAUDI ARAMCO ID/PIEU-31-Jul-2022 - REV.2022.07.00 (Standards Cutoff - July 31,2022) Rev 81 31-Jul-22
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
In-Process Inspection of FBE coating Application on External Field
Girth Welds [Includes Repair / Patch-up coating]
SAIC-H-2015 31-Jul-22 Coating-

PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?

SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

A General Requirements (Limited to APCS 104 System Application)

Personnel involved in protective coating activities has been qualified and SAEP-316,
A1
certified to perfom their task. Para. 5.1

External FBE powder shall meet the requirements of 09-SAMSS-089 and SAES-H-201,
A2
SAES-H-002, APCS-104A/B/C. Para. 7.1

100% of the coated girth weld surface area shall be holiday detected,
SAES-H-201,
A3 inspected, and repaired in accordance with the procedures and equipment
Para. 9.3.1
specified in 09-SAMSS-089 for external and 09-SAMSS-091 for internal.

During periods of bad weather (rain, high winds, etc.) cleaning and
SAES-H-201,
A4 coating operations will only proceed if protective canopies are used to the
Para. 8.3.7
satisfaction of the Saudi Aramco Inspector.

Every protective coatings applicator personnel shall be verified for Third


SAEP-316,
A5 Party Training Certification or SA approved coating supplier certificates for
Para. 5.5
coating to be applied.

B Heating of Pipe Surface:

Coating application shall be performed after completion of welding and


SAES-H-201,
B1 NDT of field welding, to prevent formation of adherent rust, which may
Para. 8.3.1
require to cut the joint and reblast.

The area to be coated shall then be immediately heated to a temperature


SAES-H-201,
in accordance with the Powder Manufacturer's recommendation using
B2 Para. 8.3.4 &
induction heating coil. Preheating shall be accomplished by using
8.3.3
induction heating coils only.

Preheating temperatures shall be measured with contact pyrometers. SAES-H-201,


B3
Temperature crayons shall not be used. Para. 8.3.5

C FBE Powder Application:

As soon as the correct metal temperature has been reached, the induction
coil shall be removed from the welded joint area and the powder
application equipment placed in position. Powder application shall start SAES-H-201,
C1
immediately. Coating shall be applied before the surface temperature Para. 8.3.6
drops below the specified application temperature in the manufacturer
datasheet.

Saudi Aramco: Company General Use


# Saudi Aramco: Company General Use
#

The machine shall apply powder to a uniform rate, to a correct width


centered on the girth weld, to the coating thickness specified Table-5, in
the least number of passes possible.
For APCS-104A, the DFT Range (μm) is 350-525 SAES-H-201,
C2
For APCS-104B, the DFT Range (μm) is 575-750 Para. 8.3.6.1
For APCS-104C, the DFT Range shall be as per CMR (Coating
Manufacturer’s Recommendation)

Care shall be taken to prevent the spray head, braces or hoses, etc., from SAES-H-201,
C3
dragging on the ground during application operations. Para. 8.3.6.2

Dirt or other deleterious foreign material shall not contaminate the powder SAES-H-201,
C4
coated area during application and curing stages. Para. 8.3.6.2

Each batch of FBE coating must be tested and certified by the


SAES-H-201,
C5 Manufacturer in accordance with the requirement of Table 1. Vendor shall
Para. 6.11
conduct the same tests to verify compliance with the requirements.

D Visual Inspection:

The quality of cure shall be checked on the first 5 joints of the job and
every 20 joints thereafter, by maintaining a MEK soaked pad in contact
with the coating surface for one minute and then rubbing vigorously for 15 SAES-H-201,
D1
seconds. Para. 9.2.3
There shall be no softening of the coating or substantial color removal
from the coating.

SAES-H-201,
D2 The finished coating shall have a uniform, glossy appearance.
Para. 9.2.4

The finished coating shall be free of coating defects such as holidays, fish SAES-H-201,
D3
eyes, lumps, dry spray, sags & runs. Para. 9.2.4
The Inspector shall verify that the surface preparation requirements of
SAES-H-201, paragraph 8.2 are met prior to the commencement of SAES-H-201,
D4 preheating. Para. 9.2.1

Coating overlap shall be within the thickness specified in 09-SAMSS-089


for external FBE Coating. SAES-H-201,
D5
Para. 9.2.4

E Dry Film Thickness (DFT) measurement:

A minimum number of 8 readings shall be taken on each field joint


coating, 4 readings in each side, to verify compliance with the thickness
requirement in Table-5.
SAES-H-201,
E1 For APCS-104A, the DFT Range (μm) is 350-525
Para. 9.2.2
For APCS-104B, the DFT Range (μm) is 575-750
For APCS-104C, the DFT Range shall be as per CMR (Coating
Manufacturer’s Recommendation)

Thickness checks shall be made on each coated weld joint using an


approved, correctly calibrated dry film thickness gauge (e.g., Microtest, SAES-H-201,
E2
Elcometer or equivalent). The instrument shall be calibrated in Para. 9.2.2
accordance with SSPC-PA2.

F Holiday Testing and Destructive Testing


100% of the coated girth weld surface area shall be holiday detected,
inspected, and repaired in accordance with the procedures and equipment
SAES-H-201,
specified in 09-SAMSS-089 for external FBE Coating. Holiday detection
Para.9.3.1 &
shall not be conducted if the surface temperature of the coated girth weld
F1 para.
area exceeds 80°C.
9.3.2

Saudi Aramco: Company General Use


# Saudi Aramco: Company General Use
#

All holidays, imperfections, and damaged areas are carefully


identified and marked with a waterproof marker. All markings shall be
SAES-H-201,
sufficiently distant from the area to be repaired to allow surface
F2 para. 9.3.2
preparation and coating application without being a detriment to the
adhesion of the repair coating. This procedure is applicable for external
coating

Coating adhesion test is conducted as follows:


A) Using a sharp knife with a narrow width blade, make two,
approximately 13-mm long incisions through to the metal substrate to form
an X in accordance with ASTM D6677.
SAES-H-201,
B) Starting at the intersection of the X, attempt to force the coating from
Para. 9.4.1
F3 the steel substrate with the knife point
&
C) Refusal of the coating to peel constitutes a PASS.
Para. 9.4.2
D) Partial or complete adhesion failure between the
coating and the metal substrate constitutes a failure. Cohesive failure
caused by voids in the coating leaving a honeycomb structure on the
specimen surface also constitutes failure.

If the coating fails adhesion test adjacent field girth weld areas shall also
be tested until acceptable coatings are found on both sides of the
defective coating.
SAES-H-201,
F4 The defective coatings shall all be completely removed and the areas
Para. 9.4.4
recoated. At least one of the repaired areas shall be re-inspected, and the
subsequent inspection frequency shall be as given in SAES-H-201, Para
9.4.3 (as stated in this SAIC, item# F5 below)

The Adhesion test is performed once every hour. When three consecutive
SAES-H-201,
F5 tests are successful, the frequency shall be reduced to once every two
Para. 9.4.3
hours.

G Repairs

All holidays, imperfections, and damaged areas are carefully identified SAES-H-201,
G1
and marked with a waterproof marker. para. 9.3.2

Girth welds showing more than 3 holidays shall be completely blasted off SAES-H-201,
G2
and the area recoated. Para. 9.5.1

The Pipe surface to be recoated shall be cleaned to remove all dirt and
damaged or disbonded coating using abrasive blasting or other approved
and suitable means. SAES-H-201,
G3
The edges of the original coatings shall be "feathered out" approximately Para. 9.5.2
50 mm around the specific area to be
coated, and all dust wiped off before applying the patch coating.

To repair holidays in external girth weld coating, two part epoxy should be SAES-H-201,
G4
used in accordance with the coating manufacturer’s requirement. Para. 9.5.4

Patch Repair areas are 100% holiday tested applying procedures used for
SAES-H-201,
G5 original coating (Refer to F1 above) and found acceptable, results
Para 9.5.5
recorded on SATR-H-008
Remarks:

REFERENCE DOCUMENTS:
1. SAES-H-201: General Spec for External and Internal FBE Coatings of Pipeline Field Girth Welds (31 May 2018)
2. SAES-H-001: Coating Selection & Application Requirements for Industrial Plants & Equipment, (23 May 2019).
3. SAEP-316: Performance Qualification of coating personnel (31 July 2016)
4. SAES-H-200: Storage, Handling and Installation of Externally Coated Pipe (28 May 2018)

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

Saudi Aramco: Company General Use


# Saudi Aramco: Company General Use
#

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED